HomeMy WebLinkAboutIntermountain Gas 240320.1 Caldwell Construction IPUC Construction Inspection
Inspector(s): Perkins Date(s): 03/20/2024
Company/Owner: Unit/OPID: 08160
Intermountain Gas Company (IGC)
Address: 606 Amber St City/District: Caldwell
Contractor/Job #: Foreman: Employees: See Job List
24NG 3081 Jesus Garcia
Job Description: Install 3/41' Service Line(s) System Type: ® Distribution ❑ Transmission
Operator Supervisor: N/A One-Call Ticket: 2024101807
On-Site: N
Total Inspection Days: 1.0
Tasks: Rating Critical Procedure# Comments
1. Materials—Handling, Storage, SAT OPS 11
Labeling
2. Trenching/Boring—Depth, Clearance SAT OPS 308
OPS 322
3. Bedding/Backfill SAT OPS 308
SF 418
4. Pipe Installation(Tracer Wire) SAT OPS 308
OPS 322
5. Valve Installation N/A OPS 703
6. Coating Condition SAT OPS 401
OPS 403 _
7. Manuals—Field Procedures, O & M SAT
8. Testing—Pressure, Duration, Type SAT OPS 505 96 PSI for 15 Min
9. OQ Qualifications SAT OPS 800 In folder
10. Casing Seal/Installation N/A OPS 325
11. Service Line Installation SAT OPS 302
12. Tie-In/Hot Tapping SAT OPS 600
13. Meter Location/Regulator Testing SAT OPS 302
14. Equipment Calibration Verification SAT OPS 501 All dates in the folder
15. EFV Installation SAT OPS 301 EFV 1200
16. MAOP N/A OPS 602
OPS 606
OPS 900
OPS 1000
17. Purge SAT OPS 603
18. Safety Equipment SAT SF 418
SF 422
19. Abandonment N/A I OPS 607
20. Line Locating SAT I OPS 611
IPUC Form 4 Rev. 12/21/2023
IPUC Construction Inspection
21. Plastic Pipe SAT OPS 307
- Joiner(s) Qualified OPS 309
- Fusion Tools OPS 324
- Heat Plate OPS 325
- Joining Procedure OPS 800
22. Steel Pipe SAT OPS 200 3/" Auto perf, welded
-Welder(s) Qualified OPS 201 onto 2" steel main
Pipe/Coating—Inspected/Repaired OPS 202
- Cathodic Protection OPS 306
-Non-Destructive Testing OPS 401
-Welding Procedures OPS 407
-Removal of asbestos wrap OPS 402
- Exothermic Welding OPS 403
4800
Additional Comments:
IPUC inspector Perkins observed Das-Co, a contractor for IGC Install 3/4" service line(s)in Caldwell,
ID.
Address: 606 Amber St
Observations Include: Correct trench depth, safety equipment, verification of OQ records, verification
of equipment calibrations, butt fusing(0), removal of tar coating, welded 3/4" auto perf to 2" steel
main,put grease and wax wrap on weld area, tracer wire, successful pressure test, EFV 1200
installation, bedded with dirt from excavation,backfill and continuity test. Quizzed personnel on trench
depths. All observed procedures were followed in accordance with IGC Operations and Maintenance
Manual.
Corrective Action Required: Yes No X
Follow-up Required: r;ByDe: Yes No X
Inspector(Lead):
/ Date: 03/20/2024
Perkins
Reviewer:
Date: 3 •a�
Brooks
IPUC Form 4 Rev. 12/21/2023