HomeMy WebLinkAboutIntermountain Gas 210414-15 Boise Construction Idaho PUC III i line Safety Inspection Summary
Inspector(s): I Ulmer I Date(s): 4/14-15/2021
Company/Owner: Intermountain Gas Unit/OPID: 1 8160
Inspection Type &Time (1 day, 0.5 day) Total Inspection Days: 2
$tandard:F—] Construction:F2 Training: F_� (T)(D)Integrity Management: =1 Incident: E]
M/M: = Follow-up: OQ: Damage Prevention: D&A:
Inspection Summary
A construction inspection was performed on Das-Co, a contractor for Intermountain Gas Company
14-15 Apr 2021 (2.0) construction)
Observed a Das-co crew installing a new W PE service line at 512 N Brookdale Dr, Boise, ID.All procedures were
followed.
Areas observed during this project were: Excavating, horizontal directional drilling, pipe handling, service line
installation,tracer wire installation, EFV installation, pressure testing, bedding and backfilling.
Attachments:
IPUC Form 4 Construction Inspections
Das-co daily itinerary
Misc. Photos
Corrective Action Required: Yes No X
Follow-up Required: bi(date): Yes I No X
Inspector(Lead): Date:
Reviewer: Date:
IPUC Form 1