Idaho P C ipeline Safety Inspection Summary
Inspector(s): Ulmer Date(s): 4/26-29/2021
Company/Owner: Intermountain Gas Unit/OPID: 8160
Inspection Type&Time (1 day, 0.5 day) Total Inspection Days: 4
Standard:F—] Construction:F4 Training: F7 (T)(D) Integrity Management: E] Incident: EJ
M/M: F7 Follow-up: F-1 OQ: F7 Damage Prevention: E] D&A:
Inspection Summary
A construction inspection was performed on KV Utilities, a contractor for Intermountain Gas Company.
April 26-27,2021 (2.0 construction)
Observed a KV crew's excavation practices while installing conduit at 118/120 Doral Dr,Jerome, ID. Excavation
included a back-hoe, hand-digging and rock-hammer for lava rock.
April 28-29,2021 (2.0 construction)
Observed a KV crew installing a new 3/4" PE service line at 3138 Boehm Estates Dr,Twin Falls, ID.
Areas observed during this project were: Excavating, pot holing, thumper-bore, service line installation,tracer
wire installation, stab fitting installation, riser setting, bedding and backfilling.
Attachments:
IPUC Form 4 Construction Inspections X2
KV daily itinerary
Corrective Action Required: Yes No X
Follow-up Required: by(dat Yes No X
Inspector (Lead): ffV� Date:
Reviewer: I Date:
IPUC Form 1