HomeMy WebLinkAboutIntermountain Gas 241119 Kimberly Construction IPUC Construction Inspection
Inspector(s): Galli Date(s): 11/19/2024
Company/Owner: Unit/OPID: 08160
Intermountain Gas Company(IGC)
Address: 924 Vista Ave City/District: Kimberly
Contractor/Job#: Foreman: Employees:
KV Utilities 585-02637 Blake Hall See lineup in file
Job Description: %" Service Line(s) System Type: ® Distribution ❑ Transmission
Operator Supervisor: Jake Robertson One-Call Ticket: 2024470440
On-Site: Y
Total Inspection Days: 1.0
Tasks: Rating Critical Procedure# Comments
1. Materials—Handling, Storage, SAT OPS 11
Labeling
2. Trenching/Boring—Depth, Clearance SAT OPS 308 18 inches
OPS 322
3. Bedding/Backfill N/A OPS 308 No sand needed
J SF 418
4. Pipe Installation(Tracer Wire) N/A OPS 308
OPS 322
5. Valve Installation N/A OPS 703
6. Coating Condition N/A OPS 401
OPS 403
7. Manuals—Field Procedures, O &M SAT
8. Testing—Pressure, Duration, Type N/A OPS 505
9. OQ Qualifications SAT OPS 800 Verified
10. Casing Seal/Installation N/A OPS 325
11. Service Line Installation SAT OPS 302
12. Tie-In/Hot Tapping N/A OPS 600
13. Meter Location/Regulator Testing SAT OPS 302 Correct Meter location
14. Equipment Calibration Verification N/A OPS 501 N/A
15. EFV Installation N/A OPS 301
16. MAOP N/A OPS 602
OPS 606
OPS 900
OPS 1000
17. Pure N/A OPS 603
18. Safety Equipment SAT SF 418 Fire extinguisher& JSA
SF 422
19. Abandonment N/A OPS 607
20. Line Locating SAT OPS 611 Hand dig to expose stub
I P U C Form 4 Rev.12/21/2023
IPUC Construction Inspection
21. Plastic Pine N/A OPS 307
- Joiner(s) Qualified OPS 309
-Fusion Tools OPS 324
- Heat Plate OPS 325
- Joining Procedure OPS 800
-Squeeze Off
22. Steel Pipe N/A OPS 200
- Welder(s) Qualified OPS 201
Pipe/Coating—Inspected/Repaired OPS 202
- Cathodic Protection OPS 306
-Non-Destructive Testing OPS 401
- Welding Procedures OPS 407
- Removal of asbestos wrap OPS 402
- Exothermic Welding OPS 403
4800
Additional Comments:
Address: 924 Vista Ave, Kimberly, ID
Observations Included: Line locating, correct trench depth, safety equipment, verification OQ records,
and valid dig ticket. Quizzed KV employee on trench depth and spacing with other utilities. All
observed procedures were followed in accordance with IGC Operations and Maintenance Manual.
Attempted to observe an IGC crew fix a leak on Aldyl-A pipe at 1257 Park Meadows Drive in Twin
Falls but was unable to meet the crew due to other work in the district.
Attempted to observe a second KV utilities crew at 501 Thompson Court in Jerome, ID but was unable
to observe any gas work due to the crew rock hammering the trench.
Corrective Action Required: Yes No X
Follow-up Required: By Date: Yes No X
Inspector (Lead): Date: 11/19/2024
Galli
Reviewer:
Brooks Date:
IPUC Form 4 Rev. 12/2112023