Inspector(s): I Perkins, Galli I Date(s): 3/23/2023
Company/Owner: I Intermountain Gas Company (IGC) I Unit#/OPID 18160
Inspection Type&Time (1 day, 0.5 day) Total Inspection Days: 1
Standard: Construction: 1 Training: (T)(D)Integrity Management: Incident:
Gas Rule: Follow-up: n Oq: Damage Prevention: D&A:
Inspection Summary
A construction inspection was performed on Das-co a contractor for Intermountain Gas.
IPUC inspectors observed contractors prep for a 4" valve replacement near the intersection of Chinden and Star
Road. Observations included: trench safety, safety equipment, coal tar removal, welding of two 4" steel end caps
for pups and OQ verification. Job will need to be re-engineered due to the configuration of the valve not
matching as-built records.
Attachments
Construction Inspection Form 4
Das-Co Daily Line-Up
Operator Qualification Records
Corrective Action Required: Yes I Nol X
Follow-up Required: by (date):; Yes I Nol X
Inspector(Lead): ,