Loading...
HomeMy WebLinkAboutIntermountain Gas 230417-18 Nampa LNG Audit Idaho PUC Pipeline Safety Inspection Summary Inspector(s): I Perkins, Brooks, Galli I Date(s): 4/17-18/2053 Company/Owner: lintermountain Gas Company (IGC) I Unit#/OPID 18160 Inspection Type&Time (1 day, 0.5 day) Total Inspection Days: 5 Standard: 5 Construction. Training: (T)(D)Integrity Management: Incident Gas Rule: Follow-up: OQ Damage Prevention: D&A: Inspection Summary IPUC inspectors conducted a records and field audit of IGCs Nampa LNG Facility. April 17, 2023: (3.0 Standard) Bruce Perkins, Jeff Brooks and Matt Galli of the Idaho Public Utilities Commission met with Intermountain Gas Company personnel Russ Nishikawa, Jacob Tschida, Dean Daniels, Tim Murray and Compliance Specialist Darrin Tinnerset at the Nampa LNG Facility to conduct an audit of records for plant operations for the 2022 calendar year. The PHMSA Inspection Assistant(IA)Program was used as a guide while reviewing multiple documents to include the Operations and Training Manuals, OQ records and inspection data and notes. An IA Post Inspection Preliminary Findings (exit interview)was performed following the inspection and sent to Colby Lundstrom, Compliance/Audit Manager and Russ Nishikawa,Nampa LNG Manager. April 1.8, 2023: (1.5 Standard, 0.5 Standard Post) Inspectors completed the 2022 records review and field inspection of the Nampa LNG facility.Parts on the field inspection will be completed during non-liquifaction times of the year(summer 2023). Completed forms and typed report.Recommendations are listed on IA Post Inspection Preliminary Findings. Discrepancies: IPUC inspectors observed discrepancies relating to recordkeeping of liquefaction cool down to specifically mention the inspection of"flanges, valves and seals" for leaks as stated in 193.2505(b). Additionally, inspectors would like to see the term "continual training"used in the monthly/annual logs to differentiate between initial and continual training. Recommended attaching a change sheet to the SEA Fire study and prevention plan. Attached: EPUC Form 1, Inspection Summary IA Post Inspection Preliminary Findings Supporting Documents Inspector (Lead): r� Bruce Perkins Date: 4/18/2023 Reviewer: Date: _. , ._. Jeff Brooks 4/18/2023 IPUC Form 1