Inspector(s): Ulmer/Brook Date(s): 11-1an-21
Company/Owner: Intermountain Gas Unit/OPID: 8160
Inspection Type &Time (1 day, 0.5 day) Total Inspection Days: 2
Standard: Construction:E11 Training: (T)(D)Integrity Management: Incident:
M/M: Follow-up: OQ: Damage Prevention: D&A:
Inspection Summary
A construction inspection was performed on Das-Co, a contractor for Intermountain Gas Company
11 January 2021 (2 construction)
Observed a Das-co crew installing new 3/4" service line at 419 W 3rd St, Emmett, Idaho.All procedures were
followed.
Areas observed during this project were: traffic control, line locating, pot-holing, horizontal directional drilling,
pipe pulling, pipe prep, welding steel service-T,verified OQ's
Attachments:
IPUC Form 4 Construction Inspections
Das-co daily itineraries located in file for the project.
OQ's for all observed employees are located in file for the project.
Corrective Action Required: Yes No X
Follow-up Required: y(date): Yes Nol X