HomeMy WebLinkAboutIntermountain Gas 220119 Emmett Construction Idaho PUC Pipeline Safety Inspection Summary Inspector(s): JPerkins I Date(s): 19-Jan-22 Company/Owner: IGC/Das-Co Unit/OPID: 18160 Inspection Type &Time (1 day, 0.5 day) Total Inspection Days: 1 Standard: Construction:Fi_� Training: (T)(D) Integrity Management: Incident: Gas Rule: Follow-up: OQ: Damage Prevention: D&A: Inspection Summary A construction inspecton was performed on Das-co, a contractor for Intermountain Gas Company 19 Jan 2022 (1.0) construction) Observed a Das-co crew installing a 3/4" service line at 311 S Fuji Ave in Emmett, Idaho. All procedures were followed. Attachments: 1PUC Form 4 Contruction Inspection Daily inenerary located in file for the project OQ's for all observed employees are located in file for the project Pictures of job tickets/dig tickets Corrective Action Required: Yes No X Follow-up Required: by(date): Yes No X Inspector(Lead): �y Date: Perkins 19-Jan-22 Reviewer: Date: Brooks IPUC Form 1