Inspector(s): I Brooks, Galli Date(s): 3/9/2023
Company/Owner: llntermountain Gas Company (IGC) Unit#/OPID 8160
Inspection Type &Time (1 day, 0.5 day) Total Inspection Days: 1
Standard: Construction: 1 Training: (T)(D)Integrity Management: Inadent
Gas Rule: Follow-up: 0 ' Damage Prevention: D&A:
Inspection Summary
A constuction inspection was performed on Track Utilities a contrator for Intermountain Gas Company.
March 9,2023: (1.0) Construction
IPUC Inspectors observed a Track Utilities crew install a 2 inch PE main with 3/ inch service stubs at 16145,
16146 and 16148 N Truman Ave in Eagle, ID. Observations included: proper trench clearance/depth,tracer wire,
saddle T's, stab fittings and bedding with sand. All activity was performed in compliance with IGC Operations
and Maintenance Manual.
Attachments:
Construction Inspection Form 4
Track Utilities Daily Line-Up
Operator Qualification Records
Corrective Action Required: Yes I Nol X
Follow-up Required: by (date):; Yes I Nol X