HomeMy WebLinkAboutIntermountain Gas 210119 Boise Construction Idaho PUC Pipeli S fety Inspection Summary
Inspector(s): UI r I Date(s): 19-Jan-21
Company/Owner: Intermountain Gas Unit/OPID: 1 8160
Inspection Type &Time (1 day, 0.5 day) I Total Inspection Days:1 1
Standard:F7 Construction:FI Training: [7 (T)(D)Integrity Management: E] Incident: El
M/M: F7 Follow-up: F7 OQ: F7 Damage Prevention: E] D&A: E]
Inspection Summary
A construction inspection was performed on Das-Co, a contractor for Intermountain Gas Company
19 January 2021: (1 Construction)
Observed a Das-co crew installing new 3/4" service line at 9560 W Desert Ave, Boise, Idaho. All procedures
were followed.
Areas observed during this project were: line locating, potholing, boring (until generator went down) and
verified Ms.
Attachments:
IPUC Form 1 Inspection Summary
IPUC Form 4 Construction Inspections
Das-co daily itineraries
Corrective Action Required: Yes No X
Follow-up Required: (date): Yes No X
Inspector(Lead): Date:
Reviewer: Date:
IPUC Form 1