Inspector(s): Perkins/Galli Date(s): 10-Jan-23
Company/Owner: Intermountain Gas Company(IGC) Unit#/OPID 8160
Inspection Type & Time (1 day, 0.5 day) Total Inspection Days: 2
Standard: Construction: 2 Training: (T)(D) Integrity Management: Incident:
Gas Rule: Follow-up: OQ: Damage Prevention: D&A:
Inspection Summary
A construction inspection was performed on Das-Co, a contractor for Intermountain Gas Company.
10 January 23 (2.0) construction,typed reports
IPUC inspectors observed contractors (Das-Co) install a new 3/4" PE service line from a 2" steel main at 2409 N
28th St, Boise, ID. Observations included line locating, excavation, thumper bore, tracer wire, plastic butt fusing,
meter bar placement, successful pressure test, EFV installation, welding on tee, wax wrapping, line purging, gas
testing, and backfilling. All procedures were followed in accordance with IGCs Operations and Maintenance
Manual.
Attachments:
IPUC Form 4 Construction Inspections
Daily itenerary located in file for the project.
OQ's for all observed employees are located in file for the project.
Corrective Action Required: Yes No X
Follow-up Required: by(date): Yes No X
Inspector (Lead): ,f, / Date:
Perkins �`'" ,l' 1/10/2023
Reviewer: Date:
Brooks