Loading...
HomeMy WebLinkAboutAvista 210626-29 Sandpoint Field Construction Idaho PUC Pipeline Safety Inspection Summary Inspector(s): Ulmer/Perkins Date(s): Jul 26-29, 2021 Company/Owner: Avista Utilities Unit/OPID: Sandpoint/31232 Inspection Type&Time (1 day, 0.5 day) Total Inspection Days: 8 Standard: 5.5 Construction: 1.5 Training: F7 (T)(D) Integrity Management: Incident: M/M: = Follow-up: OQ: Damage Prevention: D&A: Inspection Summary Audit consisted of inspecting field installed operating equipment and operator training for the Avista Sandpoint, Idaho inspection unit. Records and procedures for all Idaho Avista units were inspected March 16-17,2021 virtually from our office in Boise,Idaho. July 26,2021: (2 Standard travel) Traveled to Sandpoint, ID to conduct inspection. July 27,2021: (1.5 Standard, .5 OQ) Met with Avista company representatives in the Sandpoint, Idaho district office for in-brief and began field audit of Sandpoint installed equipment. Regulator Stations 200, 201, 208, 209A and 209B were inspected for relief operation, regulator lock-up and general condition of the station including pipe-to-soil wrap and corrosion. Two cathodic rectifiers, nine emergency valves, one patrol and one carrier-to-casing were inspected for the Sandpoint district. Observation: No deficiencies noted during inspection. IPUC Form 3 was conducted with Randy Bareither, Jim Kane,Jeff Lee, Steve Finney and Shawn Slinkard. July 28,2021: (1.5 Construction, .5 OQ) Observed an Avista crew replace an Aldyla main along 607 E 17th Ave in Post Falls, Idaho. Areas observed were excavation,pipe handling/placement,tracer wire installation, welding, service tie-ins, EFV installation, pressure testing,padding, and backfill. July 29,2021: (2 Standard travel) Traveled back to Boise, ID. Wrote the inspection report, completed audit forms. Attached: PHMSA IA Question Set,Field Inspection Portion(not attached but in IA database) PHMSA Form 15, OQ Field IPUC Form 1, Inspection Summary IPUC Form 3, Exit Interview IPUC Form 4, Construction Inspection IPUC Field equipment Work sheets IPUC Form 1 Idaho PUC Pipeline Safety Inspection Summary Corrective Action Required: Yes No X Follow-up Required: by(date): Yes No X Inspector(Lead): Date: Bruce Perkins Z y } z Reviewer: Date: r R IPUC Form 1