HomeMy WebLinkAbout20250114Tariff.pdf ON -0IQAW POWER.
RECEIVED
2024 December 20 PM 2:43
CONNIE ASCHENBRENNER IDAHO PUBLIC
Rate Design Senior Manager UTILITIES COMMISSION
caschenbrenner(a)idahopower.com Tm ffAdv xM. W VE24-0j
VIA ELECTRONIC FILING
December 20, 2024
Commission Secretary
Idaho Public Utilities Commission
11331 W. Chinden Blvd., Bldg 8,
Suite 201-A (83714)
PO Box 83720
Boise, Idaho 83720-0074
Re: Tariff Advice No. 24-06
Annual Compliance Filing to Update the Substation Allowance Amount under
Schedule 19, Large Power Service
Dear Commission Secretary,
Idaho Power Company ("Idaho Power" or"Company") hereby submits its proposed
update to the Substation Allowance amount outlined in Schedule 19, Large Power Service
("Schedule 19"). This is the annual compliance filing to update the Substation Allowance
amount contained within Schedule 19, as required by Idaho Public Utilities Commission
("Commission") Order Nos. 32893 and 32914. The following tariff sheet identifies the
proposed modification:
Second Revised Sheet No. 19-6 Cancelling First Revised Sheet No. 19-6
The cost estimation methodology the Company used in this tariff advice is the
same methodology approved by the Commission in Case No. IPC-E-13-09 and
subsequent annual filings.
The proposed Substation Allowance amount reflects updated material costs, labor
rates, and the stations overhead rate, which in total results in the proposed per megawatt
Substation Allowance amount increasing from $71,052 to $99,826, or by approximately
29 percent. The primary drivers behind the proposed increase are inflation and increased
demand that have resulted in an approximate 50 percent increase in the cost of the 4-
unit metalclad switchgear and an approximate 27 percent increase in the cost of the
P.O.Box 70(83707)
1221 W.Idaho St.
Boise,ID 83702
Commission Secretary
December 20, 2024
Page 2 of 2
138kV/13.09kV, 44.8 MVA transformer. The increases in the costs of these items more
than offset the reduction in the stations overhead rate from 4.7 percent to 2.64 percent.
The workpapers used to calculate the per megawatt Substation Allowance amount
and the stations overhead rate are provided as confidential attachments to this tariff
advice. Please note that information in the workpapers is commercially sensitive and, if
disclosed freely, could subject Idaho Power or its customers to risk of competitive
disadvantage or other business injury.
Because the Company files to update the Substation Allowance in accordance with
a previously approved Commission methodology, it has submitted the request as a tariff
advice. However, to ensure Staff has adequate time to complete its review,' the Company
is requesting the same effective date proposed by Staff in last year's update. Accordingly,
the Company respectfully requests that the proposed updates are approved and become
effective by March 15, 2025.
If you have any questions regarding this tariff advice, please contact Regulatory
Analyst Ashley Herrera at 208-388-2656 or aherrera@idahopower.com.
Sincerely,
Connie Aschenbrenner
CA:sg
Enclosures
' In last year's filing, the Company submitted IPC-TAE-23-03 with a proposed effective date of February
1, 2024. Staff recommended the Commission treat the Company's Tariff Advice as an application to allow
a more in-depth analysis to ensure the components included in the allowance calculation reflect current,
accurate costs. To provide that time, Staff recommended the Commission suspend the Company's
proposed effective date until March 15, 2024. The Commission adopted Staff's recommendation and
opened Case No. IPC-E-24-02.
CERTIFICATE OF ATTORNEY
ASSERTION THAT MATERIALS REQUESTED AND PROVIDED DURING THE
COURSE OF AN IDAHO PUBLIC UTILITIES COMMISSION PROCEEDING
ARE PROTECTED FROM PUBLIC INSPECTION
Tariff Advice No. IPC-TAE-24-06
Idaho Power Company's Schedule 19 — Large Power Service Update
The undersigned attorney, in accordance with Commission Rules of Procedure 67,
believes that the attachments to Idaho Power Company's Tariff Advice No. 24-06 —
Schedule 19 — Large Power Service, dated December 20, 2024, contain information that
constitutes trade secrets or other confidential business data exempt from disclosure
under Idaho Code § 74-101, et seq., and/or§ 48-801, et seq. As such, it is protected from
public disclosure, inspection, examination, or copying.
DATED this 20th day of December 2024.
Ic6UA aim
Megan Goicoechea Allen
Counsel for Idaho Power Company
P.O.Box 70(83707)
1221 W.Idaho St.
Boise,ID 83702
Idaho Power Company Second Revised Sheet No. 19-6
Cancels
I.P.U.C. No. 30, Tariff No. 101 First Revised Sheet No. 19-6
SCHEDULE 19
LARGE POWER SERVICE
(Continued)
SPECIAL ARRANGEMENTS FOR SUBSTATION ALLOWANCES AND/OR TRANSMISSION VESTED
INTEREST (Continued)
Definitions (Continued)
Transmission Vested Interest Portion is that part of the Company's transmission system in which
a Transmission Vested Interest is held.
Substation Allowance
If a Schedule 19 Customer's request for service requires the installation of new or upgraded
transformer capacity in Substation Facilities, the following considerations will be included in the separate
agreement between the Customer and the Company:
The Customer will initially pay for the cost of new or upgraded Substation Facilities
required because of the Customer's request. The Customer will be eligible to receive a one-time
Substation Allowance based upon subsequent sustained usage of capacity by the Customer.
a. Substation Allowance: The maximum possible allowance will be
determined by multiplying the Customer's actual increase in load by $99,826 per MW, but
will not exceed the actual cost of the Substation Facilities.
b. Substation Allowance Refunds: The Substation Allowance will be refunded
to the Customer over a five-year period, with annual payments based on the Customer's
Basic Load Capacity at the time of refund. The first refund will be paid one year following
the first month energy is delivered through the new Substation Facilities.
The refunds will occur based on the following adjustment, which will be
added to the Substation Allowance received in the previous year. If there is no
change in load from the previous year, the Substation Allowance for that year is
equal to the Substation Allowance from the previous year:
((Change in load from the previous year as measured in MW)x(Substation Allowance per MW))
Number of Substation Allowance Refunds remaining in five-year period
The Customer's annual refunds will be made in accordance with the
Substation Allowance amount stated in the separate construction agreement
between the Customer and the Company.
Transmission Vested Interest
If a Schedule 19 Customer's request for service requires the installation of new or upgraded
capacity in Transmission Facilities, and those Transmission Facilities are serving the Customer by a
radial feed, the following considerations will be included in the separate agreement between the
Customer and the Company:
IDAHO Issued by IDAHO POWER COMPANY
Issued — December 20, 2024 Timothy E. Tatum, Vice President, Regulatory Affairs
Effective — March 15, 2025 1221 West Idaho Street, Boise, Idaho
Advice No. 24-06
Idaho Power Company Forst Second Revised Sheet No. 19-6
Cancels
I.P.U.C. No. 30, Tariff No. 101 04wRa4-First Revised Sheet No. 19-6
SCHEDULE 19
LARGE POWER SERVICE
(Continued)
SPECIAL ARRANGEMENTS FOR SUBSTATION ALLOWANCES AND/OR TRANSMISSION VESTED
INTEREST (Continued)
Definitions (Continued)
Transmission Vested Interest Portion is that part of the Company's transmission system in which
a Transmission Vested Interest is held.
Substation Allowance
If a Schedule 19 Customer's request for service requires the installation of new or upgraded
transformer capacity in Substation Facilities, the following considerations will be included in the separate
agreement between the Customer and the Company:
The Customer will initially pay for the cost of new or upgraded Substation Facilities
required because of the Customer's request. The Customer will be eligible to receive a one-time
Substation Allowance based upon subsequent sustained usage of capacity by the Customer.
a. Substation Allowance: The maximum possible allowance will be
determined by multiplying the Customer's actual increase in load by $71,05299,826 per
MW, but will not exceed the actual cost of the Substation Facilities.
b. Substation Allowance Refunds: The Substation Allowance will be refunded
to the Customer over a five-year period, with annual payments based on the Customer's
Basic Load Capacity at the time of refund. The first refund will be paid one year following
the first month energy is delivered through the new Substation Facilities.
The refunds will occur based on the following adjustment, which will be
added to the Substation Allowance received in the previous year. If there is no
change in load from the previous year, the Substation Allowance for that year is
equal to the Substation Allowance from the previous year:
((Change in load from the previous year as measured in MW)x(Substation Allowance per MW))
Number of Substation Allowance Refunds remaining in five-year period
The Customer's annual refunds will be made in accordance with the
Substation Allowance amount stated in the separate construction agreement
between the Customer and the Company.
Transmission Vested Interest
If a Schedule 19 Customer's request for service requires the installation of new or upgraded
capacity in Transmission Facilities, and those Transmission Facilities are serving the Customer by a
radial feed, the following considerations will be included in the separate agreement between the
Customer and the Company:
IDAHO Issued by IDAHO POWER COMPANY
Issued — December 20, 2024 per Order non 36114Timothy E. Tatum, Vice President, Regulatory Affairs
Effective— March 15, 2 March 15, 2025 1221 West Idaho Street, Boise, Idaho
Advice No. 24-06