HomeMy WebLinkAbout20251002Staff Comments.pdf RECEIVED
October 02, 2025
ERIKA K. MELANSON IDAHO PUBLIC
DEPUTY ATTORNEY GENERAL UTILITIES COMMISSION
IDAHO PUBLIC UTILITIES COMMISSION
PO BOX 83720
BOISE, IDAHO 83720-0074
(208) 334-0320
IDAHO BAR NO. 11560
Street Address for Express Mail:
11331 W CHINDEN BLVD, BLDG 8, SUITE 201-A
BOISE, ID 83714
Attorney for the Commission Staff
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
IN THE MATTER OF IDAHO POWER )
COMPANY'S APPLICATION FOR ) CASE NO. IPC-E-25-25
APPROVAL OF THE CAPACITY )
DEFICIENCY TO BE UTILIZED FOR )
AVOIDED COST CALCULATIONS ) COMMENTS OF THE
COMMISSION STAFF
COMMISSION STAFF ("STAFF") OF the Idaho Public Utilities Commission
("Commission"), by and through its attorney of record, Erika K. Melanson, Deputy Attorney
General, submits the following comments.
BACKGROUND
On July 25, 2025, Idaho Power Company("Company") applied to the Commission
requesting an order approving the capacity deficiency period with a first deficit occurring in June
2027 to be utilized for the Company's Public Utility Regulatory Policy Act ("PURPA") avoided
cost determinations under the Company's Incremental Cost Integrated Resource Plan("ICIRP")
and Surrogate Avoided Resource ("SAR")methods.
The Commission has established a SAR methodology and an ICIRP methodology to
calculate avoided cost rates for qualifying facilities ("QFs"). Order No. 32697. Under both
STAFF COMMENTS 1 OCTOBER 2, 2025
methods, a new QF receives capacity payments only after the applicable capacity deficit date is
reached. Order No. 33159. The capacity deficiency period is determined through the Integrated
Resource Plan ("IRP")planning process and is submitted to the Commission in a proceeding
separate from the IRP docket. Order No. 32697. The capacity deficit date determined in the IRP
process is presumed to be correct as a starting point but will be subject to the outcome of the
capacity deficiency case. Id. Companies are required to file for an order from the Commission
approving the capacity deficiency period within thirty (30) days after each utility files its
respective IRP. Order No. 35810.
STAFF ANALYSIS
The first capacity deficiency date is determined when load with a planning reserve
margin exceeds the capacity of the Company's resources. The date establishes the time when
new QFs start receiving capacity payments. Staff has reviewed the load and resource inputs the
Company used to determine its capacity deficiency period in this case.
The Company states that it is not clear whether executed contracts not yet approved
should be included in the analysis. Application at 7. To clarify the confusion, Staff believes that
further explanations are needed regarding approvals of contracts and resources when determining
the capacity deficiency period. Specifically, Staff recommends that the Company file updated
capacity positions through a compliance filing that includes the resources, as of the compliance
filing, specified below:
• Include all executed contracts for non-PURPA contracts that do not require pre-
approval;
• If a resource requires a Certificate of Public Convenience and Necessity ("CPCN"),
only include it if it has received a CPCN; and
• Only include approved PURPA projects.
Furthermore, Staff recommends that the Company use exit dates that reflect the original
technical useful lives of Jim Bridger units 3 and 4 instead of the dates proposed by the Company.
Load Forecast
The Company uses the 701h-percentile peak load forecast to determine its capacity
deficiency period, which is the same percentile selected for reliability studies in the 2025 IRP.
STAFF COMMENTS 2 OCTOBER 2, 2025
Since the 701h-percentil peak load forecast results in the average Loss of Load Expectation that is
closest to the 0.1 event-days per year(Appendix D of 2025 IRP at 5), Staff believes it is
reasonable to use the 70th-percentile peak load forecast in this filing.
Resources
Staff believes the resources included in the Company's analysis are reasonable, except
the future resources that should be included and the exit dates that should be used for the Jim
Bridger units 3 and 4.
Contracts and Capacity Project Approvals
The Company includes resources that have not been approved in its analysis to determine
the capacity deficiency period, such as the Crimson Orchard Solar Power Purchase Agreement
and its Battery Energy Storage System Energy Storage Agreement (Case No. IPC-E-25-10), and
the Boise Bench Expansion and Hemingway Expansion battery storage facilities requiring a
CPCN (Case No. IPC-E-24-45). Staff recommends that the Company(1) include all non-
PURPA executed contracts that do not require pre-approval as of the compliance filing, (2) only
include approved CPCN projects as of the compliance filing, and (3) only include approved
PURPA contracts as of the compliance filing.1
Order No. 35834 states that approved contracts where pre-approval is necessary, or
executed contracts where pre-approval is unnecessary, should be included in determining the
capacity deficiency period. Although the Company typically files non-PURPA Power Purchase
Agreements and non-PURPA Energy Storage Agreements for pre-approval to gain higher
certainty of cost recovery, pre-approval for these types of contracts is not required by the
Commission(e.g., Avista Utilities and Rocky Mountain Power typically do not apply for pre-
approval of these types of contracts before these projects come online). Therefore, Staff
recommends that the Company include all executed non-PURPA contracts that do not require
pre-approval to determine the deficit date in a compliance filing. However, since Commission
authorization is required for PURPA projects and for resources that require a CPCN, Staff
' "Executed"means all the parties involved have signed the contract. "Approved"means the contract has been
approved by the Commission.
STAFF COMMENTS 3 OCTOBER 2, 2025
recommends that these resources only be included in the determination of the deficit date if they
are approved.
Jim Bridger 3 and 4
The Company assumes that Jim Bridger 3 and 4 will exit in 2030 in this case, the dates of
which are aligned with the accelerated depreciation schedules authorized by the Commission.
Order No. 35423 at 13. However, Staff believes that due to the remaining amount of uncertainty
that still exists regarding the timeframe for continued use of these two units, Staff recommends
that the operational exit dates used for determining the deficit date should reflect the original
technical useful lives of Jim Bridger units 3 and 4 until such time that the Company can
determine with a reasonable amount of certainty when these two units will cease providing
capacity to the Company's system.
In Case No. IPC-E-21-17, the Commission authorized accelerated depreciation schedules
that fully depreciate coal assets of Jim Bridger by December 31, 2030. Id. However, the dates
used to set depreciation schedules do not necessarily align with operational exit dates and can be
based on other factors. As the Commission said in its order related to its decision to accelerate
the depreciation schedule, "It is always our responsibility to balance the ratepayer's access to
affordable energy prices with the Company's right to recover its costs and earn a reasonable
return on its investments."Id. The Commission also noted"the uncertainty that remains with
respect to the Company's exit date from Bridger and the absence of any current plan to develop a
firm exit date."Id. Staff believes the uncertainty that existed in 2021 still remains. The
Company stated that the timeframe for continued operation of these units is still uncertain due to
"national policy and regulation, PacifiCorp and Idaho Power's developing needs, evolving costs,
studies, regulatory dockets, etc." Response to Staff Production Request No. 4.
STAFF RECOMMENDATION
Staff recommends that the Company file updated capacity positions through a
compliance filing that includes the resources, as of the compliance filing, to reflect the following:
• For non-PURPA contracts that do not require pre-approval, include all executed
contracts;
• For resources that require a CPCN, only include projects that have received a CPCN;
STAFF COMMENTS 4 OCTOBER 2, 2025
• For PURPA projects, only include Commission-approved PURPA projects; and
• Use exit dates that reflect the original technical useful lives of Jim Bridger units 3 and
4.
Respectfully submitted this 2nd day of October 2025.
LnA,,&J RAA_
Erika K. Melanson
Deputy Attorney General
Technical Staff: Yao Yin
I:\Utility\UMISC\COMMENTS\IPC-E-25-25 Comments.docx
STAFF COMMENTS 5 OCTOBER 2, 2025
CERTIFICATE OF SERVICE
,J
I HEREBY CERTIFY THAT I HAVE THIS DAY OF OCTOBER 2025,
SERVED THE FOREGOING COMMENTS OF THE COMMISSION STAFF, IN CASE
NO. IPC-E-25-25, BY E-MAILING A COPY THEREOF TO THE FOLLOWING:
Idaho Power Company:
DONOVAN E. WALKER
MEGAN GOICOECHEA ALLEN
CAMILLE CHRISTEN
IPC DOCKETS
IDAHO POWER COMPANY
1221 WEST IDAHO STREET (83702)
PO BOX 70
BOISE ID 83707-0070
E-MAIL:
dwalkercidahopower.eom
m goico echeaallencidahopower.com
cchristencidahopower.com
energycontractscidahopower.com
dockets c;idahopower.com
IdaHydro:
C. TOM ARKOOSH
NICHOLAS J. EREKSON
ARKOOSH LAW OFFICES
913 W. RIVER STREET, SUITE 450
P.O. BOX 2900
E-MAIL:
tom.arkoosh c arkoosh.com
nick.erekson(cL arkoosh.com
erin.cecilcarkoosh.com
PATRICIA JORD , SECRETARY
CERTIFICATE OF SERVICE