HomeMy WebLinkAbout20250716Intervention_Order_No_36673.pdf Office of the Secretary
Service Date
July 16,2025
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
IN THE MATTER OF COMMISSION ) CASE NO. GNR-E-25-02
STAFF'S APPLICATION FOR APPROVAL )
OF A FILING PROCESS FOR WILDFIRE )
MITIGATION PLANS ) ORDER NO. 36673
Kootenai Electric Cooperative, Inc. ("KEC") petitioned to intervene in this case on June
30, 2025, and Rocky Mountain Power, a Division of PacifiCorp ("Rocky Mountain Power")
petitioned to intervene in this case on July 2, 2025. These petitions were filed pursuant to Idaho
Public Utilities Commission Rules of Procedure 71-75, IDAPA 31.01.01.071-.075.
FINDINGS OF FACT
We find that no party timely opposed these Petitions to Intervene.
We further find that based on the pleadings and other documents filed in this case,
intervention by these parties would serve the purposes of intervention as described by Rule 74 and
should be granted.
ORDER
IT IS THEREFORE ORDERED that the Petition to Intervene filed by KEC is granted.
IT IS THEREFORE ORDERED that the Petition to Intervene filed by Rocky Mountain
Power is granted.
IT IS FURTHER ORDERED that all parties comply with all rules of the Commission
including Rules 71-75, and 222-223, IDAPA 31.01.01.071-.075, .222-.223.
IT IS FURTHER ORDERED that all parties in this proceeding serve all documents
hereafter filed in this matter on all parties of record. These Intervenors are represented by the
following for purposes of service:
Kootenai Electric Cooperative, Inc.:
Michael G. Andrea Thomas Maddalone
General Counsel for KEC Safety Director for KEC
9014 W. Lancaster Rd. 9014 W. Lancaster Rd.
Rathdrum, ID 83858 Rathdrum, ID 83858
mandreagkec.com tmaddalone(a),kec.com
ORDER NO. 36673 1
Rocky Mountain Power:
Joe Dallas Mark Alder
Senior Attorney Idaho Regulatory Affairs Manager
Rocky Mountain Power Rocky Mountain Power
825 NE Multnomah, Suite 2000 1407 West North Temple, Suite 330
Portland, OR 97232 Salt Lake City, UT 84116
„joseph.dallasg]2acificop2.com mark.aldergpacificorp.com
Data Request Response Center
datarequestgpacific orp.com
IT IS FURTHER ORDERED that parties comply with Order No. 35375, issued April 21,
2022. Generally, all pleadings should be filed with the Commission electronically and will be
deemed timely filed when received by the Commission Secretary.See Rule 14.02. Service between
parties should continue to be accomplished electronically when possible. However, voluminous
discovery-related documents may be filed and served on CD-ROM or a USB flash drive.
DONE by Order of the Idaho Public Utilities Commission at Boise, Idaho this 16t'day of
July 2025. /
G
Gt�
EDWARD LODGE, PRESIDEN
4
�N R. HAMMOND JR., COMMISSIONER
'ff1
AYN HA E, COMMISSIONER
ATTEST:
I /Ma4�
Mo arr a z
Commission Secretary
IALega1\ELECTRIC\GNR-E-25-02_WMP Process\orders\GNRE2502_KEC_PAC_at.docx