HomeMy WebLinkAboutIntermountain Gas 230126 IGC Nampa Construction Idaho PUC Pipeline Safety Inspection Summary Inspector(s): I Perkins, Brooks, Galli I Date(s): 26-Jan-23 Company/Owner: I Intermountain Gas Company (IGC) I Unit#/OPID 18160 Inspection Type&Time (1 day,0.5 day) Total Inspection Days: 3 Standard: Construction: F3 Training: (T)(D) Integrity Management: Incident: Gas Rule: Follow-up: Oct: Damage Prevention: D&A: Inspection Summary A construction inspection was preformed on Das-Co a contractor for IGC. IPUC inspectors observed IGC Crew and Das-Co abandon and divert approximately 200 feet of a 4" steel main to remove an existing patrol near the intersection of Lone Star and Cobblestone in Nampa, ID. Observations included: Bagging of adjacent house using IGC gas cart, tie-in/hot tapping x2, welded on a blow down valve by Das-Co Welder Bierwirth, purging with nitrogen and wrap removal using proper asbestos precautions. IGC FOC Russo and Del Torro were on-site. IGC QA Hall on-site. All procedures were followed in accordance with IGC Operation and Maintenance Manual. Attachments: Construction Inspection Form 4 DASCO Daily Line-Up Operator Qualification Records Corrective Action Required: Yes No X Follow-up Required: by (date): YesI Nol X Inspector (Lead): Perkins ,d7 Date: 1/26/2023 Reviewer: Date: Brooks 1/26/2023 IPUC Form 1