HomeMy WebLinkAboutIntermountain Gas 240318 Kuna Construction IPUC Construction Inspection Inspector(s): Perkins Date(s): 03/18/2024 Company/Owner: Unit/OPID: 08160 Intermountain Gas Company (IGC) Address: 2088/2102 E Pilsner St City/District: Kuna Contractor/Job #: Foreman: Employees: See Job List 011031-375 KC Osmus 012292-375 Job Description: Install 3/4" Service Line(s) System Type: ® Distribution ❑ Transmission Operator Supervisor: N/A One-Call Ticket: 2024100452 On-Site: N Total Inspection Days: 1.0 Tasks: Rating l Critical Procedure# Comments 1. Materials—Handling, Storage, SAT OPS 11 Labeling 2. Trenching/Boring—Depth, Clearance SAT OPS 308 _ OPS 322 3. Bedding/Backfill SAT OPS 308 Bedding with sand SF 418 4. Pipe Installation (Tracer Wire) SAT OPS 308 OPS 322 5. Valve Installation N/A OPS 703 6. Coating Condition N/A OPS 401 OPS 403 7. Manuals—Field Procedures, O & M SAT 8. Testing—Pressure, Duration, Type SAT OPS 505 96 PSI for 17 Min 9. OQ Qualifications SAT OPS 800 In folder 10. Casing Seal/Installation N/A OPS 325 11. Service Line Installation SAT OPS 302 12. Tie-In/Hot Tapping N/A OPS 600 13. Meter Location/Regulator Testing SAT OPS 302 14. Equipment Calibration Verification SAT OPS 501 All dates in the folder 15. EFV Installation SAT OPS 301 EFV 1200 16. MAOP N/A OPS 602 OPS 606 OPS 900 OPS 1000 17. Purge SAT OPS 603 18. Safety Equipment SAT SF 418 SF 422 19. Abandonment N/A OPS 607 20. Line Locating SAT OPS 611 IPUC Form 4 Rev. 12/2v2023 IPUC Construction Inspection 21. Plastic Pipe SAT OPS 307 - Joiner(s) Qualified OPS 309 - Fusion Tools OPS 324 - Heat Plate OPS 325 - Joining Procedure OPS 800 22. Steel Pipe N/A OPS 200 -Welder(s) Qualified OPS 201 Pipe/Coating—Inspected/Repaired OPS 202 - Cathodic Protection OPS 306 -Non-Destructive Testing OPS 401 -Welding Procedures OPS 407 -Removal of asbestos wrap OPS 402 - Exothermic Welding OPS 403 4800 Additional Comments: IPUC inspector Perkins observed Das-Co, a contractor for IGC Install 3/4" service line(s) in Kuna, ID. Address: 2088/2102 E Pilsner St Observations Include: Correct trench depth, safety equipment, verification of OQ records, verification of equipment calibrations, butt fusing(x4), tracer wire, successful pressure test, EFV 1200 installation, bedding with sand, backfill and continuity test. Quizzed personnel on applicable AOCs of squeeze off times and fusion procedures. All observed procedures were followed in accordance with IGC Operations and Maintenance Manual. Corrective Action Required: Yes No X Follow-up Required: By Date: Yes No X Inspector(Lead): Date: 03/18/2024 Perkins Reviewer: . \ Date: Brooks a+. P U C Form 4 Rev. 12/21/2023