HomeMy WebLinkAboutIntermountain Gas 240417-18 Boise Construction I PUC Construction Inspection Inspector(s): Galli Date(s): 04/17-18/2024 Company/Owner: Unit/OPID: 08160 Intermountain Gas Company(IGC Address: 2911 W Taft St City/District: Boise Contractor/Job#: Foreman: Employees: See Job List 118175-425 German Gomez 1 Job Description: Install 3/4" Service Line(s) System Type: ® Distribution ❑ Transmission Operator Supervisor: Jason One-Call Ticket: 2024151854 On-Site: Y Total Inspection Days: 1.5 Tasks: Rating Critical Procedure# Comments 1. Materials—Handling, Storage, SAT OPS 11 Labeling 2. Trenching/Boring—Depth, Clearance SAT OPS 308 24 inches OPS 322 3. Bedding/Backfill SAT OPS 308 SF 418 4. Pipe Installation (Tracer Wire) N/A OPS 308 OPS 322 5. Valve Installation N/A OPS 703 6. Coating Condition N/A OPS 401 OPS 403 7. Manuals—Field Procedures, O & M SAT 8. Testing—Pressure, Duration, Type N/A OPS 505 9. OQ Qualifications SAT OPS 800 Verified 10. Casing Seal/Installation N/A OPS 325 11. Service Line Installation SAT OPS 302 12. Tie-In/Hot Tapping N/A OPS 600 13. Meter Location/Regulator Testing SAT OPS 302 14. Equipment Calibration Verification SAT OPS 501 Temp gun 1/5/2025 15. EFV Installation N/A OPS 301� 16. MAOP N/A OPS 602 OPS 606 OPS 900 OPS 1000 17. Pure N/A OPS 603 18. Safety Equipment SAT SF 418 JSA & Fire Extinguisher SF 422 19. Abandonment N/A OPS 607 20. Line Locating SAT OPS 611 IPUC Form 4 Rev. 12/21/2023 IPUC Construction Inspection 21. Plastic Pipe SAT OPS 307 - Joiner(s) Qualified OPS 309 - Fusion Tools OPS 324 - Heat Plate OPS 325 - Joining Procedure OPS 800 22. Steel Pipe N/A OPS 200 -Welder(s) Qualified OPS 201 Pipe/Coating—Inspected/Repaired OPS 202 - Cathodic Protection OPS 306 -Non-Destructive Testing OPS 401 -Welding Procedures OPS 407 - Removal of asbestos wrap OPS 402 - Exothermic Welding OPS 403 4800 Additional Comments: IPUC inspector Galli observed Das-Co a contractor for IGC install 3/4" service line(s) in Boise, ID. Address: 2911 W Taft St Boise, ID Observations Include: Traffic control, asphalt cutting, correct trench depth, line locating, safety equipment, verification of OQ records, verification of equipment calibrations, butt fusion and bedding. All observed procedures were conducted in accordance with IGCs Operations and Maintenance Manual. Corrective Action Required: Yes No X Follow-up Required: By Date: Yes No X Inspector(Lead): Date: 04/18/2024 Galli _-- Reviewer: Date: Brooks IPUC Form 4 Rev. 12/21/2023