HomeMy WebLinkAboutIntermountain Gas 230803 Middleton, Eagle, Star and Caldwell Construction I PUC Construction Inspection Inspector(s): Galli, Brooks Date(s): 08/03/2023 Company/Owner: Unit/OPID: 08160 Intermountain Gas Company IGC Address: 19384 & 19936 Susquehanna Way City/District: Caldwell Contractor/Job #: Foreman: Employees: See job list 317-24849 & 317-50952 Dominic Greco Job Description: 1/4" Service Line install Circle: Distribution Operator Supervisor: IGC FOC Kyle Russo One-Call Ticket: 282423 & 282424 On-Site: N Total Inspection Days: 2 Tasks: Rating Critical Procedure# Comments 1. Materials —Handling, Storage, SAT OPS 11 Labeling 2. Trenching/Boring—Depth, Clearance SAT OPS 308 OPS 322 3. Bedding/Backfill SAT OPS 308 SF 418 4. Pipe Installation (Tracer Wire) SAT OPS 308 OPS 322 5. Valve Installation N/A OPS 703 6. Coating Condition N/A OPS 401 OPS 403 7. Manuals—Field Procedures, O & M SAT 8. Testing—Pressure, Duration, Type SAT OPS 505 90 psi for 15 minutes 9. OQ Qualifications SAT OPS 800 10. Casing Seal/Installation N/A OPS 325 11. Service Line Installation SAT OPS 302 12. Tie-In/Hot Tapping N/A OPS 600 13. Meter Location/Regulator Testing N/A OPS 302 14. Equipment Calibration Verification SAT OPS 501 Pyrometer exp 4/5/24 15. EFV Installation SAT OPS 301 EFV 1200 16. MAOP N/A OPS 602 OPS 606 OPS 900 OPS 1000 17. Pure N/A OPS 603 18. Safety Equipment SAT SF 418 SF 422 19. Abandonment N/A I OPS 607 20. Line Locating SAT I OPS 611 1 P U C Form 4 Rev. April 2023 IPUC Construction Inspection 21. Plastic Pipe SAT OPS 307 -Joiner(s) Qualified OPS 309 - Fusion Tools OPS 324 - Heat Plate OPS 325 - Joining Procedure OPS 800 22. Steel Pipe N/A OPS 200 - Welder(s) Qualified OPS 201 Pipe/Coating—Inspected/Repaired OPS 202 - Cathodic Protection OPS 306 -Non-Destructive Testing OPS 401 - Welding Procedures OPS 407 - Removal of asbestos wrap OPS 402 - Exothermic Welding OPS 403 4800 Additional Comments: IPUC inspectors Galli and Brooks observed Das-Co a contractor for IGC install 1/4" service lines to 19396 & 19384 Susquehanna Way in Caldwell, ID. Observations included: trenching, line locating, tracer wire, butt fusion, stab fittings, EFV 1200 installation, squeeze off, successful pressure test at 90 psi for 15 minutes,bedding and backfill. Quizzed employees on applicable AOC for fusion, squeeze off and pressure testing. All procedures were followed in accordance with IGC procedures. In Middleton, ID, inspectors conducted a follow-up inspection to verify no differential pressure on the in-line strainer on regulator station#30125. Pressures were the same across the strainer and showed no signs of obstructions in the strainer. Additionally, inspectors Galli and Brooks performed spot checks in the following cities: • Eagle, ID on a patrol relocation (Job number 23NG-1016) • Middleton, ID on a 4" main install (Job number 23NG-1024) • Star, ID on a new service to a commercial property (Job number 23NG-3312) which was postponed due to Idaho Power construction activities. Corrective Action Required: Yes No X Follow-up Required: By Date: Yes No X Inspector(Lead): i� Date: 08/03/2023 Galli Reviewer: Date: 018/0.3112-02 Brooks g•�•a3 s IPUC Form 4 Rev. April 2023