HomeMy WebLinkAboutIntermountain Gas 210809-12 Twin Falls Field Idaho PUC Pipeline Safety Inspection Summary
Inspector(s): I Perkins Date(s): 9-12 Aug 2021
Company/Owner: Intermountain Gas Company Unit/OPID: I Twin Falls
Inspection Type &Time (1 day, 0.5 day) I Total Inspection Days: 4
Construction: Training: = (T)(D) Integrity Management: Incident:
Standard:F3 5
M/K = Follow-up: OQ: 0.5 Damage Prevention: EJ D&A:
Inspection Summary
Audit consisted of inspecting field installed equipment and operator qualification for the Twin Falls, Idaho
inspection units. Records and procedures for all Idaho Intermountain Gas Units were inspected in March 2021
at the Intermountain Gas Company(IGC) headquarters in Boise, Idaho.
August 9-11, 2021: (2.5 Standard, .5 OQ)
Traveled to Twin Falls and met with IGC company representatives in the Twin Falls district office for in-brief and
to begin field audit.
Regulator Stations
50003,50004,50005,50006,50007,50008,50009,50010,50011,50012,50013,50015,50016,50018,
50021,50022,50023,50024,50025,50026,50056,50072,50073,50074,50075,50076,50077,50136,50140,50143,
50150 and 50160 were inspected for proper operating parameters, regulator lock-up, relief device operation,
cathodic protection pipe-to-soil readings, pipe-to soil interface wrap protection, station warning signs and right-
Fourteen casing-to-carrier isolation checks, six cathodic protection rectifier, five pipeline patrols, and 10
emergency isolation valves were checked for proper operation.
An IPUC Form 3 (exit interview) was performed following the district inspection with Will Lindsey (Pipeline
Safety Specialist) of Intermountain Gas Company.
Observations:
Reg Stations: 50018 not plumbed for lock-up
Aug 12, 2021: (1.0) Standard)
Traveled back to Boise,completed forms and typed report
Attached:
IPUC Form 1, Inspection Summary
IPUC Form 3, Exit Interview
IPUC Field Equipment Status Worksheets
PHMSA Form 2, Standard Inspection of a Gas Distribution Operator(IA Version)
PHMSA Form 15 OQ Field
IPUC Form 1
Idaho PUC Pipeline Safety Inspection Summary
Corrective Action Required: Yes X No
Follow-up Required: by (date): 22 Feb 2022 Yes X No
Inspector (Lead): j Date:
Bruce Perkins 12-Aug-21
Reviewer: Date:
IPUC Form 1