Loading...
The URL can be used to link to this page
Your browser does not support the video tag.
Home
My WebLink
About
Intermountain Gas 250108 Star Construction
IPUC Construction Inspection Inspector(s): Perkins Date(s): 8 January 2025 Company/Owner: Intermountain Gas Company (IGC) Unit/OPID: 8160 Address: 12654 W Pine Grass St City/District: Star Contractor/Job#: 08092-367 Foreman: Operator Supervisor: None J. Hammer Job Description: %" Service Install and stub I System Type: M GD ❑ GT ❑ GG One-Call Ticket: 2024512182 Total Inspection Days: 1 Tasks: Procedure# Rating Comments 1. Materials—Handling, Storage, Labeling OPS 11 SAT 2. Trenching/Boring—Depth, Clearance OPS 308 SAT OPS 322 3. Bedding/Backfill OPS 308 SAT SF 418 4. Pipe Installation(Tracer Wire) OPS 308 SAT OPS 322 5. Valve Installation I OPS 703 N/A 6. Coating Condition OPS 401 N/A OPS 403 7t Manuals—Field Procedures, O & M SAT 8. Testing—Pressure, Duration, Type OPS 505 SAT 96 PSI-15 Min 9. OQ Qualifications OPS 800 SAT 10. Casing Seal/Installation OPS 325 N/A 11. Service Line Installation OPS 302 SAT 12. Tie-In/Hot Tapping OPS 600 N/A 13. Meter Location/Regulator Testing OPS 302 N/A 14. Equipment Calibration Verification OPS 501 SAT In File 15. EFV Installation OPS 301 SAT 16. MAOP OPS 602 N/A OPS 606 OPS 900 OPS 1000 17. Purge OPS 603 SAT 18. Safety Equipment SF 418 SAT SF 422 19. Abandonment OPS 607 N/A 20. Line Locating OPS 611 SAT IPUC Form 4 Rev. 12n0i2024 IPUC Construction Inspection 21. Plastic Pipe OPS 307 SAT %" Stab Fittings and Fusing - Joiner(s) Qualified OPS 309 - Fusion Tools OPS 325 - Squeezing OPS 800 - Heat Plate - Joining Procedure 22. Steel Pipe OPS 200 N/A - Welder(s) Qualified OPS 201 Pipe/Coating—Inspected/Repaired OPS 202 - Cathodic Protection OPS 306 -Non-Destructive Testing OPS 401 - Welding Procedures OPS 407 - Removal of asbestos wrap OPS 402 - Exothermic Welding OPS 403 Additional Comments: Address: 12654 W Pine Grass, Star, Idaho Observations Included: Line locating, correct trench depth, safety equipment, verification OQ records, verification equipment calibrations, purging, pressure testing, tracer wire install, fusing, mechanical fittings (couplers), EFV 1200 installation,bedding and backfilling. Quizzed employee on squeeze time procedures. Corrective Action Required: ❑ Yes ® No Compliance Letter#: Lead Inspector: Pe kins Date: Reviewer: Brooks Date: 250108 , c Signature: Signature: - - S-IU IPUC Form 4 Rm 12/10/2024