Loading...
HomeMy WebLinkAboutIntermountain Gas 240415 Glenns Ferry Construction IPUC Construction Inspection Inspector(s): Perkins Date(s): 04/15/2024 Company/Owner: Unit/OPID: 08160 Intermountain Gas Company (IGC) Address: 875 E Cleveland Ave City/District: Glenns Ferry Contractor/Job#: Foreman: Employees: See Job List 24NG3099.1 Jesus Franco Job Description: Install 2" service System Type: ® Distribution ❑ Transmission Operator Supervisor: One-Call Ticket: 2024141507 On-Site: N [Totahlnspection Days: 1.0 Tasks: Rating Critical Procedure# Comments 1. Materials—Handling, Storage, SAT OPS 11 Labeling 2. Trenching/Boring—Depth, Clearance SAT OPS 308 Customer provided OPS 322 trench 36" depth 3. Bedding/Backfill N/A OPS 308 SF 418 4. Pipe Installation(Tracer Wire) SAT OPS 308 OPS 322 5. Valve Installation N/A OPS 703 6. Coating Condition N/A OPS 401 OPS 403 7. Manuals—Field Procedures, O & M SAT 8. Testing—Pressure, Duration, Type N/A OPS 505 9. OQ Qualifications SAT OPS 800 In folder 10. Casing Seal/Installation N/A OPS 325 11. Service Line Installation SAT OPS 302 Partial installation 12. Tie-In/Hot Tapping N/A OPS 600 13. Meter Location/Regulator Testing N/A OPS 302 14. Equipment Calibration Verification SAT OPS 501 Dates in folder 15. EFV Installation SAT OPS 301 5500 16. MAOP N/A OPS 602 OPS 606 OPS 900 OPS 1000 17. Pure N/A OPS 603 18. Safety Equipment SAT SF 418 SF 422 19. Abandonment N/A OPS 607 20. Line Locating SAT OPS 611 IPUC Form 4 Rev. 12/21/2023 IPUC Construction Inspection 21. Plastic Pine SAT OPS 307 - Joiner(s) Qualified OPS 309 - Fusion Tools OPS 324 - Heat Plate OPS 325 - Joining Procedure OPS 800 22. Steel Pine N/A OPS 200 -Welder(s) Qualified OPS 201 Pipe/Coating—Inspected/Repaired OPS 202 - Cathodic Protection OPS 306 -Non-Destructive Testing OPS 401 - Welding Procedures OPS 407 - Removal of asbestos wrap OPS 402 - Exothermic Welding OPS 403 4800 Additional Comments: IPUC inspector Perkins observed Das-Co, a contractor for IGC Install 2" service line in Glenns Ferry, ID. Address: 875 E Cleveland Ave Observations Include: (Customer provided trench, correct trench depth), safety equipment, fusing, verification of OQ records, tracer wire, setting of riser. Quizzed personnel on separation of gas lines from other utilities and rough handling procedures. All observed procedures were followed in accordance with IGC Operations and Maintenance Manual. Corrective Action Required: Yes No X Follow-up Required: By Date: Yes No X Inspector (lead): Perkins �./ /�G� �'t—� Date: 04/15/2024 Reviewer: V Brooks Date: , I6. IPUC Form 4 Rev. 12/21/2023