HomeMy WebLinkAboutIntermountain Gas 221014 Meridian Construction Idaho PUC Pipeline Safety Inspection Summary
Inspector(s): Brooks, Galli Date(s): 10/14/2022
Company/Owner: Intermountain Gas Company (IGC) Unit/OPID: 1 8160
Inspection Type &Time (1 day, 0.5 day) Total Inspection Days: 2
Standard:FI Construction:F2 Training: F__1 (T)(D)Integrity Management: Incident:
M/M: = Follow-up: = oCt: F-1 Damage Prevention: D&A:
Inspection Summary
A construction inspection was performed on Das-Co, a contractor for Intermountain Gas Company.
14 October 2022 (2.0) construction,typed reports
IPUC inspectors observed contractors install new 3/4" PE service lines at 4973 and 5030 W Marysville St
Meridian, ID. Observations included trenching,tracer wire, EFV installations, line squeezing,butt fusions,
successful pressure tests at 90 psi for 30 minutes, leak tests,bedding, and backfilling. Quizzed employees on
AOC for fusion and pressure testing. All applicable procedures were followed in accordance with IGC Operation
Attachments:
IPUC Form 4 Construction Inspections
Daily itenerary located in file for the project.
OQ's for all observed employees are located in file for the project.
Job ticket, dig ticket and calibration photos
Corrective Action Required: Yes No X
Follow-up Required: by (date): Yes No X
Inspector(Lead): Date:
Brooks 10/14/2022
Reviewer: f' Date:
Galli i�, ,% 10/14/2022