Intermountain Gas 250318 Kuna Construction
IPUC Construction Inspection Inspector(s): Galli Date(s): 250318 Company/Owner: Intermountain Gas Company (IGC) Unit/OPID: 08160 Address: 10798 W Barnbougle Lane City/District: Kuna Contractor/Job#: W012078587 Foreman: Operator Supervisor: None Jose Mendoza Job Description: %" Service Line(s) System Type: 0 GD ❑ GT ❑ GG One-Call Ticket: 2025110572 Total Inspection Days: 1.0 Tasks: Procedure# Rating Comments 1. Materials—Handling, Storage, Labeling OPS 11 SAT 2. Trenching/Boring—Depth, Clearance OPS 308 SAT 24 inch service line. OPS 322 3. Bedding/Backfill OPS 308 SAT Sand used for service line. SF 418 4. Pipe Installation(Tracer Wire) OPS 308 SAT 14-gauge OPS 322 5. Valve Installation OPS 703 N/A 6. Coating Condition OPS 401 N/A OPS 403 7. Manuals—Field Procedures, O &M SAT 8. Testing—Pressure, Duration, Type OPS 505 SAT 100 PSI for 15 MIN 9. OQ Qualifications OPS 800 SAT Verified 10. Casing Seal/Installation OPS 325 N/A 11. Service Line Installation OPS 302 SAT 12. Tie-In/Hot Tapping OPS 600 N/A 13. Meter Location/Regulator Testing OPS 302 SAT 14. Equipment Calibration Verification OPS 501 SAT Verified 15. EFV Installation OPS 301 SAT EFV 1200 16. MAOP OPS 602 N/A OPS 606 OPS 900 OPS 1000 17. Purge OPS 603 N/A 18. Safety Equipment SF 418 SAT Fire Extinguisher & JSA j SF 422 19. Abandonment OPS 607 N/A 20. Line Locating OPS 611 SAT Hand dig to locate stub. IPUC Form 4 Rev.12/10/2024 IPUC Construction Inspection 21. Plastic Pipe OPS 307 SAT Butt fusion - Joiner(s) Qualified OPS 309 Stab fittings -Fusion Tools OPS 325 Squeeze off—Utilized span of - Squeezing OPS 800 control between foreman/fuser - Heat Plate - Joining Procedure 22. Steel Pipe OPS 200 N/A - Welder(s) Qualified OPS 201 Pipe/Coating—Inspected/Repaired OPS 202 - Cathodic Protection OPS 306 -Non-Destructive Testing OPS 401 -Welding Procedures OPS 407 -Removal of asbestos wrap OPS 402 - Exothermic Welding OPS 403 Additional Comments: Observations Included: (10798 W Barnbougle Lane, Kuna, ID) Line locating, correct trench depth, safety equipment, verification OQ records, verification equipment calibrations, mechanical fittings (coupler) installation, butt fusion, tracer wire,pressure test, squeeze off, bedding and backfill. Quizzed employees on applicable AOCs of squeeze of procedures. All observed procedures were completed in accordance with IGC Operations and Maintenance Manual. Corrective Action Required: ❑ Yes ® No Compliance Letter#: Lead Inspector: Galli Date: Reviewer: Brooks Date: 250318 Signature: Signature: 031,s IPUC Form 4 Rev. 12/10/2024