HomeMy WebLinkAboutIntermountain Gas 230816-17 Nampa Construction IPUC Construction Inspection
Inspector(s): Perkins (1.5) Galli (1.0) Date(s): 8/16-17/2023
Company/Owner: Unit/OPID: 08160
Intermountain Gas Company (IGC
Address: Franklin Rd/Star Rd City/District: Nampa
Contractor/Job #: Foreman: Employees: See job list
371-3185/23NG-1027/ Donald Teel
277750
Job Description: Install a 4" 60 PSI main Circle: Distribution & high-pressure extension
and 4" high-pressure extension
Operator Supervisor: IGC FOC Joe Delatore One-Call Ticket: 2023262200/2023281039
On-Site: Y
Total Inspection Days: 2.5
Tasks: Rating Critical Procedure # Comments
1. Materials—Handling, Storage, SAT OPS 11
Labeling
2. Trenching/Boring—Depth, Clearance SAT OPS 308
OPS 322
3. Bedding/Backfill SAT OPS 308
SF 418
4. Pipe Installation (Tracer Wire) SAT OPS 308
OPS 322
5. Valve Installation SAT OPS 703
6. Coating Condition SAT OPS 401
OPS 403
7. Manuals—Field Procedures, O & M SAT
8. Testing—Pressure, Duration, Type SAT OPS 505
9. OQ Qualifications SAT OPS 800
10. Casing Seal/Installation N/A OPS 325
11. Service Line Installation SAT OPS 302
12. Tie-In/Hot Tapping SAT OPS 600
13. Meter Location/Regulator Testing N/A OPS 302
14. Equipment Calibration Verification SAT OPS 501 Dates in file
15. EFV Installation SAT OPS 301
16. MAOP N/A OPS 602
OPS 606
OPS 900
OPS 1000
17. Pure SAT OPS 603
18. Safety Equipment SAT SF 418
SF 422
19. Abandonment N/A OPS 607
20. Line Locating SAT OPS 611
1 P U C Form 4 Rev. April 2023
IPUC Construction Inspection
21. Plastic Pipe SAT OPS 307
- Joiner(s) Qualified OPS 309
- Fusion Tools OPS 324
- Heat Plate OPS 325
- Joining Procedure OPS 800
22. Steel Pipe SAT OPS 200
-Welder(s) Qualified OPS 201
Pipe/Coating—Inspected/Repaired OPS 202
- Cathodic Protection OPS 306
-Non-Destructive Testing OPS 401
-Welding Procedures OPS 407
- Removal of asbestos wrap OPS 402
- Exothermic Welding OPS 403
4800
Additional Comments:
IPUC inspector Perkins observed Das-Co a contractor for IGC install 4" PE main and 4"high-pressure
main extension and service lines to two houses at Franklin Rd & Star Rd in Nampa, Idaho.
Observations included: Trenching, line locating, safety equipment, shore box install, pipe wrapping,
pipe stringing,purging, tracer-wire, 750 PSI nitrogen pressure test and 200 PSI integrity pressure hold
on steel line and 150 PSI air test on plastic line , welding on side pots, tapping and plugging, tie-in of
steel and plastic mains and electro-fusing, Quizzed employees on AOC recognition for trenching per
Idaho dig line law and shading/cover of pipelines. All procedures were observed in compliance with
IGCs Operations and Maintenance Manual.
Corrective Action Required: Yes No X
Follow-up Required: By Date: Yes No X
Inspector (Lead): Date: 08/17/2023
Perkins
Reviewer:
Date:
Brooks �• 01� •�
IPUC Form 4 Rev. April 2023