HomeMy WebLinkAboutIntermountain Gas 220310 Star Construction Idaho PUC Pipeline Safety Inspection Summary
Inspector(s): Perkins Date(s): 10-Mar-22
Company/Owner: Intermountain Gas Unit/OPID: 1 8160
Inspection Type &Time (1 day, 0.5 day) Total Inspection Days:1 1
Standard: Construction:a1 Training: (T)(D) Integrity Management: Incident:
M/M: Follow-up: OQ: Damage Prevention: D&A:
Inspection Summary
A construction inspection was performed on Das-co Utilities, a contractor for Intermountain Gas Company
10 Mar 22 (1.0) construction,typed reports
Observed a Das-co crew installing a new W PE service line, utility line locating, excavating, bedding, shading,
tracer wire and pressure testing at 11557 W Soaring Hawk Ct, Star ID. AIIā¢procedures were followed.
Attachments:
IPUC Form 4 Construction Inspections
Das-co Utilities daily iteneraries located in file for the project.
OQ's for all observed employees are located in file for the project.
Pictures of job ticket.
Corrective Action Required: Yes No X
Follow-up Required: by(date): Yes No X
Inspector (Lead): Date:
Bruce Perkins ] 10-Mar-22
Reviewer: Date:
Jeff Brooks
IPUC Form 1