HomeMy WebLinkAboutIntermountain Gas 220928 Kuna Construction Idaho PUC Pipeline Safety Inspection Summary
Inspector(s): 1perkins, Galli Date(s): 28-Sep-22
Company/Owner: I Intermountain Gas Company(IGC) Unit#/OPID 18160
Inspection Type &Time (1 day, 0.5 day) Total Inspection Days: 2
Standard: Construction:F2 Training: (T)(D)Integrity Management: Incident:
Gas Rule: Follow-up: Oct: Damage Prevention: D&A:
Inspection Summary
A constuction inspection was preformed on Probst Electric(Gas Division) a contractor of Intermountain Gas
Company.
28 September 2022 (1.0) construction,typed reports
IPUC inspectors observed contractors install (6) 3/4" service lines from a 2" unpressurized main throughout new
subdivision Shafer View in Meridian, ID. Job included: tracer wire, 3/4" PE service lines, stab fitting and bolt-on
saddle T's. Additionally, at 23536 Canyon Lane in Caldwell, ID, inspectors observed Probst crews install a 2"
service line approximately 1500 feet.
Attachments:
IPUC Form 4 Construction Inspections
Daily itenerary located in file for the project.
OQ's for all observed employees are located in file for the project.
Pictures of job ticket and other pertinent paperwork
Corrective Action Required: Yes No X
Follow-up Required: by(date): Yes No X
Inspector (Lead): '2 ' Date:
Perkins 9/28/2022
Reviewer: G Date:
Brooks