HomeMy WebLinkAboutIntermountain Gas 240326-28 Hailey Construction IPUC Construction Inspection
Inspector(s): Perkins Date(s): 03/26-28/2024
Company/Owner: Unit/OPID: 08160
Intermountain Gas Company (IGC)
Address: 1831 Heroic, 20 Copper Creek City/District: Hailey
Contractor/Job #: Foreman: Employees: See Job List
04739-521, 04740-521 Troy Anderson
Job Description: Install 3/" and 2" Service Line(s) System Type: ® Distribution ❑ Transmission
One-Call Ticket: 2024111797,2024120059
Total Inspection Days: 3.0
Tasks: Rating Critical Procedure# Comments
1. Materials—Handling, Storage, SAT OPS 11
Labeling
2. Trenching/Boring—Depth, Clearance SAT OPS 308
OPS 322
3. Bedding/Backfill SAT OPS 308
SF 418
4. Pipe Installation(Tracer Wire) SAT OPS 308
OPS 322
5. Valve Installation N/A OPS 703
6. Coating Condition N/A OPS 401
OPS 403
7. Manuals—Field Procedures, O & M SAT
8. Testing—Pressure, Duration, Type SAT OPS 505 100 PSI for 15 Min(3/4")
9. OQ Qualifications SAT OPS 800 In folder
10. Casing Seal/Installation N/A OPS 325
11. Service Line Installation SAT OPS 302
12. Tie-In/Hot Tapping SAT OPS 600
13. Meter Location/Regulator Testing SAT OPS 302
14. Equipment Calibration Verification SAT OPS 501 All dates in the folder
15. EFV Installation SAT OPS 301 EFV 1200 (3/4")
16. MAOP N/A OPS 602
OPS 606
OPS 900
OPS 1000
17. Puke SAT OPS 603
18. Safety Equipment SAT SF 418
SF 422
19. Abandonment N/A OPS 607
20. Line Locating SAT OPS 611
IPUC Form 4 Rev. 12/2v2023
IPUC Construction Inspection
21. Plastic Pipe SAT OPS 307
- Joiner(s) Qualified OPS 309
- Fusion Tools OPS 324
- Heat Plate OPS 325
- Joining Procedure OPS 800
22. Steel Pipe N/A OPS 200
- Welder(s) Qualified OPS 201
Pipe/Coating—Inspected/Repaired OPS 202
- Cathodic Protection OPS 306
-Non-Destructive Testing OPS 401
- Welding Procedures OPS 407
- Removal of asbestos wrap OPS 402
- Exothermic Welding OPS 403
4800
Additional Comments:
IPUC inspector Perkins observed KV-Utilities, a contractor for IGC Install 3/4" and 2" service line(s) in
Hailey, ID.
Address: 1831 Heroic (3/4" service) and 20 Copper Creek(2" Service)
1831 Heroic Ave-Observations Include: IGC personnel gas bagging residence, correct trench depth,
safety equipment, verification of OQ records, verification of equipment calibrations, stab fittings, tracer
wire, successful pressure test, EFV 1200 installation, bedded with sand and backfilled, line squeeze.
Quizzed personnel on squeeze times and separation between electrical conduit and gas line. All
observed procedures were followed in accordance with IGC Operations and Maintenance Manual.
20 Copper Creek-Observations Include: Correct trench depth, safety equipment, verification of OQ
records, verification of equipment calibrations, tracer wire,potholing, set riser,bedded with sand and
backfilled. Quizzed personnel on and separation between electrical conduit and gas line and bedding
below and above gas line. All observed procedures were followed in accordance with IGC Operations
and Maintenance Manual.
Corrective Action Required: Yes No X
Follow-up Required: By Date: Yes I No X
Inspector (Lead): Date: 03/29/2024
Perkins ?`� � �
Reviewer:
Brooks Date:
IPUC Form 4 Rev. 12/21/2023