HomeMy WebLinkAboutAvista 250610 IPUC Form 1 - Coeur d'Alene Field IPUC Pipeline Safety Inspection
Inspector(s): Perkins, Brooks, Galli Date(s): 250609,250610, 250612
Company/Owner: Avista Utilities Unit/OPID: 31232
Standard: ® Training: ❑ TIMP/DIMP: ❑ OQ: ❑
Incident: ❑ Damage Prevention: ❑ Drug &Alcohol: ❑ Inspection Days: 7.5
Inspection Summary
June 9, 2025: (3.0 Standard) (Galli 1.0) (Brooks 1.0) (Perkins 1.0)
IPUC inspectors Perkins, Brooks and Galli traveled to Coeur d'Alene, Idaho to inspect field installed
operating equipment for the Avista Coeur d'Alene inspection unit.
June 10, 2025: (1.5 Standard) (Galli 0.5) (Brooks 0.5) (Perkins 0.5)
Met with Avista company representatives in the Coeur d'Alene District Office for a briefing, reviewed
welding records, past year work orders.
Ten regulator stations were inspected for relief operation, lock-up, general condition of the station
including pipe-to-soil wrap, and cathodic protection. Three rectifiers, eight carrier-to-casings and fifteen
valves were also inspected.
Wrote inspection report, completed audit forms: PHMSA IA question set with OQ protocol 9,
IPUC Form 1, Post-Inspection Preliminary Written Findings and attached inspection documents.
Discrepancies:
None.
June 12, 2025: (3.0 Standard) (Galli 1.0) (Brooks 1.0) (Perkins 1.0)
IPUC inspectors Perkins, Brooks and Galli traveled back to Boise, ID.
Corrective Action Required: ❑ Yes N No Compliance Letter#: NA
Follow Up Required: ❑ Yes N No By Date: NA
Lead Inspector: Galli/Perkins Date: Reviewer: Brooks Date:
250616
Signature: Z ' Signature: �506 l�O
IPUC Form 1 Rev. 12/11/2024