HomeMy WebLinkAboutIntermountain Gas 240626 Eagle Construction PUC Construction Inspection
Inspector(s): Brooks Date(s): 6-26-24
Company/Owner: Unit/OPID: 08160
Intermountain Gas Company IGC)
Address: 44 N Fisher Park Way (Suites A-B) City/District: Eagle
400 Brookdale Dr Boise
Contractor/Job#: Foreman: Employees: Z. Rosales-Velazquez, J. Hernandez
09944-413, 13316-425 E. Call
Job Description: Install %" Service Lines System Type: ® Distribution ❑ Transmission
Operator Supervisor: Mingo One-Call Ticket: 250066, 250060
On-Site: N
Total Inspection Days: 1
Tasks: Rating Critical Procedure# Comments
1. Materials—Handling, Storage, SAT OPS 11
Labeling
2. Trenching/Boring—Depth, Clearance SAT OPS 308
OPS 322
3. Bedding/Backfill SAT OPS 308
SF 418
4. Pipe Installation (Tracer Wire) SAT OPS 308
OPS 322
5. Valve Installation N/A OPS 703
6. Coating Condition N/A OPS 401
OPS 403
7. Manuals—Field Procedures, O & M SAT
8. Testing—Pressure, Duration, Type N/A OPS 505
9. OQ Qualifications SAT OPS 800 Verified
10. Casing Seal/Installation N/A OPS 325
11. Service Line Installation SAT OPS 302
12. Tie-In/Hot Tapping N/A OPS 600
13. Meter Location/Regulator Testing N/A OPS 302
14. Equipment Calibration Verification SAT OPS 501 Verified
15. EFV Installation SAT OPS 301
16. MAOP N/A OPS 602
OPS 606
OPS 900
OPS 1000
17. Pure N/A OPS 603
18. Safety Equipment SAT SF 418
SF 422
19. Abandonment N/A OPS 607
20. Line Locating SAT OPS 611
IPUC Form 4 Rev. 12/21/2023
I PUC Construction Inspection
21. Plastic Pine SAT OPS 307 Rough Handling time
- Joiner(s) Qualified OPS 309 met.
- Fusion Tools OPS 324
- Heat Plate OPS 325
- Joining Procedure OPS 800
-Squeeze Off
22. Steel Pipe N/A OPS 200
- Welder(s) Qualified OPS 201
Pipe/Coating—Inspected/Repaired OPS 202
- Cathodic Protection OPS 306
- Non-Destructive Testing OPS 401
- Welding Procedures OPS 407
- Removal of asbestos wrap OPS 402
- Exothermic Welding OPS 403
4800
Additional Comments:
IPUC inspector Brooks observed Das-Co, a contractor for IGC install 3/4" service line(s) in Eagle, ID.
Addresses: 44 N Fisher Park Way(Suites A-B)
Observations Included: Excavation, trench depth, safety equipment, verification of OQs, equipment
calibrations, tracer wire, plastic butt fusion, riser placement, EFV 1200 installations,. Quizzed
employees on applicable fusion equipment inspections and related AOCs. All procedures were
followed in accordance with IGC Operations and Maintenance Manual.
Addresses: 400 N Brookdale Dr
Observations Included: Excavation, trench depth, safety equipment, verification of OQs, and back fill.
Gas service installation was not performed due to foreman recognizing an AOC involving new stub
length requirements. All procedures were followed in accordance with IGC Operations and
Maintenance Manual.
Corrective Action Required: Yes No X
Follow-up Required: By Date: Yes No X
Inspector(Lead): J
14 Date: 6-26-24