HomeMy WebLinkAboutIntermountain Gas 230814 Boise Construction IPUC Construction Inspection
Inspector(s): Galli, Brooks Date(s): 08/14/2023
Company/Owner: Unit/OPID: 08160
Intermountain Gas Company IGC
Address: 11467 W Mesquite St City/District: Boise
Contractor/Job#: Foreman: Employees: See job list
425-117577 & 425-116734 Librado Ruiz
Job Description: 1/4" Service Line install Circle: Distribution
Operator Supervisor: IGC FOC Jason One-Call Ticket: 311085
On-Site: Y
Total Inspection Days: 2
Tasks: Rating Critical Procedure # Comments
1. Materials—Handling, Storage, SAT OPS 11
Labeling
2. Trenching/Boring—Depth, Clearance SAT OPS 308
OPS 322
3. Bedding/Backfill SAT OPS 308
SF 418
4. Pipe Installation(Tracer Wire) SAT OPS 308
OPS 322
5. Valve Installation N/A OPS 703
6. Coating Condition N/A OPS 401
OPS 403
7. Manuals—Field Procedures, O & M SAT
8. Testing—Pressure, Duration, Type SAT OPS 505 90 psi for 15 minutes
9. OQ Qualifications SAT OPS 800
10. Casing Seal/Installation N/A OPS 325
11. Service Line Installation SAT OPS 302
12. Tie-In/Hot Tapping N/A OPS 600
13. Meter Location/Regulator Testing N/A OPS 302
14. Equipment Calibration Verification SAT OPS 501 Pyrometer exp 4/5/24
15. EFV Installation SAT OPS 301 EFV 1200
16. MAOP N/A OPS 602
OPS 606
OPS 900
OPS 1000
17. Pure N/A OPS 603
18. Safety Equipment SAT SF 418
SF 422
19. Abandonment N/A OPS 607
20. Line Locating SAT OPS 611
1PUC Form 4 Rev. April 2023
IPUC Construction Inspection
21. Plastic Pipe SAT OPS 307
- Joiner(s) Qualified OPS 309
- Fusion Tools OPS 324
- Heat Plate OPS 325
- Joining Procedure OPS 800
22. Steel Pipe N/A OPS 200
-Welder(s) Qualified OPS 201
Pipe/Coating—Inspected/Repaired OPS 202
- Cathodic Protection OPS 306
-Non-Destructive Testing OPS 401
- Welding Procedures OPS 407
- Removal of asbestos wrap OPS 402
- Exothermic Welding OPS 403
4800
Additional Comments:
IPUC inspectors Galli and Brooks observed Das-Co a contractor for IGC install a 1/4" service line at
11467 W Mesquite Way, Boise ID. Observations included: trenching, line locating, tracer wire,butt
fusion, stab fittings, EFV 1200 installation, squeeze off, successful pressure test at 90 psi for 15
minutes,bedding and backfill. All procedures were followed in accordance with IGC procedures.
Additionally, Das-Co crews discontinued a service line install at 11445 W Mesquite Way, Boise, ID due
to the casing under the driveway not being installed at the correct depth of 18 inches or more.
Corrective Action Required: Yes No X
Follow-up Required: By Date: Yes No X
Inspector (Lead):
Date: 08/14/2023
Galli
Reviewer:
Date: 08/14/2023
Brooks A=== I
IPUC Form 4 Rev. April 2023