HomeMy WebLinkAbout20250305AVU to Staff 1-18.pdf RECEIVED AVISTA CORPORATION March 5, 2025 Idaho Public RESPONSE TO REQUEST FOR INFORMATION Utilities Commission JURISDICTION: IDAHO DATE PREPARED: 03/05/2025 CASE NO: AVU-E-25-02 WITNESS: James Gall REQUESTER: IPUC RESPONDER: John Lyons TYPE: Production Request DEPARTMENT: Resource Planning REQUEST NO.: Staff-001 TELEPHONE: (509) 495-8515 REQUEST: Please provide the monthly capacity positions for 2025. RESPONSE: Here are the monthly capacity positions for 2025 from the 2025 IRP study,these estimates exclude any planned maintenance. Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec 2025 2025 2025 2025 2025 2025 2025 2025 2025 2025 2025 2025 50 181 330 655 500 197 103 105 440 422 280 153 AVISTA CORPORATION RESPONSE TO REQUEST FOR INFORMATION JURISDICTION: IDAHO DATE PREPARED: 03/05/2025 CASE NO: AVU-E-25-02 WITNESS: James Gall REQUESTER: IPUC RESPONDER: John Lyons TYPE: Production Request DEPARTMENT: Resource Planning REQUEST NO.: Staff-002 TELEPHONE: (509) 495-8515 REQUEST: Table 1 of the Compliance Filing shows that Colstrip Units 3 and 4 will exit in 2025 and Northeast will exit in 2029. Please explain whether these exits have regulatory certainties such as a signed contract or a Commission approval. Please also provide the exit dates based on their useful lives. RESPONSE: The exit from Colstrip Units 3 & 4 at the end of 2025 is based on a contract signed with NorthWestern Energy on January 16, 2023, that transfers ownership on January 1, 2026. The exit from Northeast is an Avista target date. No contract is needed to be signed to exit Northeast since Avista owns the entire plant and can unilaterally make decisions on the plant. The 2029 exit date does coincide with the end of the current 5-year air permit test schedule, although the current air permit expires in 2032. AVISTA CORPORATION RESPONSE TO REQUEST FOR INFORMATION JURISDICTION: IDAHO DATE PREPARED: 03/05/2025 CASE NO: AVU-E-25-02 WITNESS: James Gall REQUESTER: IPUC RESPONDER: John Lyons TYPE: Production Request DEPARTMENT: Resource Planning REQUEST NO.: Staff-003 TELEPHONE: (509) 495-8515 REQUEST: Prior Commission orders such as Order No. 33958 required the Company to use the latest information for determining capacity deficiency periods. Please respond to the following: a. Is the load forecast used in the Compliance Filing the latest load forecast? i.If not,please provide the latest load forecast and explain the difference between the latest and the proposed load forecast. b. Is the contract information used for determining capacity deficiency periods the latest contract information? i. If not, please provide the latest contract information and explain the difference between the latest contract information and the proposed contract information. RESPONSE: a. Yes. The load forecast used in the Compliance filing is the latest long-term forecast. b. Yes. The contract information used for determining capacity deficiency includes the latest contract information. AVISTA CORPORATION RESPONSE TO REQUEST FOR INFORMATION JURISDICTION: IDAHO DATE PREPARED: 03/05/2025 CASE NO: AVU-E-25-02 WITNESS: James Gall REQUESTER: IPUC RESPONDER: John Lyons TYPE: Production Request DEPARTMENT: Resource Planning REQUEST NO.: Staff-004 TELEPHONE: (509) 495-8515 REQUEST: Are Public Utility Regulatory Policies Act ("PURPA") contracts assumed to be renewed in the Load and Resource Balance? Please explain and justify the decision. RESPONSE: Based on Avista's experience with these contracts, as well as ongoing communications with the project owners, the Company assumes the renewal of these contracts after the term expires. This has been Avista's policy for the last 20 years at least, regarding PURPA contracts. AVISTA CORPORATION RESPONSE TO REQUEST FOR INFORMATION JURISDICTION: IDAHO DATE PREPARED: 03/05/2025 CASE NO: AVU-E-25-02 WITNESS: James Gall REQUESTER: IPUC RESPONDER: John Lyons TYPE: Production Request DEPARTMENT: Resource Planning REQUEST NO.: Staff-005 TELEPHONE: (509) 495-8515 REQUEST: Please explain why the values in Table 2 of the Compliance Filing do not match the table on the Tab "Position Summary" of confidential file "AVU-E-25_2025 Capacity Deficiency Application-Confidential 1-29-25.xlsm". Also,please explain which table is correct. RESPONSE: Table 2 was copied and pasted from the position summary tab in the referenced spreadsheet. The 1 MW difference in some of the cells is due to how Word rounds data on tables. They are both correct,but the spreadsheet would be more accurate given that number of significant digits on each cell can be expanded. AVISTA CORPORATION RESPONSE TO REQUEST FOR INFORMATION JURISDICTION: IDAHO DATE PREPARED: 03/05/2025 CASE NO: AVU-E-25-02 WITNESS: James Gall REQUESTER: IPUC RESPONDER: John Lyons TYPE: Production Request DEPARTMENT: Resource Planning REQUEST NO.: Staff-006 TELEPHONE: (509) 495-8515 REQUEST: Please define and explain the following resources that are included in Tab "System_LR" of confidential file "AVU-E-25_2025 Capacity Deficiency Application-Confidential 1-29-25.xlsm" and why their values are zero. Juris Purch Palouse Wind Juris Purch Rattlesnake Flat Juris Purch Kettle Falls Juris Purch Chelan PUD Juris Purch Chelan PUD Canadian Entitlement Juris Purch Columbia Basin Hydro Juris Purch Clearwater Wind RESPONSE: In the event Idaho's jurisdictional allocated share of one of these resources is used to comply with Washington's CETA on a planning basis, this section of the model would account for the change in available generation for each state to its position. The amounts moving between jurisdictions is shown in each individual state's L&R tab. On the system L&R, the movement of generation balances out to zero since there is no change in the overall utility position by temporarily assigning generation to an individual jurisdiction.An example of moving generation between jurisdictions is in Cell DB 172 on the"WA LR"tab". AVISTA CORPORATION RESPONSE TO REQUEST FOR INFORMATION JURISDICTION: IDAHO DATE PREPARED: 03/05/2025 CASE NO: AVU-E-25-02 WITNESS: James Gall REQUESTER: IPUC RESPONDER: John Lyons TYPE: Production Request DEPARTMENT: Resource Planning REQUEST NO.: Staff-007 TELEPHONE: (509) 495-8515 REQUEST: Please define "Jurisdictional Transfer" and explain why its capacity is zero. RESPONSE: Please see the response to Staff PR 006. AVISTA CORPORATION RESPONSE TO REQUEST FOR INFORMATION JURISDICTION: IDAHO DATE PREPARED: 03/05/2025 CASE NO: AVU-E-25-02 WITNESS: James Gall REQUESTER: IPUC RESPONDER: James Gall TYPE: Production Request DEPARTMENT: Resource Planning REQUEST NO.: Staff-008 TELEPHONE: (509) 495-2189 REQUEST: Please explain how the values of"Short Term Market Purchases"are determined and why they are not used in calculating Net Position. Also, please explain if the values are subject to a 330 MW market limitation. RESPONSE: The"Short Term Market Purchases" are transactions the utility has committed to at the time of the IRP. These are typically market transactions for at least one month. These are different than the 330 MW market limitation. The 330 MW market limitation applies to reliability modeling of the limit we anticipate being able to depend on for market transactions in real time operations during peak events based on our regional share of the market and transactional history during peak events. Avista will often buy as much power that is economic considering the ability to deliver the energy but does not want to depend on market power exceeding 330 MW for resource adequacy. AVISTA CORPORATION RESPONSE TO REQUEST FOR INFORMATION JURISDICTION: IDAHO DATE PREPARED: 03/05/2025 CASE NO: AVU-E-25-02 WITNESS: James Gall REQUESTER: IPUC RESPONDER: James Gall TYPE: Production Request DEPARTMENT: Resource Planning REQUEST NO.: Staff-009 TELEPHONE: (509) 495-2189 REQUEST: Please define "Embedded EE" and "Selected EE". Please explain the difference between the two and also explain why their values are the same. RESPONSE: Avista's load forecast includes expected energy efficiency savings. Since the IRP must determine the amount of cost-effective energy efficiency to pursue, the load forecast must estimate the amount of energy efficiency implied in the load forecast as the model solves for a load without energy efficiency. To determine how much load to add back to the load forecast, the model is run iteratively until the amount of energy efficiency selected is similar to the amount added back. The "Embedded EE"is an estimate of the amount of energy efficiency added to the load forecast from this iterative process, whereas the "Selected EE" is the actual amount of the model selection. AVISTA CORPORATION RESPONSE TO REQUEST FOR INFORMATION JURISDICTION: IDAHO DATE PREPARED: 03/05/2025 CASE NO: AVU-E-25-02 WITNESS: James Gall REQUESTER: IPUC RESPONDER: John Lyons TYPE: Production Request DEPARTMENT: Resource Planning REQUEST NO.: Staff-010 TELEPHONE: (509) 495-8515 REQUEST: Please explain what"Electrification"represents and why its values are zero. RESPONSE: The "Electrification" cells are all zero in the expected or base case. These cells are only used in 2025 IRP scenarios studying additional electrification of building stock where electricity replaces natural gas use not already embedded in the load forecast. AVISTA CORPORATION RESPONSE TO REQUEST FOR INFORMATION JURISDICTION: IDAHO DATE PREPARED: 03/05/2025 CASE NO: AVU-E-25-02 WITNESS: James Gall REQUESTER: IPUC RESPONDER: John Lyons TYPE: Production Request DEPARTMENT: Resource Planning REQUEST NO.: Staff-0I I TELEPHONE: (509) 495-8515 REQUEST: For the line item"Reserves + Regulation+ Maintenance Adjustment", please define "Reserves", "Regulation" and"Maintenance Adjustment" and explain how their values are determined. Also, please explain the difference between"Reserves" and"Regulation." RESPONSE: These are a total of adjustments used in the IRP where the amounts individually may provide information to the general public that is confidential. Since Avista makes its PRiSM model public, these values are summed. "Reserves" is the account of the operating reserves Avista must hold for loads and generators within its balancing authority. For loads, this is 3% of load. Avista also carries reserves for two generators not serving Avista customers. "Regulation" accounts for the difference between the average load of the peak hour versus the absolute peak load within the hour. Avista assumes this is 10 MW. The "Maintenance Adjustment" is an adjustment to the peak planning forecast to account for unit maintenance using a combination of historical outages and a forecast of routine maintenance. AVISTA CORPORATION RESPONSE TO REQUEST FOR INFORMATION JURISDICTION: IDAHO DATE PREPARED: 03/05/2025 CASE NO: AVU-E-25-02 WITNESS: James Gall REQUESTER: IPUC RESPONDER: James Gall TYPE: Production Request DEPARTMENT: Resource Planning REQUEST NO.: Staff-012 TELEPHONE: (509) 495-2189 REQUEST: Please explain why the Planning Reserve Margin("PRM")for winter is determined by a reliability study, while the PRM for summer is determined by the single largest contingency resource compared to expected load. Also, please explain the rationale behind the method for summer PRM. Lastly, please explain if the reliability study that determines PRM uses the Qualifying Capacity Contribution ("QCCs") in 2030 derived from the short-term Western Resource Adequacy Program ("WRAP") QCCs. RESPONSE: When Avista conducted its hourly reliability planning study, the study found the primary capacity shortfalls are in the winter months. When determining the planning reserve margin (PRM), the resources added to meet winter capacity shortfalls also would meet the smaller summer requirements. Since IRP planning requires a PRM in all months in the event a resource is added to solve a particular season, Avista needed a summer PRM as the utility could be short in this season if winter only resources are added. Avista decided to use the single largest contingency method to arrive at this estimate. This method quantifies the amount of lost generation of the single largest facility in the event it went on outage. In this case, Coyote Springs 2 is assumed to generate 288 MW in a summer peak event and peak summer load is approximately 1,837 MW,dividing the two results is a 16% factor. Since Avista is at risk of losing this asset, the 16% summer PRM seemed reasonable to ensure the utility has adequate capacity in this season. Absent this PRM, the utility could be overly dependent on the market. Regarding QCCs, Avista's reliability study does not use the WRAP's QCC values, the study is based on the capability of each resource using 1,000 simulations of load, forced outages, wind, temperatures, and hydro conditions. The WRAP QCC values are only used as the capacity value for estimating the PRM based upon the resource capacity shortfall from the resource adequacy study. AVISTA CORPORATION RESPONSE TO REQUEST FOR INFORMATION JURISDICTION: IDAHO DATE PREPARED: 03/0/2025 CASE NO: AVU-E-25-02 WITNESS: James Gall REQUESTER: IPUC RESPONDER: James Gall TYPE: Production Request DEPARTMENT: Resource Planning REQUEST NO.: Staff-013 TELEPHONE: (509) 495-2189 REQUEST: Page 6 states that Avista conducts a reliability study with the resources chosen within the Preferred Resource Strategy for 2030, and the results show the system is below the 5% Loss of Load Probability("LOLP")threshold. Please explain if it is possible for the LOLP to be above 5%if the PRM is selected using the 5%LOLP threshold and resources are selected based on the PRM. If so, please explain how that would occur. RESPONSE: If the PRS resulted in a portfolio with a LOLP above 5%,the PRM would be increased, and a new portfolio would be created to ensure the resulting portfolio's PRM is below 5%. This did occur in high load scenarios where additional capacity added did not meet the 5%threshold with the higher loads. AVISTA CORPORATION RESPONSE TO REQUEST FOR INFORMATION JURISDICTION: IDAHO DATE PREPARED: 03/05/2025 CASE NO: AVU-E-25-02 WITNESS: James Gall REQUESTER: IPUC RESPONDER: James Gall TYPE: Production Request DEPARTMENT: Resource Planning REQUEST NO.: Staff-014 TELEPHONE: (509) 495-2189 REQUEST: Page 5 of the Compliance Filing states that using the WRAP values creates a consistency of resource assumptions in other resource adequacy settings. Please explain what are "other resource adequacy settings" and why the consistency of resource assumptions is important. RESPONSE: The "other resource adequacy setting" is compliance with the WRAP and for Avista's internal L&R tracking. Avista is a participant in the WRAP and finds this is the best method to account for L&R balancing as it creates a consistent methodology between all participating utilities of how to estimate the capacity value of each resource. If Avista did not use a consistent method of capacity quantification it would have multiple estimates of how much capacity an individual resource is assumed to meet peak load events. This would result in duplication of analysis and tracking. AVISTA CORPORATION RESPONSE TO REQUEST FOR INFORMATION JURISDICTION: IDAHO DATE PREPARED: 03/05/2025 CASE NO: AVU-E-25-02 WITNESS: James Gall REQUESTER: IPUC RESPONDER: James Gall TYPE: Production Request DEPARTMENT: Resource Planning REQUEST NO.: Staff-015 TELEPHONE: (509) 495-2189 REQUEST: Please provide examples showing how WRAP short-term QCCs are converted to long-term QCCs. RESPONSE: See the confidential attachment Staff_PR_015_Attachment A. This attachment is currently being prepared for use in Avista's upcoming Request for Proposals for new capacity. This file includes the WRAP's estimated ELCC value for VERB and energy storage(WRAP QCC Linear tab). These estimates are for the amount of effective load carrying (ELCC) for the year for each resource for the current generation level in the region and for if the region adds generation. These ELCC changes are then applied to the QCCs the WRAP currently estimates for each month (See "Monthly QCC" tab). Avista forecasts the change based upon its regional forecast for growth of each resource type in tab "QCC WRAP Forecast". The remaining tab "E3 study reference" is a comparison as it is an independent view of how ELCC/QCC values will change over time. Avista is currently working with E3 to conduct an updated study on regional resource adequacy along with other utilities in the Northwest. AVISTA CORPORATION RESPONSE TO REQUEST FOR INFORMATION JURISDICTION: IDAHO DATE PREPARED: 03/05/2025 CASE NO: AVU-E-25-02 WITNESS: James Gall REQUESTER: IPUC RESPONDER: James Gall TYPE: Production Request DEPARTMENT: Resource Planning REQUEST NO.: Staff-016 TELEPHONE: (509) 495-2189 REQUEST: Page 6 of the Compliance Filing states that if Avista used the prior methodology approved in past orders for resource capacity contribution, the resulting capacity need would be the same. Please provide the following: a. Please explain how the prior methodology determined resource capacity contribution and provide examples for each technology type. b. Please explain how WRAP method determines short-term QCCs and provide examples for each technology type. c. Please explain how Avista determined long-term QCCs and provide examples for each technology type. RESPONSE: a. The prior methodology could have assigned a higher or lower capacity value for each resource. This could be because Avista did not include forced outages in its methodology to account for generation capacity or if the variable resource had a different resulting effective load carrying capability assumed depending on the methodology of the study of the resource. For example, Coyote Springs 2 has a 314 MW QCC value by the WRAP, if Avista used its prior methodology it would be 317.5 MW. The WRAP determines its value by historical forced outage rates and specific historical generation resource submittals. b. Please see Confidential Staff_PR_016 Attachment A pages 17 to 34 for detailed documentation about the WRAP methodology for the calculation of short-term QCCs for all resource types including thermal or long duration storage resources (p. 17 — 21), variable energy resources (p. 22—29), energy storage(p. 29—30),hybrid facilities (p. 30 - 31), and hydro resources (p. 31 —34). c. See Response to Staff_PR 015 for an example. The WRAP's study results for bother winter and summer periods if additional resource capacity is added to the system are shown in Confidential Staff_PR_016 Attachment B (2024-12-12 Webinar Summer 2026 and 2029 Data final.pdf) and Confidential Staff_PR_016 Attachment C (2024-06-13 Webinar Winter 2025-2026 and 2028-2029 Data.pdf). AVISTA CORPORATION RESPONSE TO REQUEST FOR INFORMATION JURISDICTION: IDAHO DATE PREPARED: 03/05/2025 CASE NO: AVU-E-25-02 WITNESS: James Gall REQUESTER: IPUC RESPONDER: James Gall TYPE: Production Request DEPARTMENT: Resource Planning REQUEST NO.: Staff-017 TELEPHONE: (509) 495-2189 REQUEST: Page 6 of the Compliance Filing states that Avista uses the resource adequacy study to calculate its resource deficit.Please explain the method used in the resource adequacy study and provide a copy of the study. Also, please explain the relationship between the deficit amount determined in the resource adequacy study and the deficit amount determined by the Load and Resource Balance. RESPONSE: The confidential resource adequacy study documents are included as: • Staff_PR_017 Attachment A • Staff PR 017 Attachment B Attachment A contains a summary of the 1,000 simulations, including the quantity and size of resource deficits, this file also demonstrates how the 24% Planning Reserve Margin (PRM) is calculated in the L&R 2030 tab, in this case 50 MW is added to the January month to arrive at the 24%PRM value,whereas the 50 MW addition was required to get close to the 5%LOLP target in 2030.Attachment B is the model used to estimate our capacity shortfalls. The results of this model are input into Attachment A. The model runs each simulation one at a time then stores the results. In this example,the 1,000 simulations were split between 5 files and only the first 200 simulations are included as an example. There is one major difference regarding the differences between this result and the L&R. The difference is the L&R used in the IRP includes the maintenance outages discussed in the response to Staff PR_011. AVISTA CORPORATION RESPONSE TO REQUEST FOR INFORMATION JURISDICTION: IDAHO DATE PREPARED: 03/05/2025 CASE NO: AVU-E-25-02 WITNESS: James Gall REQUESTER: IPUC RESPONDER: James Gall TYPE: Production Request DEPARTMENT: Resource Planning REQUEST NO.: Staff-018 TELEPHONE: (509) 495-2189 REQUEST: Page 5 of the Compliance Filing states that the PRM is determined by summing the QCCs of all existing and "required" resources to determine the 5% LOLP result and then dividing it by the expected peak load. In reference to Table 3 of the Compliance Filing,does the"required"resource mean the 50-MW resource? Please explain whether the 50-MW resource is determined based on the 5% LOLP target under both Method 1 and/or Method 2. RESPONSE: The reference is referring to the requirement of needing a 50 MW resource. The 50 MW resource is needed in both Method 1 and Method 2 as the resource need is being identified in the resource adequacy model, not the L&R. The L&R is used for the Planning Reserve Margin calculation.