HomeMy WebLinkAboutIntermountain Gas 220711-14 Pocatello Field Idaho PUC Pipeline Safety Inspection Summary Inspector(s): Perkins/Brooks/Galli I Date(s): 11-14 July 2022 Company/Owner: Intermountain Gas Company Unit/OPID: I Pocatello Inspection Type &Time (1 day, 0.5 day) Total Inspection Days:1 11 Standard:F10.0 Construction:71 Training: (T)(D)Integrity Management: Incident: M/M: = Follow-up: OQ: Damage Prevention: D&A: Inspection Summary Audit consisted of inspecting field installed equipment and operator qualification for the Pocatello, Idaho inspection unit. Records and procedures for all Idaho Intermountain Gas Units were inspected in March 2022 at the Intermountain Gas Company (IGC) headquarters in Boise, Idaho. January 24, 2022: (0.5 Standard Prep) Prepared IGC Pocatello Field Audit. July 11-13, 2022: (8.0 Standard, 1.0 OQ) Traveled to Pocatello and met with IGC company representatives in the Pocatello district office for in-brief,JSA and to begin field audit. Regulator Stations 48721-RS-59814, 48721-RS-60092,48721-RS-60076,48721-RS-59067, 48721-RS-59719, 48725-RS-60091,48725-RS-59826,48725-RS-59831, 48725-RS-60052,48725-RS-60082, were inspected for proper operating parameters, regulator lock-up, relief device operation, cathodic protection pipe-to-soil readings, pipe-to soil interface wrap protection, station warning signs and right-of-way clearances. One odorizer reading on regulator station 48725-RS-59831,twelve casing-to-carrier isolation checks, three cathodic protection rectifiers,ten pipeline patrols, and fifteen emergency isolation valves were checked for proper operation. An IPUC Form 3 (exit interview) was performed following the district inspection with Will Lindsey(Pipeline Safety Specialist) and Phil Colburn (Pocatello Operations Manager) of Intermountain Gas Company. Observed meter proofing and differential testing on 2 meters: 48717-gp-73516 failed 3 differential tests and then proof test were performed and successfully passed. Initial test using diffential method failed due to inconsistent flow; used a prover pump to provide consistent flow to the meter then passed using differential method. Meter 48725-gp-73754 had 2 differential tests ran and it passed both times. Observations: Reg Stations: 48721-RS-60092 primary failed lock-up due to weld slag on diaghragm 48725-RS-60082, Removed old ERX Post on secondary side due to corrosion concerns Jul 14, 2022: (1.5) Standard) Traveled back to Boise,completed forms and typed report IPUC Form 1 Idaho PUC Pipeline Safety Inspection Summary Attached: IPUC Form 1, Inspection Summary IPUC Form 3, Exit Interview IPUC Field Equipment Status Worksheets PHMSA Form 15 OQ Field Pictures of calibration certificates Corrective Action Required: Yes Na X Follow-up Required: by(date)---, ,, Yes No X Inspector (Lead): Date: Perkins F 14-Jul-22 Reviewer: Date: ql Brooks (— 7- /V IPUC Form 1