HomeMy WebLinkAbout20250410Decision Memo.pdf DECISION MEMORANDUM
TO: COMMISSIONER LODGE
COMMISSIONER HAMMOND
COMMISSIONER HARDIE
COMMISSION SECRETARY
COMMISSION STAFF
LEGAL
FROM: ERIKA K. MELANSON
DEPUTY ATTORNEY GENERAL
DATE: APRIL 10, 2025
SUBJECT: IN THE MATTER OF IDAHO POWER COMPANY'S APPLICATION FOR
ITS FIRST ANNUAL UPDATE TO THE EXPORT CREDIT RATE FOR NON-
LEGACY ON-SITE GENERATION CUSTOMERS FROM JUNE 1, 2025
THROUGH MAY 31, 2026, IN COMPLIANCE WITH ORDER NO. 36048;
CASE NO. IPC-E-25-15.
On April 1, 2025, Idaho Power Company ("Company") filed an application with the Idaho
Public Utilities Commission ("Commission") for an order authorizing the Company, in compliance
with Commission Order No. 36048, to implement the Export Credit Rate for non-legacy on-site
generation customers from June 1, 2025 through May 31, 2026, and to approve the Company's
corresponding proposed changes to Schedule 6, Residential Service On-Site Generation, Schedule 8,
Small General Service On-Site Generation, and Schedule 84, Large General, Large Power, and
Irrigation On-Site Generation Service. The Company requests a June 1, 2025, effective date.
STAFF RECOMMENDATION
Commission Staff("Staff') recommends the Commission issue a Notice of Application and
Notice of Modified Procedure, establishing a May 15,2025,public comment deadline, and a May 22,
2025, reply comment deadline.
COMMISSION DECISION
Does the Commission wish to issue a Notice of Application and Notice of Modified
Procedure, establishing a May 15, 2025, public comment deadline, and a May 22, 2025, reply
comment deadline?
rill
k�hnhf
Erika K. Melanson
Deputy Attorney General
I:\Legal\ELECTRIC\IPC-E-25-15_ECR\memos\IPCE2515_dec 1_em.docx
DECISION MEMORANDUM 1