HomeMy WebLinkAboutIntermountain Gas 210901 Caldwell Construction Idaho PUC Pipeline Safety Inspection Summary
Inspector(s): I Perkins/Brooks I Date(s): 1-Sep-21
Company/Owner: Intermountain Gas Unit/OPID: 1 8160
Inspection Type &Time (1 day, 0.5 day) I Total Inspection Days:1—
StandardT-1 Construction: -2 Training: F7 (T)(D)Integrity Management: Incident:
M/M: F1 Follow-up: OQ: = Damage Prevention: D&A:
Inspection Summary
A construction inspection was performed on Das-co Utilities, a contractor for Intermountain Gas Company
1 Sept 2021 (2.0) construction,typed reports
Observed a Das-co Utilities crew installing new%" service line at 2416 Wyoming Ave, Caldwell Idaho. All
procedures were followed.
Areas observed during this project were: Excavating, pressure testing, riser install,tracer wire install, purging,
potholing, boring,JSA, IGC bagging the meter and squeezing.
Attachments:
IPUC Form 4 Construction Inspections
Das-co Utilities daily iteneraries located in file for the project.
OQ's for all observed employees are located in file for the project.
Pictures of job ticket.
Corrective Action Required: Yes I No X
Follow-up Required: by(date): Yes No X
Inspector(Lead): Date:
Bruce Perkins Bruce Perkins 1-Sep-21