HomeMy WebLinkAboutAvista 210216-17 CRM Construction Idaho PUC Pipeline Safety Inspection Summary
Inspector(s): Perkins/Ulmer/Brooks Date(s): See below
11, 16-17 and 24 Feb 2021
Company/Owner: Avista Unit/OPID: CRM/31232
Inspection Type &Time (1 day, 0.5 day) Total Inspection Days: 8
Standard:F8 Construction: Training: a (T)(D) Integrity Management: Incident:
M/M: = Follow-up: OQ: Damage Prevention: D&A:
Inspection Summary
2021 Control Room Avista Utilities
11 February 2021: (1 Standard prep)
Prepared for Avista Utilities Control Room inspection through review of PHMSA IA question set and 2017
inspection results.
16-17 February 2021: (6 Standard)
Bruce Perkins, Darrin Ulmer, and Jeff Brooks completed a joint (Washington UTC and Oregon PUC)
virtual/teleconference audit of Avista's Control Room records, procedures and operations. The PHMSA IA
question set was used as a guide throughout the audit to ensure all areas were completed/covered.
Areas of Concern:See attached Post-Visit Verbal Briefing
24 February 2021: (1 Standard post )
Completed forms and typed report
Attached:
PHMSA Operator Qualification Inspection (IA version) 8154 Avista HQ Control Room Management
IPUC Form 1, Inspection Summary
IPUC Form 3, Exit Interview
Operator Document Records are located in: 1:\Pipeline\Inspections\2021\Avista CRM
Corrective Action Required: Yes No X
Follow-up Required: by(date): Yes No X
Inspector (Lead): Date:
Perkins /' �— 24-Feb-21
Reviewer: Date:
IPUC Form 1