HomeMy WebLinkAboutIntermountain Gas 211021 Filer NEO Construction Idaho PUC Pipeline Safety Inspection Summary
Inspector(s): Perkins/Brooks Date(s): See Below
20th, 21st Oct 2021
Company/Owner: New Energy One Unit/OPID: 40203/08160
Inspection Type &Time (1 day) Total Inspection Days:1 4
Standard: Construction:F4 Training: (T)(D) Integrity Management: Incident:
M/M: Follow-up: OQ: Damage Prevention: D&A:
Inspection Summary
Construction inspections were performed on Das-co, a contractor for New Energy One and Intermountain Gas
Company.
20 and 21 Oct 2021: (4.0 Construction and typed reports)
Observed Das-co crews excavating, pipe handling, and performing traffic control,fusing,tracer wire installation,
and backfilling. All procedures were followed.
Attachments:
IPUC Form 4 Construction Inspections
OQ's for all observed employees are located in file for the project.
Dig tickets
Corrective Action Required: Follow-up Required: Yes No X
Yes No X by (date):
Inspector (Lead): Date:
Perkins v' C%- �1 �C,__7 z e z t
Reviewer: Dater
IPUC Form 1