BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
IN THE MATTER OF IDAHO POWER ) CASE NO. IPC-E-25-07
COMPANY'S 2024 VARIABLE ENERGY )
RESOURCE STUDY AND PROPOSED ) NOTICE OF FILING
UPDATE TO SCHEDULE 87 )
NOTICE OF
INTERVENTION DEADLINE
ORDER NO. 36510
BACKGROUND
On February 27, 2024, Idaho Power Company ("Company") filed a petition ("Petition")
with the Idaho Public Utilities Commission ("Commission") requesting to modify a compliance
requirement in Commission Order No. 36048,issued in Case No. IPC-E-23-14,regarding updating
the Company's Schedule 87, Intermittent Generation Integration Charges ("Schedule 87").
The Company requested that the Commission modify the Company's compliance
requirement to: (1) authorize the Company to update Schedule 87 integration costs based on the
forthcoming 2024 Variable Energy Resource("VER") Study, instead of the 2020 VER Study; and
(2)authorize the Company to file both the forthcoming 2024 VER Study and updated Schedule 87
no later than December 31, 2024.
On June 10, 2024, the Commission issued Order No. 36219, granting the Company's
request to modify the compliance requirement in Order No. 36048, and directing the Company to
file both the 2024 VER Study and updated Schedule 87 proposed rates no later than December 31,
2024. Order No. 36219 at 2. On December 31, 2024, the Company submitted a compliance filing
with its 2024 VER Study and Updated Schedule 87 proposed rates.
On February 18, 2025, the Commission issued Order No. 36466 in Case No. IPC-E-24-08
ordering a new docket be opened to consider the Company's proposed update to Schedule 87 rates.
NOTICE OF FILING
YOU ARE HEREBY NOTIFIED that the Company submitted a 2024 VER Integration
Study and updated Schedule 87. The Company requests that the Commission accept the
Company's 2024 VER Integration Study and the accompanying Schedule 87 integration charges
for an effective date of January 31, 2025.
NOTICE OF FILING
NOTICE OF INTERVENTION DEADLINE
ORDER NO. 36510 1
YOU ARE FURTHER NOTIFIED that all documents and materials have been filed with
the Commission and are available for public inspection during regular business hours at the
Commission's office. These documents are also available on the Commission's website at
www.puc.idaho.gov. Click on the "ELECTRIC" icon, select "Open Cases," and click on the case
number as shown on the front of this document.
YOU ARE FURTHER NOTIFIED that all proceedings in this case will be held pursuant
to the Commission's jurisdiction under Title 61 of the Idaho Code, and that all proceedings in this
matter will be conducted pursuant to the Commission's Rules of Procedure, IDAPA 31.01.01.000
et seq.
NOTICE OF INTERVENTION DEADLINE
YOU ARE FURTHER NOTIFIED that persons desiring to intervene in this matter to
obtain parties' rights of participation must file a Petition to Intervene with the Commission
pursuant to this Commission's Rules of Procedure 71-73,IDAPA 31.01.01.072-073. Persons who
wish to intervene as a party must file a Petition to Intervene no later than 21 days after the
date of service of this Order. Persons desiring to present their views without parties' rights of
participation do not have to intervene and may present their comments without prior notification
to the Commission or the parties.
YOU ARE FURTHER NOTIFIED that the Commission Secretary shall issue a Notice of
Parties after the deadline for intervention has passed. The Notice of Parties shall assign exhibit
numbers to each party in this proceeding.
YOU ARE FURTHER NOTIFIED that once the Notice of Parties is issued, Commission
Staff("Staff')will informally confer with the parties to discuss a schedule to process this case and
other issues as may be raised by the parties.
YOU ARE FURTHER NOTIFIED that the following persons are designated as the
Company's representatives in this matter:
Donovan E. Walker Alison Williams
Idaho Power Company Idaho Power Company
P.O. Box 70 P.O. Box 70
Boise, Idaho 83707 Boise, Idaho 83707
dwalker(a),idahopower.com awilliams(&,idahopower.com
dockets kidahopower.com
NOTICE OF FILING
NOTICE OF INTERVENTION DEADLINE
ORDER NO. 36510 2
ORDER
IT IS HEREBY ORDERED that persons desiring to intervene in this case for the purpose
of obtaining parties' rights of participation must file a Petition to Intervene with the Commission,
under Rules 71-73, IDAPA 31.01.01.071-073, no later than 21 days after the service date of this
Order.
IT IS FURTHER ORDERED that, after the Secretary issues a Notice of Parties, Staff will
informally confer with the parties to discuss the appropriate scheduling of this case.
IT IS FURTHER ORDERED that parties comply with Order No. 35375, issued April 21,
2022. Generally, all pleadings should be filed with the Commission electronically and will be
deemed timely filed when received by the Commission Secretary.See Rule 14.02. Service between
parties should continue to be accomplished electronically when possible. However, voluminous
discovery-related documents may be filed and served on CD-ROM or a USB flash drive.
DONE by Order of the Idaho Public Utilities Commission at Boise, Idaho this 14th day of
March 2025.
G
EDWARD LODGE, SIDENT
kk �/a�
J R. HAMMOND JR., COMMISSIONER
DAMN HA IE, COMMISSIONER
ATTEST:
�..
NVIel
Ba io
Commission Secre
IALegahELECTRIC\IPC-E-25-07_Sch 87\orders\IPCE2507_Ntc_Fil_Int_cb.docx
NOTICE OF FILING
NOTICE OF INTERVENTION DEADLINE
ORDER NO. 36510 3