HomeMy WebLinkAbout20250623Application for Intervenor Funding.pdf RECEIVED
Eric L. Olsen(ISB#4811) June 23, 2025
ECHO HAWK& OLSEN, PLLC IDAHO PUBLIC
505 Pershing Ave., Ste. 100 UTILITIES COMMISSION
P.O. Box 6119
Pocatello, Idaho 83205
Telephone: (208) 478-1624
Facsimile: (208)478-1670
Email: elo(a)echohawk.com
Attorney for Intervenor Idaho Irrigation Pumpers Association, Inc.
BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
IN THE MATTER OF IDAHO POWER CASE NO. IPC-E-25-03
COMPANY FOR APPROVAL OF THE
NORTH VALMY POWER PLANT APPLICATION FOR INTERVENOR
NATURAL GAS CONVERSION FUNDING OF THE IDAHO
AGREEMENT WITH NV ENERGY IRRIGATION PUMPERS
ASSOCIATION,INC.
COMES NOW the Idaho Irrigation Pumpers Association, Inc. ("IIPA"), by and through
counsel of record, Echo Hawk & Olsen, PLLC, and hereby respectfully makes application to the
Idaho Public Utilities Commission ("Commission") for intervenor funding, pursuant to Idaho
Code § 61-617A and IDAPA §§ 31.01.01.161 through .165, in this case, as follows:
(A) A summary of the expenses that the IIPA request to recover broken down into legal
fees, witness fees and other costs and expenses is set forth in Exhibit A attached hereto and
incorporated by reference. The expenses and costs incurred by the IIPA set forth in Exhibit A are
reasonable in amount and were necessarily incurred. The expenses and costs were incurred in
participating in the case. Without incurring these expenses and costs, IIPA would not have been
able to fully participate in this matter.
(B) The IIPA's Counsel, Eric L. Olsen of Echo Hawk & Olsen ("Mr. Olsen") and its
Expert witnesses Lance D. Kaufman, Ph.D. ("Dr. Kaufman") and Deborah Glosser, PhD. ("Dr.
APPLICATION FOR INTERVENOR FUNDING OF THE IDAHO IRRIGATION PUMPERS ASSOCIATION,INC.—
Page 1
CASE NO.IPC-E-25-03
Glosser")participated in Idaho Power Company's ("IPC")North Valmy Power Plant Natural Gas
Conversion Agreement with NV Energy case("Valmy").Mr. Olsen,Dr.Kaufman and Dr. Glosser
prepared and served written discovery; reviewed and analyzed the various parties' positions.
Dr. Glosser's review in this case raised concerns that the Valmy repower may not be the
least cost, least risk resource to meet IPC's needs because the project was not fairly evaluated
against new and more efficient simple cycle or combined cycle combustion turbines or other
shorter term and potentially less expensive alternatives. Dr. Glosser's review focused on: (1) the
issues with IPC's modeling methodology; (2)the failure to properly account for possible cost
overruns and static cost inputs with capital and O&M cost modeling; (3)the lack of comparative
scoring with alternative projects; and(4)possibility of stranded utilization risk. These factors
could result in significant ratepayer exposure to increased costs for this resource. As such, IIPA
recommended that the CPCN for the Valmy repower should not be approved. In the event the
Commission grants the CPCN, IIPA recommended that the Commission impose cost
containment measures in the form of a capital cost cap; stranded cost safeguards; and utilization
reporting to protect ratepayers from cost overruns or poor utilization.
(C) The costs described in Exhibit A constitute a financial hardship for the IIPA. The
IIPA is an Idaho nonprofit corporation qualified under I.R.C. § 501(c)(5) representing farm
interests in electric utility rate matters affecting farmers in southern and central Idaho. The IIPA
relies solely upon dues and contributions voluntarily paid by members, together with intervenor
funding, to support its activities. Each year mailings are sent to approximately 7,000 Idaho
Irrigators (approximately one-third in the IPC service area and the remainder in IPC's service
area), soliciting annual dues. IIPA recommends members make voluntary contributions based on
APPLICATION FOR INTERVENOR FUNDING OF THE IDAHO IRRIGATION PUMPERS ASSOCIATION,INC.—
Page 2
CASE NO.IPC-E-25-03
acres irrigated or horsepower per pump. Member contributions have been falling which is believed
to be attributable to increased operating costs and declining commodity prices.
From member contributions the IIPA must pay all expenses, which generally include
mailing expenses, meeting expenses, post office box, in addition to the expenses relating to
participation in matters before the Commission. The Executive Director, Amy McKoon, is the
only part-time paid contractor, receiving a retainer plus expenses for office space, office
equipment, and secretarial services. Other IIPA officers and directors are elected annually and
serve without compensation.
It has been and continues to be a financial hardship for the IIPA to fully participate in
important cases such as this one due to the time and expense that must be incurred to fully
participate in such a case. Because of the IIPA's financial constraints, participation in this case,
preparing to file testimony, and participating in the settlement negotiations has been focused and
prudent.
(D) IIPA's recommendations materially differed from Commission Staff s comments.
The IIPA recommended that the Commission should not grant the CPCN for the Valmy repower
project. The IIPA found that the Company failed to demonstrate that the project represents a least-
cost, least-risk resource. The IIPA identified possible cost overruns and O&M cost modeling
issues. The IIPA identified that IPC planned to utilize Valmy primarily to a peaking resource and
that IPC did not model whether it would be dispatched enough to recover its fixed costs. The IIPA
requested if approval is given that the Commission impose cost containment measures in the form
of a capital cost cap, stranded cost safeguards, and utilization reporting to protect ratepayers from
cost overruns and poor utilization.
APPLICATION FOR INTERVENOR FUNDING OF THE IDAHO IRRIGATION PUMPERS ASSOCIATION,INC.—
Page 3
CASE NO.IPC-E-25-03
(E) The IIPA's participation addressed issues of concern to the general body of users
or consumers on IPC's system in the recommended cost containment measures would benefit all
of IPC's customers.
(F) The IIPA represents the irrigation class of customers under Schedule 10 on IPC's
system.
Based on the foregoing, it is respectfully submitted that the IIPA is a qualifying intervenor
and should be entitled to an award of costs of intervention in the maximum amount allowable
pursuant to Idaho Code § 61-617A and IDAPA §§ 31.01.01.161 through .165.
DATED this 23rd day of June, 2025.
EC WK& OLSEN
ERIC L. OLSEN
APPLICATION FOR INTERVENOR FUNDING OF THE IDAHO IRRIGATION PUMPERS ASSOCIATION,INC.—
Page 4
CASE NO.IPC-E-25-03
CERTIFICATE OF SERVICE
I HEREBY CERTIFIY that on this 23rd day of June, 2025, I served a true, correct and
complete copy of the Idaho Irrigation Pumpers Association, Inc.'s Application for Intervenor
Funding to each of the following, via the method indicated below:
Monica Barrios-Sanchez, Commission Secretary ❑ U.S. Mail
Chris Burdin, Deputy Attorney General ❑ Hand Delivered
Idaho Public Utilities Commission ❑ Overnight Mail
P.O. Box 83720 ❑ Telecopy(Fax)
Boise, ID 83720-0074 ® Electronic Mail (Email)
secretM(iDj2uc.idaho.gov
chris.burdingpuc.idaho.gov
Donovan Walker ❑ U.S. Mail
Megan Goicoechea Allen ❑ Hand Delivered
Tim Tatum ❑ Overnight Mail
Idaho Power Company ❑ Telecopy(Fax)
1221 W. Idaho Street (83702) ® Electronic Mail (Email)
P.O. Box 70
Boise, ID 83707
dwalker(a,idahopower.com
mgoicoecheaallengidahopower.com
dockets(&idahopower.com
ttatumgidahopower.com
Lance Kaufman, Ph.D. ❑ U.S. Mail
2623 NW Bluebell Place ❑ Hand Delivered
Corvallis, OR 97330 ❑ Overnight Mail
lancegae isg insi h� ❑ Telecopy(Fax)
® Electronic Mail (Email)
Ed Jewell ❑ U.S. Mail
Jessica Harrison ❑ Hand Delivered
Deputy City Attorneys ❑ Overnight Mail
Boise City Attorney's Office ❑ Telecopy(Fax)
150 N. Capitol Blvd. ® Electronic Mail (Email)
Boise, ID 83701
BoiseCityAttorneygcityofboise.org
eiewell(i cityofboise.org
j harrisonncityofboise.org
APPLICATION FOR INTERVENOR FUNDING OF THE IDAHO IRRIGATION PUMPERS ASSOCIATION,INC.—
Page 5
CASE NO.IPC-E-25-03
Katie O'Neil ❑ U.S. Mail
Energy Program Manager ❑ Hand Delivered
Boise City Dept. of Public Works ❑ Overnight Mail
150 N. Capitol Blvd. ❑ Telecopy(Fax)
Boise, ID 83701 ® Electronic Mail (Email)
koneil(ir cityofboise.com
Austin Rueschhoff ❑ U.S. Mail
Thorvald A. Nelson ❑ Hand Delivered
Austin W. Jensen ❑ Overnight Mail
Kristine A.K. Roach ❑ Telecopy(Fax)
Holland& Hart, LLP ® Electronic Mail (Email)
Micron Technology, Inc.
555 17th Street Suite 3200
Denver, CO 80202
darueschhoff(c�hollandhart.com
tnelson(a,hollandhart.com
awj ensen(&hollandhart.com
karoachkhollandhart.com
aclee(a,hollandhart.com
ERIC L. OLSEN
APPLICATION FOR INTERVENOR FUNDING OF THE IDAHO IRRIGATION PUMPERS ASSOCIATION,INC.—
Page 6
CASE NO.IPC-E-25-03
EXHIBIT A
Expert Witnesses: Deborah Glosser and Lance Kaufman,Expenses:
1. Witness Fees: 23.35 Hours @ $250= $ 5,837.50
Sub Total: $ 5,837.50
Legal Expenses:
1. Paralegal Fees: 5 Hours @ $155 = $ 775.00
2. Legal Fees Eric L. Olsen: 6.2 Hours @ $250 = $ 1,550.00
3. Soft Costs (Copies/Legal Research) $ 10.35
Sub Total: $ 2,335.35
Grand Total: $ 8,172.85
APPLICATION FOR INTERVENOR FUNDING OF THE IDAHO IRRIGATION PUMPERS ASSOCIATION,INC.—
Page 7
CASE NO.IPC-E-25-03