Loading...
HomeMy WebLinkAboutIntermountain Gas 240415 Star Construction I PUC Construction Inspection Inspector(s): Galli, Brooks Date(s): 04/15/2024 Company/Owner: Unit/OPID: 08160 Intermountain Gas Company (IGC) Address: 6963 Campolina Way, City/District: Star 200 S Pecknhold Lane _ Contractor/Job#: Foreman: Employees: See Job List 009595-367. 9064-367 Juan Soto Job Description: Install 3/4" Service Line(s) System Type: x Distribution ❑ Transmission Operator Supervisor: Mingo One-Call Ticket: 2024133618, 2024140943 On-Site: N Total Inspection Days: 1.0 Tasks: Rating Critical Procedure # Comments 1. Materials—Handling, Storage, SAT OPS 11 l Labeling 2. Trenching/Boring—Depth, Clearance SAT OPS 308 OPS 322 3. Bedding/Backfill SAT OPS 308 Sand used SF 418 4. Pipe Installation(Tracer Wire) SAT OPS 308 14-gauge wire OPS 322 5. Valve Installation N/A OPS 703 6. Coating Condition N/A OPS 401 OPS 403 7. Manuals—Field Procedures, O & M SAT 8. Testing—Pressure, Duration, Type N/A OPS 505 9. OQ Qualifications SAT OPS 800 Verified 10. Casing Seal/Installation N/A OPS 325 11. Service Line Installation SAT OPS 302 12. Tie-In/Hot Tapping N/A OPS 600 13. Meter Location/Regulator Testing SAT OPS 302 14. Equipment Calibration Verification SAT OPS 501 Temp Gauge 2/23/2025 Pres Gauge 2/22/2025 15. EFV Installation N/A OPS 301 16. MAOP N/A OPS 602 OPS 606 OPS 900 OPS 1000 17. Pure SAT OPS 603 18. Safety Equipment SAT SF 418 Fire Extinguisher SF 422 19. Abandonment N/A OPS 607 20. Line Locating SAT OPS 611 IPUC Form 4 Rev. 12/2v2023 I PUC Construction Inspection 21. Plastic Pipe UNSAT OPS 307 3 failed butt fusions - Joiner(s) Qualified OPS 309 - Fusion Tools OPS 324 - Heat Plate OPS 325 - Joining Procedure OPS 800 22. Steel Pipe N/A OPS 200 -Welder(s) Qualified OPS 201 Pipe/Coating—Inspected/Repaired OPS 202 - Cathodic Protection OPS 306 -Non-Destructive Testing OPS 401 - Welding Procedures OPS 407 - Removal of asbestos wrap OPS 402 - Exothermic Welding OPS 403 4800 Additional Comments: IPUC inspector Galli observed Das-Co a contractor for IGC install 3/4" service line(s) in Star, ID. Address: 6963 Campolina Way, Star, ID Observations Include: Abandoned service line job due to no locates for live power. Address: 200 S Pecknhold Lane, Star, ID Observations Include: Correct trench depth, line locating, safety equipment, verification of OQ records, verification of equipment calibrations, tracer wire, failed butt fusions and bedding. Discrepancies: Three butt fusions failed visual acceptance criteria per ASTM F2620 due to not having even roll backs. The contractor employee was asked all three times if they are comfortable with the fusions. The third fusion showed uneven rollback and was put in the ground with bedding. IGC's compliance department was notified. FOC responded to have the pipe fusion cut out. Corrective Action Requir 1202406 NOPV Yes X No tETBy Follow-up Required: Date: 5/31/2024 Yes X No Inspector(Lead): Date: 04/16/2024 Galli Reviewer: Date: y- Brooks A-- 1PUC Form 4 Rev. 12/21/2023