Intermountain Gas 250305 Kuna Construction
IPUC Construction Inspection Inspector(s): Perkins Date(s): 5 March 2025 Company/Owner: Intermountain Gas Company (IGC) Unit/OPID: 8160 Address: 682 W Snowy Owl City/District: Kuna Contractor/Job #: W012012107 Foreman: Operator Supervisor: None S. Creasy Job Description: 3/" Service Install System Type: © GD ❑ GT ❑ GG One-Call Ticket: 2025070703 Total Inspection Days: 1.0 Tasks: Procedure# Rating Comments 1. Materials—Handling, Storage, Labeling OPS 11 SAT 2. Trenching/Boring—Depth, Clearance OPS 308 SAT OPS 322 3. Bedding/Backfill OPS 308 SAT SF 418 4. Pipe Installation(Tracer Wire) OPS 308 SAT OPS 322 5. Valve Installation OPS 703 N/A 6. Coating Condition OPS 401 N/A OPS 403 7. Manuals—Field Procedures, O &M SAT 8. Testing—Pressure, Duration, Type OPS 505 SAT 94 PSI-15 Min 9. OQ Qualifications OPS 800 SAT 10. Casing Seal/Installation OPS 325 N/A 11. Service Line Installation OPS 302 SAT 12. Tie-In/Hot Tapping OPS 600 N/A 13. Meter Location/Regulator Testing OPS 302 N/A 14. Equipment Calibration Verification OPS 501 SAT Date in file 15. EFV Installation OPS 301 SAT 1200 16. MAOP OPS 602 SAT 60 PSI OPS 606 OPS 900 OPS 1000 17. Purge OPS 603 SAT 18. Safety Equipment SF 418 SAT SF 422 19. Abandonment OPS 607 N/A 20. Line Locating OPS 611 SAT IPUC Form 4 Rev. 12/10/2024 IPUC Construction Inspection 21. Plastic Pine OPS 307 SAT Stab Fittings - Joiner(s) Qualified OPS 309 - Fusion Tools OPS 325 - Squeezing OPS 800 - Heat Plate - Joining Procedure 22. Steel Pine OPS 200 N/A -Welder(s) Qualified OPS 201 Pipe/Coating—Inspected/Repaired OPS 202 - Cathodic Protection OPS 306 -Non-Destructive Testing OPS 401 - Welding Procedures OPS 407 -Removal of asbestos wrap OPS 402 - Exothermic Welding OPS 403 Additional Comments: Address: 682 W Snowy Owl, Kuna, Idaho Observations Conducted: • Ensured proper use of safety equipment. • Verified Operator Qualification(OQ) records. • Oversaw line locating, purging, and pressure testing processes. • Assessed installation of tracer wire, stab fittings, and Excess Flow Valve(EFV). • Reviewed bedding/backfill depths and procedures. • Quizzed employees on appropriate squeeze and release times, as well as adherence to excavation clearance standards. Corrective Action Required: ❑ Yes ® No Compliance Letter#: Lead Inspector: Per ins Date: Reviewer: Brooks Date: 250305 Signature: f Signature: 03 Os IPUC Form 4 Rev. 12/10/2024