HomeMy WebLinkAboutIntermountain Gas 230420 Caldwell Construction IPUC Construction Inspection Inspector(s): Perkins Date(s): 4/20/2023 Company/Owner: Unit/OPID: 08160 Intermountain Gas Company (IGC Address: 19752 Simplot Blvd City/District: Caldwell Contractor/Job #: Foreman: Contractor/Job #: 23NG-3155 German Gomez 23NG-3155 Job Description: 1200' 2" PE Service Circle: Distribution Operator Supervisor: Mingo One-Call Ticket: Yes On-Site: Yes 2023151553 Total Inspection Days: 1 Tasks: Rating Critical Procedure# Comments 1. Materials—Handling, Storage, N/A OPS 11 Labeling 2. Trenching/Boring—Depth, Clearance SAT OPS 308 OPS 322 3. Bedding/Backfill N/A OPS 308 SF 418 4. Pipe Installation (Tracer Wire) N/A OPS 308 OPS 322 5. Valve Installation N/A OPS 703 6. Coating Condition N/A OPS 401 OPS 403 7. Manuals—Field Procedures, O & M SAT 8. Testing—Pressure, Duration, Type N/A OPS 505 9. OQ Qualifications SAT OPS 800 10. Casing Seal/Installation N/A OPS 325 11. Service Line Installation N/A OPS 302 12. Tie-In/Hot Tapping N/A OPS 600 13. Meter Location/Regulator Testing N/A OPS 302 14. Equipment Calibration Verification N/A OPS 501 15. EFV Installation N/A OPS 301 16. MAOP N/A OPS 602 OPS 606 OPS 900 OPS 1000 17. Pure N/A OPS 603 18. Safety Equipment SAT SF 418 SF 422 19. Abandonment N/A OPS 607 20. Line Locating SAT OPS 611 1PUC Form 4 Rev. April 2023 I PUC Construction Inspection 21. Plastic Pipe N/A OPS 307 - Joiner(s) Qualified OPS 309 - Fusion Tools OPS 324 - Heat Plate OPS 325 - Joining Procedure OPS 800 22. Steel Pipe N/A OPS 200 - Welder(s) Qualified OPS 201 Pipe/Coating—Inspected/Repaired OPS 202 - Cathodic Protection OPS 306 -Non-Destructive Testing OPS 401 - Welding Procedures OPS 407 - Removal of asbestos wrap OPS 402 - Exothermic Welding OPS 403 4800 Additional Comments: IPUC inspector Perkins met with Das-Co a contractor for IGC at 19752 Simplot Blvd, Caldwell Idaho. Observations included: trenching, line locating and boring. All procedures were followed in accordance with IGCs Operations and Maintenance Manual, Federal Code, and Idaho Dig Line Laws. Corrective Action Required: Yes I No ix Follow-up Required: By Date: Yes No I x Inspector (Lead): Date: Perkins f - 4/20/2023 Reviewer: Date: Brooks 4/20/2023 1PUC Form 4 Rev. April 2023