HomeMy WebLinkAbout20250410Decision Memo.pdf DECISION MEMORANDUM
TO: COMMISSIONER LODGE
COMMISSIONER HAMMOND
COMMISSIONER HARDIE
COMMISSION SECRETARY
COMMISSION STAFF
LEGAL
FROM: CHRIS BURDIN
DEPUTY ATTORNEY GENERAL
DATE: APRIL 10, 2025
SUBJECT: IN THE MATTER OF COMMISSION STAFF'S APPLICATION FOR
APPROVAL OF AN OVERSIGHT PROCESS FOR THE ACQUISITION
OF LARGE SUPPLY-SIDE ELECTRICAL RESOURCES; CASE NO.GNR-
E-25-01.
On March 31, 2025, Idaho Public Utilities Commission Staff("Staff') filed an application
("Application") with the Idaho Public Utilities Commission ("Commission") requesting that the
Commission modify its Request for Proposal ("RFP") oversight process. Application at 1.
STAFF RECOMMENDATION
Staff recommends that the Commission issue a Notice of Application and Notice of
Intervention Deadline establishing a 21-day intervention period.
COMMISSION DECISION
Does the Commission wish to issue a Notice of Application and Notice of Intervention
Deadline establishing a 21-day intervention period?
A�2, ; Z1,A.
Chris Burdin
Deputy Attorney General
I:Usgal\ELECTRIC\GNR-E-25-01\memos\GNRE2501_dec 1_cb.docx
DECISION MEMORANDUM 1