HomeMy WebLinkAbout20250124First_Amended_Certificate_No_300.pdf BEFORE THE IDAHO PUBLIC UTILITIES COMMISSION
IN THE MATTER OF THE APPLICATION ) CASE NOS. ATL-E-22-02
OF GREYLOCK ENERGY HOLDINGS,LLC ) ATL-E-22-01
FOR APPROVAL OF ITS STOCK AND )
OWNERSHIP INTERESTS PURCHASE ) FIRST AMENDED
AGREEMENT WITH ISRAEL RAY FOR ) CERTIFICATE NO. 300
THE ACQUISITION OF THE ATLANTA )
POWER COMPANY )
IN THE MATTER OF THE INVESTIGATION )
OF ATLANTA POWER COMPANY )
SERVICE AND CUSTOMER RELATION )
IT IS HEREBY CERTIFIED that the public convenience and necessity is transferred to
Greylock Energy Holdings, LLC.
IT IS FURTHER CERTIFIED that the public convenience and necessity requires Greylock
Energy Holdings, LLC, its successors and assigns to hold, construct, or otherwise acquire, to
maintain and to operate Atlanta Power Company, Inc., and supply electricity to that certain
territory within and surrounding the community of Atlanta, Idaho, described below:
Begin at NW Corner Section 19, Township 6 North, Range 11
E.B.M. thence eastward to NE corner of Section 22; thence
southward to NE corner Section 34; thence eastward to NE corner
Section 31, Township 6 N, Range 12 E.B.M.; thence southward to
SE corner Section 19, Township 5 N, Range 12 E.B.M.; thence
westward to SW corner Section 24, Township 5 N, Range 10
E.B.M.; thence northward to NW corner Section 1; thence eastward
to SW corner Section 31, Township 6 N, Range 11 E.B.M.; thence
northward to NW corner Section 19, Township 6 N, Range 11
E.B.M., the POINT OF BEGINNING
This First Amended Certificate is predicated upon and issued pursuant to the findings and
conclusions of Order No. 35649 in Case Nos. ATL-E-22-01 and ATL-T-22-02 to which reference
is hereby made.
FIRST AMENDED
CERTIFICATE NO. 300 1
DATED at Boise, Idaho this 24th day of January 2025.
E CC�-�D RSON, PRESIDENT
J R. HAMMOND JR., COMMISSIONER
G
EDWARD LODGE, C _ MISSIONER
ATTEST:
L- fj-
Ba 7
ios- a
Commission ecret
I:\Legal\ELECTRIC\\ATLE2202_First Amended Cert 300_kh.docx
FIRST AMENDED
CERTIFICATE NO. 300 2