HomeMy WebLinkAboutIntermountain Gas 220803 Sugar City Construction Idaho PUC Pipeline Safety Inspection Summary
Inspector(s): JPerkins Date(s): 8/3/2022
Company/Owner: Intermountain Gas Company Unit/OPID: 08160
Inspection Type &Time (1 day, 0.5 day) I Total Inspection Days: 1.0
Standard: Construction: 1.0 Training: F__] (T)(D) Integrity Management: Incident:
Gas Rule: Follow-up: Oct: Damage Prevention: D&A:
Inspection Summary
A construction inspection was performed on Primoris, a contractor for Intermountain Gas Company.
3 August 22 (1.0) construction, typed reports
IPUC inspector observed a Primoris crew installing 2" HDPE lines as part of a total Sugar City Aldyl
replacement project. Crews were trenching,boring,pot holing,bedding,backfilling, and line locating. All
procedures were followed.
Attachments:
IPUC Form 4 Construction Inspections
OQ's for all observed employees are located in file for the project.
Pictures of job ticket and other pertinent paperwork
Corrective Action Required: Yes No X
Follow-up Required: by(dat : Yes I No X
Inspector(Lead): JDate:
Perkins � 8/3/2022
Reviewer: Date:
Brooks 7•
IPUC Form 1