Loading...
HomeMy WebLinkAbout20250611Staff Comments.pdf RECEIVED June 11, 2025 ADAM TRIPLETT IDAHO PUBLIC DEPUTY ATTORNEY GENERAL UTILITIES COMMISSION IDAHO PUBLIC UTILITIES COMMISSION PO BOX 83720 BOISE, IDAHO 83720-0074 (208) 334-0318 IDAHO BAR NO. 10221 Street Address for Express Mail: 11331 W CHINDEN BLVD, BLDG 8, SUITE 201-A BOISE, ID 83714 Attorney for the Commission Staff BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION IN THE MATTER OF IDAHO POWER ) COMPANY'S APPLICATION FOR A ) CASE NO. IPC-E-24-45 CERTIFICATE OF PUBLIC CONVENIENCE ) AND NECESSITY FOR TWO BATTERY ) STORAGE FACILITIES ) REDACTED COMMENTS OF THE COMMISSION STAFF COMMISSION STAFF ("STAFF") OF the Idaho Public Utilities Commission ("Commission"), by and through its Attorney of record, Adam Triplett, Deputy Attorney General, submits the following comments. BACKGROUND In June 2023, the Company issued a Request for Proposal ("RFP") for 2026 resources for its identified capacity deficit in 2026, following the Oregon Procurement rules. In 2024, the Company filed two cases for approval of resources with the Commission to help meet its projected capacity deficit of 236 megawatts ("MW") in 2026. In its comments filed in Case No. IPC-E-24-12, Staff believed the Market Purchase Agreement was one of the least-cost least-risk resources selected in the RFP process and STAFF COMMENTS 1 June 11, 2025 recommended approval.' In Final Order No. 36309, the Commission approved the Market Purchase Agreement with capacity up to 200 MW. In its comments in Case No. IPC-E-24-16, Staff was not confident that the selected 150 MW Boise Bench BESS project was least-cost. The Company's least-cost portfolio analysis was a combination of three resources to fill the 2026 capacity deficit; however, the identified third resource was no longer feasible. Therefore, Staff recommended approval of the Certificate of Public Convenience and Necessity("CPCN") due to the capacity need and cost caps on the project due to the uncertainty of the project being least-cost. 2 In Final Order No. 36389, the Commission approved the request for a CPCN for the 150 MW Boise Bench BESS; however, the Commission did not order cost caps for the project. The Company's two approved resources did not fulfill the total identified 2026 capacity deficit of 236 MW. The Company anticipated filing a third case for Commission approval for the Savion Solar plus BESS project as identified in the 2026 Final Short List("FSL"). However, due to permitting issues, the resource was no longer feasible and would not be online by June 1, 2026. Application at 8. The Company returned to its Initial Short List("ISL") and the FSL from the 2026 RFP and was not able to secure a resource for the remaining deficit. This led the Company to negotiate outside the 2026 RFP bids due to the time constraint of the capacity deficit. On December 27, 2024, Idaho Power Company applied for a CPCN to acquire new dispatchable energy storage that would provide a total of 100 MW of incremental nameplate capacity through two battery energy storage system(`BESS")projects: (1) the Hemingway Incremental 50 MW BESS ("Hemingway Incremental"), and(2)the Boise Bench 50 MW Expansion BESS ("Bench Expansion") . On February 3, 2025, the Commission issued a Notice of Application and Notice of Intervention Deadline, setting a deadline for interested parties to intervene. Order No. 36454. The Industrial Customers of Idaho Power, Idaho Irrigation Pumpers Association, Inc., and Micron Technology, Inc. intervened. Order Nos. 36485 & 36492. 'IPC-E-24-12 Staff Comments at 4-5. 2 IPC-E-24-16 Staff Comments at 4-5. STAFF COMMENTS 2 June 11, 2025 STAFF ANALYSIS Staff has reviewed the Company's Application, responses to Production Requests and supporting documentation. First, Staff believes the 50 MW Hemingway Incremental project is cost effective and will help meet the 2026 capacity deficit. Therefore, Staff recommends the Commission grant a CPCN for this project. Second, Staff believes the Company will be resource sufficient in 2026 without the need for the 50 MW Bench Expansion project given implementation of the 50 MW Hemingway Incremental project, the previously approved 150 MW Boise Bench BESS resource, and the initial overbuild planned for both projects. In addition, due to currently known import tariff increases, Staff believes the 50 MW Bench Expansion project may not be cost-effective and could put ratepayers at financial risk without significant effort to mitigate the cost. Therefore, Staff does not recommend a CPCN for the Bench Expansion project. Third, Staff recommends that the Company explore ways to mitigate the increased cost of the 150 MW Boise Bench BESS project given the import tariffs. Finally, Staff recommends that the Company keep the Commission appraised of the tariff situation and the delivery status of the batteries for the overall Boise Bench BESS project. Need for Capacity After receiving Commission approval of the Market Purchase Agreement and the 150 MW Boise Bench BESS, and the fall through of the Savion project, the Company updated its capacity position resulting in a 41 MW capacity deficit, which the Company is now seeking to fill with two proposed BESS projects. Ellsworth Direct at 10-11. The update also included (1) an updated load forecast, (2) inclusion of a wildfire risk factor, (3) an updated generation unit outage schedule, and(4) the acceleration of the commercial operation date of the PVS 2, LLC, solar facility. Staff reviewed the new wildfire risk factor that was utilized in the calculation of the updated capacity deficit. The Company stated, "Incorporating these wildfire risk inputs into the RCAT model impacts the outage generation table used to calculate the Loss of Load Expectation, thus impacting the annual capacity position calculation." See Company's response to Production Request No. 1. Staff reviewed the Company's workpapers provided in its response to Production Request Nos. 1 and 20 and believes that the wildfire risk factor is a reasonable STAFF COMMENTS 3 June 11, 2025 input into the Company's assessment of its capacity position. Additionally, Staff reviewed and re-validated the Company's capacity deficit with its supporting workpapers.3 Staff concludes that the update to assumptions and inputs are reasonable and that a 41 MW capacity deficit in 2026 is valid. Below is a summary table of previous cases which identified a 2026 capacity deficit and how each resource selected has contributed to reducing the deficit. The last row of the table displays the capacity deficit calculated in December 2024, and how the two proposed BESS projects will reduce the capacity deficit. Table 1: Summary of Capacity Position Changes 2026 Capacity Capacity Document Load& Resource Position Position After Changed Assumptions Before the Project the Project 2023 IRP(Sep'23) B2H online Jun '26 (22) MW N/A 2023 IRP B2H online Nov'26 (356) MW N/A IPC-E-24-12 B2H online Nov'26 (236) MW (186) MW 2026 20OMW Powerex Updated load forecast Market Purchase CBM =0 MW year-round Valmy 261 MW online in '26 IPC-E-24-16 No change. Concurrent (186) MW (120) MW 2026 15OMW Boise BESS analysis as IPC-E-24-12. IPC-E-24-45 B2H online Nov'27 (41) MW +7 MW 2026 2 x 50MW BESS Updated load forecast extensions Wildfire risk factor Delay hydro shutdown Accelerate PVS2 to May 2026 50MW Summer Firm Energy The Selected BESS Projects Staff evaluated the selection of the 50 MW Hemingway Incremental and 50 MW Bench Expansion projects based on the information contained in the initial filing. The Company had to negotiate outside of the RFP to fmd additional resources to fill its anticipated 2026 capacity deficit. After reviewing the remaining available alternatives of projects that were included in the Company's RFP shortlists and with the 41 MW capacity deficit, Staff believed the two selected 3 Company's response to IIPA's Production Request No.25—Attaclunent. STAFF COMMENTS 4 June 11, 2025 projects would be the most feasible solutions to resolve the 2026 capacity deficit, for the reasons below: 1. Several of the projects that were included in the Company's ISL and FSL of the 2026 RFP were no longer feasible due to a range of issues preventing the projects from meeting the required commercial operation date ("COD"); 2. The inability to find additional short-term market purchases that would allow later implementation of projects on the shortlist that could not meet the COD; and 3. The Company's ability to develop a solution to meet the 2026 deficit through a combination of purchasing power from the market and cost-effectively expanding the capacity of BESS projects that are already in operation and/or currently being implemented with Commission authorization. As mentioned in the Background section of these comments, the Savion Project, one of the most promising FSL projects, was no longer feasible due to a denied permit. Staff then discovered that other projects on both the ISL and the FSL were no longer viable because of the inability for them to meet the desired COD in time to satisfy the 2026 capacity deficit or lack of ability to interconnect to the system. Application at 8 and response to Production Request No. 9. Because of the lack of options, Staff also investigated whether the Company could acquire short-term market purchases, bridging the time gap allowing projects that could not meet the required COD to be implemented later. As mentioned earlier, to meet the 2026 capacity deficit, a 200 MW market purchase was selected through the RFP process and the Commission approved it through Order No. 36309. The Company did find an additional 50 MW market purchase opportunity for the summer months of 2026 to be delivered to the Company's border. Ellsworth Direct Testimony at 14. However, the Company was not able to find any additional market purchases that could satisfy the remaining 2026 capacity deficit. See response to Production Request No. 11. Through the RFP, the Company received a bid for a 100 MW Hemingway BESS project, which was one of the top 10 most cost-effective resources to meet the 2026 deficit. This bid was an additional amount of BESS capacity to be added to the existing 116 MW BESS at the Hemingway substation. However, the Company initially screened out the bid because the existing generator interconnection agreement only allowed an additional 50 MW of available capacity. But due to the lack of feasible options, the Company was able to negotiate with a STAFF COMMENTS 5 June 11, 2025 battery supplier for a 50 MW project instead of the 100 MW project in the original bid. Hackett Direct Testimony at 26. The capacity deficit of 41 MW was not completely remedied by the addition of the 50 MW Hemingway Incremental. To acquire the remaining capacity needed, the Company negotiated additional equipment necessary to expand the Commission-approved 150 MW Boise Bench BESS by another 50 MW, for a total of 200 MW. 50 MW Hemingway Incremental Project The Company proposes to increase its Hemingway BESS capacity by building an additional 50 MW segment. The 50 MW Hemingway Incremental project will not be directly integrated with the existing 116 MW of Hemingway BESS; however, it will share the same point of interconnection. The Company plans to operate the Hemingway Incremental project and the existing BESS as a single asset.4 In the Company's response to Production Request No. 4, the estimated construction cost is-. Additionally, the Company estimates O&M cost for the Incremental 50 MW to be $1.5 million in the first year, increasing to $2 million over the remaining life of the project. The O&M costs evaluated considered long-term service agreements, warranties, and augmentation, as well as property taxes and property insurance.5 The Company executed a Long-Term Service Agreement("LTSA") for the 50 MW Hemingway Incremental project in December 2024. Hemingway Incremental Project Overbuild While the Company's modeling suggests that 50 MW of incremental Hemingway BESS capacity is sufficient to offset a portion of the Company's capacity deficit, the actual beginning- of-life capacity of the resource is slightly higher. In response to Production Request No. 8, the Company explains that to satisfy a contractual performance guarantee of 50 MW or 200 MWh for three years, the Hemingway Incremental project needs a beginning-of-life capacity of about 58 MW. This capacity can supply a total of 233 MWh across four hours. In the same response, the Company provided a table showing the expected energy of the resources over 20 years. Staff a See Company's response to Production Request No.2. 5 See Company's response to Production Request No.2. STAFF COMMENTS 6 June 11, 2025 believes that it is reasonable to include some amount of excess capacity to account for initial degradation. A reasonable amount of excess capacity allows for the measurement of actual degradation in the first years of operation and lead time to acquire additional capacity. Staff believes that the negotiated three-year capacity guarantee and associated beginning-of-life capacity satisfies these needs. Staff has verified the degradation assumptions and believes that 8 MW of additional capacity aligns with the three-year guarantee. Evaluation of Hemingway Incremental Project Staff determined the levelized cost of the 50 MW BESS project is less than the levelized cost of the original 150 MW Boise Bench BESS project that was approved through Order No. 36386. Furthermore, the levelized cost is lower than all the BESS projects that were selected for the initial and final RFP short-lists. It is for these reasons that Staff believes the project should provide incremental capacity at a cost comparable to the lowest cost BESS projects submitted for bid through the RFP. Staff believes that the 50 MW Hemingway Incremental project is cost effective and will help meet the 2026 capacity deficit. CPCNfor Hemingway Incremental Project Staff evaluated the Company's Application with Idaho Code § 61-526 and Rule 112. Staff believes the Company has met the requirements of Idaho Code § 61-526 showing (1) financial ability, (2) good faith of the Applicant, and(3)public need. Additionally, the Company provided documents through its Application and through discovery that Staff believes satisfies Rule 112. As Staff believes the project is cost effective and will contribute to the capacity position, Staff recommends the Commission grant a CPCN for 50 MW of BESS capacity through the Hemingway Incremental project. 50 MW Bench Expansion Project The Company proposes a 50 MW expansion to the already approved 150 MW Boise Bench BESS. The 50 MW Bench Expansion project is planned to be directly incorporated into the approved 150 MW Boise Bench BESS project to be a single 200 MW BESS project at the Boise Bench Substation and will share the same point of interconnection.6 6 See Company's response to Production Request No.2. STAFF COMMENTS 7 June 11, 2025 In the Company's response to Production Request No. 3, the initial total estimated construction cost of the 200 MW BESS was . The total 200 MW BESS cost estimate was approximately more than the cost estimate provided in IPC-E-24-16 for the 150 MW Boise Bench BESS. The cost of the 50 MW Bench Expansion alone was estimated to be-. However, as discussed below, the cost estimate for the 200 MW of BESS has been updated to include a higher import tariff, significantly increasing the project cost estimate. Staff discusses this cost change further in sections below. Additionally, the Company estimates O&M for the 50 MW Bench Expansion to be $l.4 million in the first year, increasing to $1.9 million over the remaining life of the project. The O&M costs consider long-term service agreements, warranties, and augmentation, as well as property taxes and property insurance. The Company is pursuing negotiations for an LTSA for the total 200 MW BESS at the Boise Bench substation. Tariff Risks On May 1, 2025, the Company reached out to Staff to discuss the financial impact of increased U.S. Government import tariffs on goods from China. The Company alerted Staff that the Boise Bench battery supplier,_, is a Chinese company and thus the product would be subject to the new 145% import tariff and estimated this would increase the total project price by approximately . See Company's response to Production Request No. 26. The Company did not explicitly state this concern with the Hemingway Incremental Project; therefore, Staff's analysis of tariff risks focused on the Boise Bench BESS 200 MW project. In addition to alerting Staff about tariff risks, the Company discussed five alternatives it was considering due to the increased project costs: See Company's response to Production Request No.2. STAFF COMMENTS 8 June 11, 2025 , which would leave the Company still needing additional resources to meet its capacity deficit. As discussed above, the Company has no alternative resources through the 2026 RFP and would need to look outside of it to secure additional resources. This would not be able to meet the identified capacity deficit in 2026. The Company concluded that alternative No. 4 was The Company indicated it favored alternative No. 5, Since May 5, 2025, there have been trade negotiations which have resulted in the import tariff being reduced to 30% for 90 days, effective May 14 through August 12, 2025.8 The Company has since decided to request - The Company estimated under the reduced tariff. See Company's response to Production Request No. 27. As this is an evolving situation, there is substantial financial risk to ratepayers due to the uncertainty of the resource cost. Cost Evaluation of the Boise Bench BESS The import tariff rates could affect the cost effectiveness of the Boise Bench BESS project. The Chinese supplier can deliver approximately. of the product during the 90-day period. However, there is a risk that the. of batteries that cannot be delivered in this timeframe may have a tariff rate much greater than the 30%rate, which could affect the economics of the project. Staff believes the uncertainty of higher import tariffs may keep this project from being cost-effective. Table 2 displays cost-estimate comparisons of the following: the original 150 MW Boise Bench BESS project filed in Case No. IPC-E-24-16, the cost of the 150 MW Boise Bench BESS with the 50 MW Bench Expansion project using the initial cost 8 Company's response to Production Request No.27.;see also Nick Edser,"Markets rise as US an dchina agree to slash tariffs,"BBC(May 12,2025),hitps://www.bbc.com/news/articles/czxOry7kdk5o. STAFF COMMENTS 9 June 11, 2025 estimate in this case, and the updated cost estimate with the new tariffs. As can be seen in the table, if 70% of the batteries are subject to a 145% tariff rate, the total cost of the full 200 MW of BESS capacity will increase from Table 2: Cost Estimate Comparisons PC-E-24-45 I PC-E-24-45 150 MW Boise Bench 150 MW Boise Bench Scenario IPC-E-24-16 BESS w/50 MW BESS w/50 MW Expansion Expansion (Tariff Assumed at Filing) (Current Tariff) Capacity 150 MW 200 MW 200 MW Percentage of Deliveries at Tariff o 0 0 100/ 100/ 30/ 70/ Rate Tariff Rate 0% 7.50% 30% 145% Manufacturer Supplied BESS Equipment Other Construction Costs Total Project Cost Project Cost: $/ MW Capacity Evaluation of the Boise Bench BESS As discussed earlier, Staff analyzed the Company's capacity position. Following the May 1, 2025, meeting with the Company, Staff inquired what the capacity position would be with and without the 200 MW Boise Bench BESS. In the Company's response to Production Request No. 24, the Company updated its capacity position again. Without the 200 MW Boise Bench BESS and the 50 MW Hemingway Incremental project included, the system has a 29 MW capacity deficit. With the 200 MW Boise Bench BESS and the 50 MW Hemingway Incremental project, the system has a surplus capacity of 46 MW. Although the Company has merged the two Boise Bench BESS capacities together in this case, the Commission has only provided a CPCN for 150 MW of BESS capacity. By linearly interpolating between these two points, Staff concludes that the 150 MW BESS would enable a surplus system capacity of about 27 MW. In other words, Staff believes the Company is likely able to maintain reliable service through 2026 with the already approved 150 MW Boise Bench STAFF COMMENTS 10 June 11, 2025 BESS without the 50 MW Bench Expansion. The table below depicts the capacity position in each scenario. Table 3: Updated Capacity Positions Load&Resource Capacity Position Document Changed Assumptions After the Project IPC-E-24-45 Resource Stack without (29)MW Production Request No. 200 MW Boise Bench BESS 24: All other resource Resource Stack with 200 +46 MW assumptions remained MW Boise Bench BESS the same as described in the Application Resource Stack with 150 +27 MW MW Boise Bench BESS The Company signed the supply agreement in July 2024 for 200 MW prior to Commission approval. The Commission only approved a Company CPCN for 150 MW BESS capacity at that point. At the time of Commission approval in Order No. 36389, the tariff circumstances were not known. However, m this case, tariff impacts to ratepayers are known and ratepayers would bear all the risk of additional cost increases. Staff is opposed to ratepayers paying for extra capacity length and bearing all the risk of increased tariffs. Therefore, Staff believes that the already approved 150 MW of Boise Bench BESS puts the Company into a capacity sufficient position for 2026 without the need for the additional 50 MW Bench Expansion. However, the Bench Expansion could be needed to fill deficits in 2027 and beyond, which can provide the Company with additional time to explore ways to minimize the cost, including some of the five alternatives that the Company presented to Staff on May 1, 2025. Furthe more, because the tariffs also have a significant effect on the cost of the 150 MW Boise Bench BESS project, Staff recommends that the Company explore ways to mitigate the cost of the tariffs. For example, because the infrastiuchue of a BESS is scalable and can be implemented in an incremental way, Staff recommends the Company explore ways to incrementally delay taking delivery of batteries to take advantage of potential more favorable trade conditions. This would include exploring the renegotiation of delivery delays with its battery supplier coupled with efforts to find other sources of capacity including, but not limited to, short-term market purchases, incremental demand response,potential short-term curtailment STAFF COMMENTS 11 June 11, 2025 contracts with large customers, and/or finding additional capacity from the Company's existing resources, to enable the delay. Staff further recommends that the Company be prepared to demonstrate that it has taken these and other possible steps to mitigate the cost to customers with documented analysis of the costs and risks of each potential effort. CPCNfor the Bench Expansion Project As mentioned above, there are substantial financial risks of the overall Boise Bench BESS project due to the uncertainty of the import tariffs. Additionally, Staff s analysis shows there is not a need in 2026 for the additional 50 MW Bench Expansion project. Because of these reasons, Staff does not recommend the Commission grant a CPCN for the 50 MW Bench Expansion project at this time. Staff is aware the Company faces continued load growth and has identified capacity deficits in 2027 and beyond, although the capacity positions change each time the Company's models are updated. Staff encourages the Company to evaluate all various options to resolve its deficits, including this resource if prices stabilize and become cost-effective. Staff also recognizes that the multi-year RFP process has proven to have significant challenges for the Company to acquire resources and is discussing this issue in Case No. GNR-E-25-01. Boise Bench Excess Capacity As described in further detail above, Staff believes that the entirety of the 50 MW expansion is not needed for 2026. However, should the Commission reject Staff's recommendation to deny the CPCN for the 50 MW Bench Expansion, Staff believes a portion of this project may be excessive beyond the requested capacity. Similar to the Hemingway Incremental project, the actual beginning-of-life capacity of the 50 MW Bench Expansion project is also slightly higher. In response to Production Request No. 7, the Company explains that to satisfy a contractual three-year performance guarantee for 200 MW or 800 MWh, the total Boise Bench BESS needs a beginning-of-life capacity of about 222 MW. Approximately 55 MW of this capacity is associated with the expansion. The total capacity can supply a total of 887 MWh across four hours. Approximately 221.7 MWh of this supply is associated with the expansion. STAFF COMMENTS 12 June 11, 2025 In the same response, the Company provided a table showing the expected energy of the resources over 20 years. This table shows that the expected energy of the Boise Bench BESS resource at the end of year three is approximately 829 MWh and does not drop below the guaranteed energy amount until after year five. Staff believes this indicates that the total Boise Bench resource may be overbuilt by 29 MWh or about 7 MW. Applying this degradation rate to the 55 MW of the expansion,beginning-of-life capacity suggests that the expansion may be excessively overbuilt by approximately 2 MW. Staff believes it is appropriate to include some amount of excess capacity to account for degradation during the first years of operation; however, excessive overbuild capacity is not needed to satisfy the capacity deficit identified in the Company's Application. Staff applied the $/MW levelized cost of the initial Boise Bench BESS project construction cost estimate to the 7 MW of expansion overbuild to estimate its value. Staff's calculation suggests that- of the total project cost is being incurred before needed. - of this amount is associated with the 50 MW expansion. These estimates are based on the Company's initial cost estimate; therefore, the impact of import tariffs may increase the value of the excess capacity. Future Recovery In its Application, the Company does not request ratemaking treatment for the two BESS additions. Generally, this is reasonable because a CPCN only grants the decisional prudence required to begin the projects and does not guarantee recovery of any project costs. Accordingly, Staff will review the prudence of all project costs in a future recovery proceeding. If the Commission grants a CPCN for the Bench Expansion project, the project costs incurred for any purpose beyond what is supported by the CPCN may not benefit from the decisional prudence of this filing. Specifically, should the Commission opt to approve the CPCN for the 50 MW Bench Expansion project, Staff believes that 2 MW of excess capacity for the expansion project is not needed to maintain capacity of the resource in the near term and that the associated expense of- should not be included when the Company initially seeks recovery. STAFF COMMENTS 13 June 11, 2025 BESS Fire Risk There are concerns about the fire risks that a BESS may pose. Staff believes that the risk of a BESS fire occurring is low, but the potential consequences if one does occur are high. On January 16, 2025, the largest BESS system in the world caught fire, the 750 MW Vistra system, located in Moss Landing, California.9 The fire caused the evacuation of 1,500 residents, continued burning for several days and 300 MW of BESS capacity was destroyed.'0 On October 2, 2023, the Company's Melba BESS caught fire,burning on and off until October 5, 2023.11 These are two of over 50 BESS fires that have occurred around the world since 2021. Over 30 additional large-scale battery fires (not associated with utility BESSs) have occurred during the same period.12 There are several factors that distinguish BESS fires from typical fires, which pose additional risks to ratepayers and the public. First, some BESS fires have started "spontaneously"due to an unknown internal failure allowing thermal runaway to the point of combustion. Second, once a BESS fire starts, it is extremely difficult to extinguish due to the intrinsic stored chemical energy. This means the fire may burn a long time and it is more likely to spread, extending the damage. Third, lithium-ion batteries emit toxic smoke, which is an immediate hazard to nearby people. Also, the toxic smoke residue presents a longer-term environmental hazard. Because of these unique hazards, a BESS fire presents meaningful risks to ratepayers, in the form of investment losses and damage liability. However, the Company has proposed reasonable steps to mitigate these risks. Staff agrees with the Company's assessment that codes and standards are rapidly evolving, and the risk of a battery fire is low and getting lower. Response to Production Request No. 12. Staff also notes that"[t]he Company has engaged with a nationally recognized consultant, Fire & Risk Alliance to support safety planning, design, and first responder training." Id. The Company also asserts that its installation design will include features to isolate battery units from one another to minimize the risk of fire spread. Id. Finally, the Company states that should a BESS be destroyed by fire, the Company has recourse to contract warranties and traditional insurance, which may mitigate the financial impact to ratepayers. Response to Production Request No. 14. 9 hit2s:Hctif.org/news/fire-largest-bess-us-led-evacuation-1500-residents-near-moss-landing-fire-left-burn-out 10 h!Ws:Hstora eg wiki.epri.com/index.php/Failure_Event_-_US,_CA,_Moss_Landing -_16_Jan_2025 "Response to Production Request No.13,Attachment at 3. 12 h!Ws:Hstora eg wiki.epri.com/index.php/BESS_Failure_Incident Database STAFF COMMENTS 14 June 11, 2025 Given these assurances by the Company, Staff believes that the risk to ratepayers from a BESS fire should be low; therefore, this type of resource is a reasonable option to meet system needs. However, Staff recommends that the Company continue to carefully evaluate the fire risk for this project and future BESS projects. STAFF RECOMMENDATION Staff recommends the Commission: 1. Grant a CPCN for the 50 MW Hemingway Incremental project to meet the 2026 capacity deficit; 2. Deny a CPCN for the 50 MW Bench Expansion project; 3. Direct the Company to explore ways to mitigate the cost of tariffs for the 150 MW Boise Bench BESS as discussed above; and 4. Direct the Company to keep the Commission appraised of the tariff situation and the delivery status of the batteries for the overall Boise Bench BESS project. Respectfully submitted this 1 1 th day of June 2025. Adam riplett Deputy Attorney General Technical Staff: Kimberly Loskot Jason Talford Matt Suess Seungjae Lee L•`Utility`UM ISC\COM M ENTS�I PC-E-24-45 Commcnts-Rodectcd.docx STAFF COMMENTS 15 June l 1, 2025 CERTIFICATE OF SERVICE I HEREBY CERTIFY THAT I HAVE THIS 1 1TH DAY OF JUNE 2025, SERVED THE FOREGOING REDACTED COMMENTS OF THE COMMISSION STAFF, IN CASE NO. IPC-E-24-45, BY E-MAILING A COPY THEREOF, TO THE FOLLOWING: DONOVAN E. WALKER TIM TATUM IDAHO POWER COMPANY IDAHO POWER COMPANY PO BOX 70 PO BOX 70 BOISE ID 83707-0070 BOISE ID 83707-0070 E-MAIL: dwalker a,idahopower.com E-MAIL: ttatum a idahopower.com dockets(a,idahopower.com Industrial Customers of Idaho Power: Industrial Customers of Idaho Power. Peter J. Richardson Dr. Don Reading Richardson Adams, PLLC 280 S. Silverwood Way 515 N. 271h St. Eagle, ID 83716 Boise, ID 83702 E-MAIL: dreading(i�mindspring.com E-MAIL: peter&richardsonadams.com Micron Technology, Inc.: Idaho Irrigation Pumpers Assn, Inc.: Austin Rueschhoff Eric L. Olsen Thorvald A. Nelson Echo Hawk & Olsen, PLLC Kristine A.K. Roach P.O. Box 6119 Holland & Hart, LLP 505 Pershing Ave., Ste. 100 555 171h St., Ste. 3200 Pocatello,ID 83205 Denver, CO 80202 E-MAIL: elo(w_ echohawk.com E-MAIL: darueschhoff(ct hollandhart.com tnelson u.hollandhart.com karoachQhol landhart.com aclee c,hollandhart.com Idaho Irrigation Pumpers Ass 'n, Inc.: Lance Kaufman, Ph.D. 2623 NW Bluebell Place Corvallis, OR 97330 E-MAIL: lance(a,aegisinsi hg t.com ZA .� PAT 4MIRDAN, S RETARY CERTIFICATE OF SERVICE