HomeMy WebLinkAboutIntermountain Gas 210614-17 Hailey Construction Idaho PUC Pipeline Safety Inspection Summary
Inspector(s): Perkins/Brooks I Date(s): 6/14-17/2021
Company/Owner: Intermountain Gas Unit/OPID: 8160
Inspection Type &Time (1 day, 0.5 day) I Total Inspection Days:1 8
StandardT—1 Construction: 8 Training: F-] (T)(D)Integrity Management: Incident:
M/M: = Follow-up: OQ: Damage Prevention: D&A:
Inspection Summary
A construction inspection was performed on KV Utilities, a contractor for Intermountain Gas Company
14 Jun 2021 (2.0) construction)
Observed a KV Utilities crew installing new%" service line at 630 Elm St, Hailey, Idaho.All procedures were
followed.
Areas observed during this project were: Excavating, line locating, pressure testing, EFV install,
bedding/backfilling, riser install, tracer wire install, purging, potholing, boring,JSA, IGC bagging the meter and
squeezing.
15 Jun 2021 (2.0) construction)
Observed a KV Utilities crew installing new%" service line at 213 S 3rd St, Bellevue, Idaho. All procedures were
followed.
Areas observed during this project were: Excavating, line locating, riser install, purging, boring,JSA, welding and
tracer wire install.
16 Jun 2021 (2.0) construction)
Observed a KV Utilities crew installing new%" service line at 1591 and 1620 Red Feather Way, Hailey, Idaho.All
procedures were followed.
Areas observed during this project were: Excavating, line locating, riser install, purging,JSA, squeezing,
bedding/backfilling, pressure testing and tracer wire install.
17 Jun 2021 (2.0)travel/typed reports)
IPUC Form 1
Idaho PUC Pipeline Safety Inspection Summary
Attachments:
IPUC Form 4 Construction Inspections
KV Utilities daily iteneraries located in file for the project.
OQ's for all observed employees are located in file for the project.
Pictures of job ticket.
Corrective Action Required: Yes No X
Follow-up Required: by(date): If Yes No X
Inspector (Lead): Date:
Bruce Perkins 17-Jun-21
Reviewer: Date:
Darrin Ulmer al �3 ,v, Al
IPUC Form 1