Loading...
HomeMy WebLinkAboutIntermountain Gas 210429 Hailey Construction Idaho PUC Pipeline Safety Inspection Summary Inspector(s): I Perkins, Brooks I Date(s): 29-Apr-21 Company/Owner: Intermountain Gas Unit/OPID: 1 8160 Inspection Type &Time (1 day, 0.5 day) Total Inspection Days: 1,ti Standard: ConstructionT.31 Training: (T)(D) Integrity Management: Incident: M/M: Follow-up: Oct: Damage Prevention: D&A: Inspection Summary An incident inspection was performed on KV, a contractor for Intermountain Gas Company 29 Apr 2021 (1.0) construction) Observed a KV crew repairing a line strike with gas leak on a service line from a 2" main on 105 Homestead Dr, Hailey, ID. All procedures were followed. Areas observed during this project were: Emergency response, line locating, excavation, and traffic control. Attachments: IPUC Form 4 Construction Inspections Corrective Action Required: Yes No X Follow-up Required: by(date): Yes No X Inspector (Lead): Date: Reviewer: Date: Alu .z IPUC Form 1