HomeMy WebLinkAboutI202410 NOPV Response EXECUTIVE OFFICES
INTERMOUNTAIN GAS COMPANY
555 SOUTH COLE ROAD-P.O.BOX 7608• BOISE,IDAHO 83707• (208)377-6000• FAX:377-6097
September 16,2024
Mr.Jeff Brooks,Programs Manager
Idaho Public Utility Commission
PO Box 83720
Boise,ID 83720-0074
Subject:Response to the Notice of Probable Violation dated August 5,2024(Report#I202410)
Dear Mr.Brooks,
This letter is intended to address one(1)notice of probable violation stemming from a construction inspection
conducted by the Idaho Public Utilities Commission(IPUC)on July 24,2024,on service line 02251-621 of
Intermountain Gas Company(IGC)pursuant of Chapter 601 Title,49,United States Code.
PROBABLE VIOLATION
1. 49 CFR§ 192,605 Procedural manual for operations.maintenance.and emergencies.
(a) General. Each operator shall prepare and follow for each pipeline,a manual of written
procedures for conducting operations and maintenance activities and for emergency response.For
transmission lines,the manual must also include procedures for handling abnormal operations. This
manual must be reviewed and updated by the operator at intervals not exceeding 15 months,but at
least once each calendar year.This manual must be prepared before operations of a pipeline system
commence.Appropriate parts of the manual must be kept at locations where operations and
maintenance activities are conducted.
2. OPS 307 Polyethylene(PE) Main and Service Construction
5.3. Connections shall be made by butt fusion or electrofusion.
5.3.1. Mechanical fittings may be used for connections when space does not allow the use of a butt fusion
machine or electrofusion clamp,or when temperatures do not allow electrofusion.
Finding(s)•
IPUC staff observed a contractor for IGC build a service line on a trailer using(3)Continental Stab fittings
and a 1/4"Met Fit Tee.Per OPS 307,connections shall be made by butt fusion or electrofusion,unless space
does not allow the use of fusion machines and clamps.The majority of the service line was built on an open
trailer with adequate space for butt fusions.
Intermountain Gas Resgonse
IGC acknowledges the findings brought forth by the IPUC.While butt fusion and electrofusion are the preferred
connection methods, with IGC's current inventory of Continental Stab Fittings, it has been the intent to allow
the fittings to be used in lieu of butt fusion or electrofusion in order to burn down the remaining inventory.OPS
307—Polyethylene(PE)Main and Service Construction has been revised to provide clarification on the use of
Continental Stab Fittings.
Please contact Josh Sanders at(701)222-7773 with questions or comments.
Respectfully Submitted,
Pat Darras
Vice President,Engineering&Operations Services
Intermountain Gas Company
POLICY STATEMENT OPS 307
Cascade Natural Gas Corporation Polyethylene(PE) Main and Service Status: Released
Great Plains Natural Gas Co. Construction Revision Date:Sept.16,2024
Intermountain Gas Company OPSMOC-2266
Montana-Dakota Utilities Co. Page 1 of 32
PURPOSE
This procedure details construction requirements for the installation of Polyethylene (PE) mains and
service lines in MDU Utilities Group (MDUG)systems.
REFERENCES
External References:
49 CFR Part 192 Subpart F—Joining of Materials Other Than by Welding
49 CFR Part 192 Subpart G—General Construction Requirements for Transmission Lines and Mains
49 CFR Part 192 Subpart H—Customer Meters, Service Regulators, and Service Lines
49 CFR Part 192 Subpart M—Maintenance
49 CFT Part 192.283 Plastic pipe: Qualifying joining procedures
ASTM 2620-19 - Standard Practice for Heat Fusion Joining of Polyethylene Pipe and Fittings
GF Central Plastics Electrofusion Installation and Training Manual
GPTC Guide Material 192.317 Protection from hazards
GPTC Guide material 192.321 Installation of plastic pipe
MNOPS 216G.07— Protecting Public Facilities and Agricultural Land
National Electric Safety Code Rule 320135, 353, and 354
OAR 952-001-0070 (9) - Operators to Mark Underground Facilities or Notify Excavator that None Exist
Plastics Institute Technical Report 33 (TR-33) Generic Butt Fusion Joining Procedure for Field Joining of
Polyethylene Pipe WAC 480-93-115 -Casing of line pipes
TR 33—Appendix A
WAC 480-93-178- Protection of plastic pipe
Internal References:
CNG CP 860— Facilities Installation Diagram
OPS 1 — Management of Change
OPS 10—Gas Non-Emergency Notification and Reporting Requirements
OPS 103— Pipe and Pipeline Components
OPS 11 —Storage and Handling of Plastic Pipe and Components
OPS 204—Qualifying Plastic Joiners
OPS 301 — Excess Flow Valves
OPS 302—Gas Service Line Siting and Meter Sets
OPS 308—Gas Joint and Provided Trench Installations
OPS 309—Squeeze Off of Plastic Pipe
OPS 322—Trenchless Pipeline Installation
OPS 323— Plastic Pipe Insertion
OPS 324— Poly Vinyl Chloride (PVC)Joining and Repair
OPS 325—Casing, Sleeve, and Polyethylene (PE) Insertion Installations
OPS 327— Inspection, Evaluation, and Repair of Pipelines
OPS 407— Exothermic Welding Connections to Steel Pipelines
OPS 501 — Equipment Calibration, Maintenance, and Testing
OPS 505— Pressure Testing
OPS 603— Pipeline Purging and Cleaning
OPS 611 —Line Locating and Marking
OPS 625—Material and Construction Failure Reporting and Investigation
Forms:
CNG 315- Facilities Installation Diagram
CNG 315R—Service Line Remediation Record
CNG 336— Distribution Line Report
Form 23007—Customer Load Summary
IGC 319— Distribution Line Report
IGC 457 - Report of Damage and/or Repair
POLICY STATEMENT OPS 307
Cascade Natural Gas Corporation Polyethylene(PE) Main and Service Status: Released
Great Plains Natural Gas Co. Construction Revision Date:Sept.16,2024
Intermountain Gas Company OPSMOC-2266
Montana-Dakota Utilities Co. Page 2 of 32
IGC 512—Service Line Work Order
MDU/GPNG Task
TRAINING AND QUALIFICATION
Training is required for personnel who install and relocate PE mains and service lines. Training shall be
conducted by the Safety& Technical Training Department, or their designee. Subsequent training will be
conducted by the employee's manager or designee.
RECORD RETENTION
Record Retention Period Storage Location
Installation As-Built Documentation Life of pipeline Documentum or similar electronic repository.
DEFINITIONS
Refer to OPS 3 Master Glossary
SCOPE
This procedure applies to the installation and relocation of PE mains and service lines. Refer to OPS 327
— Inspection, Evaluation, and Repair of Pipelines for additional repair requirements. This procedure does
not apply to PVC. Refer to OPS 324 - Poly Vinyl Chloride (PVC) Joining and Repair.
PROCEDURE
1. Safety
1.1. When a potentially hazardous amount of gas is being vented into open air, sources of ignition
shall be removed from the area. A fire extinguisher shall be available.
1.2. Refer to OPS 309—Squeeze-Off of Plastic Pipe prior to performing a squeeze-off.
2. Material Inspection
2.1. New Pipe and Fittings:
2.1.1. Pipe and fittings with gouges or scratches exceeding 10% of wall thickness shall not
be installed.
2.1.2. Creased or folded material (e.g., kinked pipe) shall not be installed.
2.1.3. Each length of pipe and each fitting shall be visually inspected prior to installation to
ensure that it has no damage or defects that could impair its serviceability.
2.1.4. Materials suspected of being damaged or defective shall not be installed. Damages
or defects that did not occur during transportation, installation, or testing (e.g.,
damaged and defective material received from the manufacturer)shall be reported
via a Material and/or Component Failure Report (MCFR) JIRA ticket. Contractors
shall contact their MDUG representative (e.g., Field Operations Coordinator, Third-
Party Inspector, local District Management, etc.) immediately after identifying a
material failure. Refer to OPS 625—Material and Construction Failure Reporting and
Investigation.
2.1.5. Defective or damaged pipe and fittings discovered prior to being placed into service
shall be removed and discarded.
2.1.6. Refer to OPS 11 - Storage and Handling of Plastic Pipe and Components for loading,
hauling, and unloading requirements.
2.2. In-Service Pipe and Fittings:
2.2.1. When inspecting for gouges or scratches on in-service pipe and fittings, refer to
Appendix 1 of OPS 327— Inspection, Evaluation, and Repair of Pipelines, for pipe
inspection criteria and replacement parameters.
POLICY STATEMENT OPS 307
Cascade Natural Gas Corporation Polyethylene(PE) Main and Service Status: Released
Great Plains Natural Gas Co. Construction Revision Date:Sept.16,2024
Intermountain Gas Company OPSMOC-2266
Montana-Dakota Utilities Co. Page 3 of 32
3. Cutting
3.1. When cutting pipe to length before fusing, the pipe shall be cut using cutting tools which do
not introduce contamination to the pipe surfaces or the fusion equipment. Cutting shall be
performed using hand saws, reciprocating saws, run-around pipe cutters, guillotine cutters,
pipe sheers, or chain saws.
3.2. Liquid lubricants (for example, bar or chain oil or other lubricants)or soap transferred to the
pipe ends during cutting, shall be removed per the Cleaning Section of this procedure.
4. Cleaning
4.1. Cleaning shall be performed per the manufacturer's instructions, or when butt fusing per TR-
33 Appendix A.
4.2. If contamination cannot be removed per the manufacturer's instructions, or when butt fusing
per TR-33, wash the pipe with water and a clean cloth or paper towel, rinse the pipe with
water, and dry thoroughly with a clean dry, lint-free, non-synthetic cloth such as cotton or
paper towel.
4.3. If water or soap are used in the cutting process, the pipe surfaces shall be cleaned using
isopropyl alcohol and allowed to dry prior to facing.
4.4. Lubricants such as chain oil or drilling lubricants such as bentonite shall be removed from the
outside diameter and inside diameter of the fusion area with a 90% or greater isopropyl
alcohol on a clean cloth or paper towel or isopropyl alcohol wipe prior to scraping or facing.
5. Pipeline Installation
5.1. Plastic joints shall be made with procedures qualified per the requirements of§192.283 Plastic
pipe: Qualifying joining procedures.
5.1.1. The joining procedures referenced in this procedure are qualified per the
requirements of§192.283 Plastic pipe: Qualifying joining procedures. The
manufacture's qualifying procedure letters are available in the Guides & Resources
section of the MDUG Policy& Procedure (P&P) SharePoint site.
5.2. Company and Contractor personnel shall be qualified per the requirements of OPS 204—
Qualifying Plastic Joiners for applicable joining procedure being made (e.g., butt fusion,
electrofusion, external compression ring mechanical fitting, stab-type mechanical fitting, or
mechanical saddle). Each joint shall be visually inspected by the joiner or inspection personnel
that have the training and experience to inspect the type of joint being made.
5.3. Connections should be made by butt fusion or electrofusion.
5.3.1. Mechanical fittings (e.g., Met Fits) may be used for connections when space does not
allow the use of a butt fusion machine or electrofusion clamp, or when temperatures
do not allow electrofusion or butt fusion.
5.3.2. Existing inventories of socket fusion fittings, and stab fittings (e.g., Continental Stab
Fittings- Constab), may be used until current inventories are used and required butt
fusion and electrofusion tooling is acquired, or December 31, 2026.
5.4. Production to in-service connections:
5.4.1. Production to in-service connections of pipe larger than two (2") inches in diameter
shall be made with an electrofusion coupler. Production to in-service connection for
pipe larger than two (2") inches in diameter shall not be butt fused.
5.4.2. Production to in-service connections of pipe two (2") inches in diameter and smaller
shall be made with an electrofusion coupler, mechanical fitting, or butt fused.
5.4.3. Tie-ins for ongoing single projects (e.g., SSIP, Plats, Subdivisions) may be made by
butt fusion.
5.5. Polyamide 11 (PA-11) and PE pipe shall not be joined to each other.
5.6. Plastic joining manuals, procedures, and specification are available in the Guides &
Resources section of the MDUG P&P SharePoint site. Contractors can access manuals on
the manufacturer's website.
POLICY STATEMENT OPS 307
Cascade Natural Gas Corporation Polyethylene(PE) Main and Service Status: Released
Great Plains Natural Gas Co. Construction Revision Date:Sept.16,2024
Intermountain Gas Company OPSMOC-2266
Montana-Dakota Utilities Co. Page 4 of 32
5.6.1. George Fischer Central Plastics Electrofusion Installation and Training Manual.
5.6.2. Innogaz Electrofusion System Installation Procedure.
5.7. Main and service line extensions from steel pipe shall be made with an approved fitting and
transition. Unless approved by Corrosion Control, Engineering Services, or System Integrity,
steel to plastic transitions shall be installed without a stiffener/protective sleeve.
5.7.1. Refer to OPS 327— Inspection, Evaluation, and Repair of Pipelines for existing (in-
service)cathodic protection test reading requirements and coating condition, external
condition, and internal condition inspection and documentation requirements.
5.8. Refer to OPS 308- Gas Joint and Provided Trench Installations for joint trench and customer
provided trench installation requirements.
5.9. When inserting PE pipe into an abandoned steel pipeline, or when installing PE pipe in a
sleeve or casing refer to OPS 325—Casing, Sleeve, and Polyethylene (PE) Insertion
Installation.
5.10. Refer to OPS 327— Inspection, Evaluation, and Repair of Pipelines when temporary above
ground installations are required.
5.11. Butt fusions shall be made in accordance with TR-33 Appendix A.
NOTE: TR-33 was used to develop ASTM 2620-19, making the level of safety in TR-33 equivalent to
that of ASTM 2620-19.
5.11.1. New procedures require an MOC. Refer to OPS 1 — Management of Change.
5.11.2. MDPE may be butt fused to HDPE.
5.11.2.1. Connections (e.g., cross fusions) to Dupont Aldyl A MDPE, Uponor Aldyl A
MDPE and Phillips Driscopipe 7000 and 8000 HDPE shall not be made by
butt fusion.
5.11.3. Butt fusion is not recommended below negative 4°F without special provisions such
as a heated portable shelter(e.g., tent or trailer).
5.11.4. Protect fusion heater plates and fusion surfaces from unacceptable temperature
variations and possible contamination from wind and rain as needed.
5.11.5. Butt fusions made in ambient temperatures of 100°F and higher require additional
cooling time while in the clamp. The clamp shall not be removed until the fusion bead
is cool to the touch.
5.11.6. Avoid rough handling, pulling, installation and pressure testing for a minimum of an
additional 30 minutes after fusion has properly cooled.
5.11.7. A butt fusion joint shall be joined by a tool that holds the iron square to the ends of
the piping, compresses the heated ends together, and holds the pipe in proper
alignment while the plastic hardens.
5.11.8. Hydraulic butt fusion machine pressures shall be set using the butt fusion machine
manufacturer's recommendation for specific machine settings.
5.11.9. Heating tools shall be equipped with a thermometer or other built-in temperature
indicating device. Before the first fusion of the day, actual surface temperature of the
heater plate or adapter surface shall be checked with a pyrometer(infrared or
surface) calibrated per the requirements of OPS 501 - Equipment Calibration,
Maintenance, and Testing. The actual temperature of the heater plate or adapter
surface should be checked periodically through the day.
5.12. Electrofusion(s)shall be made in accordance with manufacturer specifications and
procedures.
5.12.1. Electrofusion fittings shall not be installed when ambient temperatures are below
negative 10°F or greater than 120°F.
5.12.2. Scraping/peeling shall be completed with an approved scraping tool. Scraping shall
not be performed with sandpaper, utility/emery cloth, wood rasps, metal files, or
grinders. A paint scraper should only be used in situations where confined working
space (e.g., proximity to other structures and utilities) requires a hand tool.
POLICY STATEMENT OPS 307
Cascade Natural Gas Corporation Polyethylene(PE) Main and Service Status: Released
Great Plains Natural Gas Co. Construction Revision Date:Sept.16,2024
Intermountain Gas Company OPSMOC-2266
Montana-Dakota Utilities Co. Page 5 of 32
5.12.3. Assure a minimum depth of.007"was scraped/peeled using one of the following
methods:
5.12.3.1. Preferred method: Physically scribe a scraping depth indicator mark, or
witness mark with an approved scribe tool (e.g., Marksman 007), onto the
pipe surface at intervals around the pipe. This mark scribes the pipe
surface to the depth of at least .006"while not removing more than 10% of
the pipe wall thickness. Removal of the minimum amount of.007"when
scraping/peeling will remove the scribe mark and provide visual
confirmation that adequate pipe surface has been removed by scraping.
5.12.3.2. Optional method: Mark the area to be peeled with an oil free permanent
marker at intervals around the pipe. Allow marks to dry before peeling. After
scraping/peeling witness marks shall be completely removed.
5.12.3.3. Optional method: Measure the thickness of the ribbon peeled for the pipe
with a micrometer calibrated per the requirements of OPS 501 - Equipment
Calibration, Maintenance, and Testing. The ribbon shall be at least .007"
but less than 10% of wall thickness of the pipe.
5.13. Mechanical joints or fittings installed after January 22, 2019, shall be Category 1 joint as
defined in ASTM F1924-12, providing a seal plus resistance to a force on the pipe joint equal
to, or greater than, that which will cause no less than 25% elongation of pipe, or the pipe fails
outside the joint area if tested.
5.13.1. Mechanical connections shall be made in accordance with manufacturer
specifications and procedures.
5.13.2. Stab type mechanical fittings shall not be installed after December 31, 2024.
5.14. Pipelines shall be protected from washouts, floods, unstable soil, landslide, and other hazards
that may cause the pipe to move or sustain abnormal loads.
5.14.1. Where pipelines cross areas that are not normally under water but are subject to
periodic run-off or flooding (e.g., near a river or runoff), the depth should be increased
to protect the pipeline from expected scour(washout), such as that expected from a
100-year flood.
5.14.2. When pipelines are installed over landfill areas where the supporting fill may
decompose, contact Engineering Services for pipe support requirements.
5.15. Pipelines shall not be permanently installed aboveground, either exposed or in a casing or
sleeve, or in a below grade enclosure or vault. Valve boxes are excluded from this
requirement.
5.16. Examples of trench configurations are shown in Appendices 4-15. Joint trench configurations
may vary with the addition or exclusion of other utilities. The selected joint trench configuration
shall meet the requirements of the utilities sharing the trench and easement, city, county, or state
requirements. The following are the minimum radial separation distances of utilities (e.g.,
horizontal/perpendicular crossings and paralleling main/service):
5.16.1. PE pipelines should be installed with at least four(4") inches of clearance from other
underground utilities, (excluding electric) and structures. For electric clearance
requirements refer to Section 5.16.2.
5.16.1.1. If minimum clearance cannot be attained, the pipeline shall be protected
from damage that might result from its proximity to other structures and
utilities, excluding electric. For electric clearance requirements refer to
Section 5.16.2. Examples of protective measures are placing sandbags,
rock shield, PVC, or FRP half sleeve between the pipe and the foreign
utility to prevent contact and wear.
5.16.1.2. In WASHINGTON, plastic pipelines paralleling other utilities shall have a
minimum of 12" of separation from the other utilities, and plastic pipelines
perpendicular(e.g., crossing)to other utilities shall have a minimum of six
(6") inches of clearance of separation from other utilities, excluding electric.
POLICY STATEMENT OPS 307
Cascade Natural Gas Corporation Polyethylene(PE) Main and Service Status: Released
Great Plains Natural Gas Co. Construction Revision Date:Sept.16,2024
Intermountain Gas Company OPSMOC-2266
Montana-Dakota Utilities Co. Page 6 of 32
For electric clearance requirements refer to Section 5.16.2. Where
minimum separation is not possible, adequate precautions, such as
inserting the plastic pipeline in conduit, shall be taken to minimize potential
hazards resulting from the close proximity to the other utilities.
5.16.2. At least 12"separation should be maintained when crossing or paralleling electric(direct
bury or in conduit).
5.16.2.1. When 12"separation cannot be maintained, mechanical protection is to be
used to limit the likelihood of detrimental heat transfer to gas facilities.
Examples of protective measures are placing sandbags, rock shield, PVC,
or FRP half sleeve between the pipe and the foreign utility to prevent
contact and wear.
5.16.2.2. Electric separation should be discussed with all parties involved prior to
installation.
5.16.3. Service lines may be installed in a sleeve or by bore with communication conduits(e.g.,
phone, cable,fiberoptic, etc.). Minimum separation should be maintained outside of the
sleeve or bore, see Appendices 10-15. Service lines shall not be installed in a sleeve or
by bore with electric.
5.17. Pipelines shall not be installed within the influencing area (typically 10') of any system that
radiates temperatures above 100°F. If there is a concern that this may occur, contact
Engineering Services.
5.18. Pipelines shall not be installed or operated under enclosed structures without approval from
Engineering Services and the installation of proper casings, seals, and vents. Refer to OPS
302—Gas Service Line Siting and Meter Sets for service line requirements.
5.19. Pipelines installed in a navigable stream, river, or harbor shall be installed with a minimum
cover of 48", or 24" in consolidated rock, from the top of pipe and the underground natural
bottom and shall meet permitting agency requirements.
5.20. Two (2") inch and smaller pipe should be snaked in the trench to allow for movement of the
pipe.
5.21. Each field bend of PE pipe shall comply with the following:
5.21.1. PE pipe shall not be installed with a bend radius that is less than the minimum bend
radius specified by the manufacturer for the diameter of the pipe being installed.
5.21.2. Each bend shall have a smooth contour and be free from buckling, cracks, or other
mechanical damage.
5.21.3. Lengths of PE pipe installed without fittings shall not be bent to a radius smaller than the
following minimum values:
Pie Minimum Allowed Bend Radius
2" IPS 5'
4" IPS 10,
6" IPS 14'
8" IPS 18'
5.21.4. Lengths of PE pipe installed with fittings(e.g., couplers, in-line tees, etc.)shall not be
bent to a radius smaller than the following minimum values:
Pipe with Fittings Minimum Allowed Bend Radius
2" IPS 20'
4" IPS 38'
6" IPS 56'
8" IPS 72'
5.22. Cover and Backfill:
POLICY STATEMENT OPS 307
Cascade Natural Gas Corporation Polyethylene(PE) Main and Service Status: Released
Great Plains Natural Gas Co. Construction Revision Date:Sept.16,2024
Intermountain Gas Company OPSMOC-2266
Montana-Dakota Utilities Co. Page 7 of 32
5.22.1. Backfill, including compaction specifications, shall be performed per the requirements
of governing/permitting agencies.
5.22.2. Mains shall be installed with a minimum of 30"of cover in soil or 24" in consolidated
rock.
5.22.2.1. Service lines converted to main do not require the minimum depth
requirements in Step 5.22.1. Refer to Company procedures and practices
for service line conversions.
5.22.2.2. When required by the permitting agency, the main or service line shall be
installed at the depth required by the permitting agency.
5.22.2.3. Mains and service lines installed in cultivated agricultural areas should
have a minimum of 54" of cover at the time of installation.
5.22.2.3.1. Where an underground structure prevents installation at those
depths, the service line shall be able to withstand anticipated
external loads.
5.22.2.4. In Minnesota, mains and service lines installed in cultivated agricultural
areas shall have a minimum of 54" of cover at the time of installation.
5.22.2.4.1. Where an underground structure prevents installation at those
depths, the service line shall be able to withstand anticipated
external loads.
5.22.3. Bottom of ditch shall be clean and free of rock or other hard objects. The pipe shall
be uniformly and continuously supported over its entire length on firm stable material.
5.22.3.1. When native material is not clean and free of rock or debris, pipe shall be
bedded with six (6") inches of bedding material that consist of well graded
from course to fine, non-corrosive sand, or non-fractured gravel not
exceeding one-fourth (1/4") inch minus in size (typically sand).
5.22.4. Ensure the ditch wall is clean and free of rock or other hard objects. If the ditch wall
adjacent to the pipe is not clean and free of rocks or other hard objects, maintain three
(3") inches from the ditch wall.
5.22.5. Pipe shall be shaded with six(6") inches of material that is clean and free of rock and
debris.
5.22.5.1. When native material is not clean and free of rock or debris, pipe shall be
shaded with six (6") inches of shading material that consist of well graded
from course to fine, non-corrosive sand, or non-fractured gravel not
exceeding one-fourth (1/4") inch minus in size (typically sand).
5.22.6. Except for purge locations, distribution pipelines shall be shaded with six (6")inches of
cover prior to pressure testing. Refer to OPS 505—Pressure Testing or contact
Engineering Services for high pressure pipeline and transmission pipeline requirements.
5.22.7. When required by the permitting agency, warning tape shall be installed
approximately 18" below finish grade.
5.22.8. Native soil may be used to backfill the remainder of the trench unless other materials
are specified by the permitting agency or property owner. Final backfill should not
include trash and debris.
5.22.9. In all states, except Oregon if determined to be necessary by Field Operations, upon
completion of installation of underground facilities, the facilities shall be marked per
the requirements of OPS 611 — Line Locating and Marking prior to leaving the job
site.
5.22.9.1. In Oregon, in areas of ongoing excavation or construction, operators must
mark newly installed underground facilities immediately upon placement.
As per the requirements of OPS 611- Line Locating and Marking.
5.23. Standard Service Line Installations:
5.23.1. Standard service line diameter is three-fourths (1/") inch IPS unless one (1") inch, two
(2") inch, or four(4") inch is specified on the Customer Load Summary— Form 23007,
POLICY STATEMENT OPS 307
Cascade Natural Gas Corporation Polyethylene(PE) Main and Service Status: Released
Great Plains Natural Gas Co. Construction Revision Date: Sept. 16,2024
Intermountain Gas Company OPSMOC-2266
Montana-Dakota Utilities Co. Page 8 of 32
or when a larger diameter is required per OPS 301 - Excess Flow Valves. Refer to
OPS 301 - Excess Flow Valves for EFV and service line sizing requirements.
5.23.1.1. Low pressure and five (5) psig distribution pressure service lines shall be
sized per the following tables.
Low Pressure System (< one (1) psig) Service Line Capacity
In Cubic Feet Per Hour with a Pressure Drop of 0.3 Inches Water Column
Length of Service Nominal Pipe Size Inches
Line (Feet) 3/" 1" 2"
20 215 400 1,950
30 170 315 1,550
40 145 265 1,300
50 125 235 1,150
60 115 210 1,050
70 110 190 975
80 105 175 905
90 100 166 845
100 95 155 795
125 90 140 700
150 85 135 630
175 80 125 575
200 70 120 530
Contact Engineering Services for Service Lines longer than 200' or larger than two (2") inches.
Assumes a minimum main pressure of five 5" Inches Water Column and IPS SDR-11 plastic pipe.
Five (5) psig Distribution Pressure System Service Line Capacity
in Cubic Feet Per Hour with a Pressure Drop of 0.3 psig
Length of Service Nominal Pipe Size (Inches)
Line (Feet) %11 1" 2"
20 1,585 2,700 8,850
30 1,260 2,300 8,800
40 1,070 1,950 8,700
50 945 1,700 8,450
60 850 1,550 7,600
70 780 1,400 7,000
80 725 1,300 6,500
90 675 1,200 6,050
100 635 1,150 5,700
125 560 1,000 5,050
150 505 925 4,550
175 460 850 4,200
200 430 785 3,850
Contact Engineering Services for Service Lines longer than 200' or larger than two (2")inches.
Assumes a minimum main pressure of three 3psig and IPS SDR-11 plastic pipe.
5.23.2. Service lines less than two (2") inches in diameter shall have at least 18" cover on
private property and at least 24" cover in the right-of-way (ROW).
5.23.2.1. A minimum 24" of cover is preferred over service lines on private property
and in the ROW in non-rock type soil.
POLICY STATEMENT OPS 307
Cascade Natural Gas Corporation Polyethylene(PE) Main and Service Status: Released
Great Plains Natural Gas Co. Construction Revision Date:Sept.16,2024
Intermountain Gas Company OPSMOC-2266
Montana-Dakota Utilities Co. Page 9 of 32
5.23.2.2. In consolidated rock, service lines shall be installed with a minimum of 18"
of cover in the ROW and 12" cover on private property. Caliche is not
considered consolidated rock.
5.23.2.3. Exceptions to minimum cover in non-rock type soils require the approval of
local Field Operations Management and the Engineering Services, or
System Integrity Manager. The approval shall be documented on the
service line As-Built.
5.23.2.4. When required by the permitting agency, the service line shall be installed
at the depth required by the permitting agency.
5.23.2.5. Service lines two (2") inches and larger in diameter should be installed at
main depth requirements. Exception to this step would include areas near
the riser where depth may be less than main depth requirements due to
bury line requirements of anodeless service risers.
5.23.2.6. For cultivated agricultural areas refer to the Cover and Backfill Section of
this procedure.
5.23.3. Beginning December 31, 2024, three-fourths (3/4") inch, one (1") inch, and two (2")
inch service line extensions from PE main shall be made with electrofusion service
punch tees, unless approved by Engineering Services.
5.23.3.1. Service lines extending from PE main may be installed with in-line tees.
5.23.4. Three-fourths (3/4") inch connections shall be made by butt fusion.
5.23.4.1. Mechanical fittings may be used when space does not allow the use of a
butt fusion machine.
5.23.5. One (1") inch and larger connections shall be made by butt fusion or electrofusion.
5.23.5.1. Mechanical fittings may be used when space does not allow the use of a
butt fusion machine or electrofusion clamp.
5.23.6. Standard installation height for anodeless service risers (ASR) is determined by the
manufacturers DO NOT BURY line recommendations. The DO NOT BURY line (e.g.,
Red Line) shall be above final grade. Allow room for future fill or landscape. Refer to
OPS 302—Gas Service Line Siting and Meter Sets.
5.23.7. Refer to OPS 302—Gas Service Line Siting and Meter Sets when an ASR riser is
likely to be set in a hard surface (e.g., concrete or asphalt). Stiffeners are not
required at the pigtail of an ASR.
5.24. Exhibit 1 outlines potential inspectable items.
6. Tracer Wire and Locate Test Stations
6.1. PE pipe shall be installed with a minimum 14-gauge wire. Refer to OPS 103— Pipe and
Pipeline Components and OPS 322—Trenchless Pipeline Installation for trenchless
installation wire requirements.
6.2. Tracer wire connections shall be made with MDUG approved connectors.
6.3. Tracer wire shall not be brazed or soldered.
6.4. Tracer wire shall be connected in a way to protect the connection for pulling/tension, typically
by wrapping the wire around the pipe with a half hitch.
6.5. Transition fitting tracer wire connections shall be made with the supplied tracer wire
connection or exothermic weld (e.g., cad weld). Refer to OPS 407 - Exothermic Welding
Connections to Steel Pipelines.
6.6. Transition fitting tracer wire for main shall terminate into an above ground or flush mount
locate test station. A test lead from the steel main connection shall terminate in the same
locate test station. The PE tracer wire and the lead from the steel main should not be
connected to the same locate test station terminal. Wire configurations shall be installed per
brand specific standards. Refer to Appendix 1 —CNG, MDU, and GPNG Transition Fitting
POLICY STATEMENT OPS 307
Cascade Natural Gas Corporation Polyethylene(PE) Main and Service Status: Released
Great Plains Natural Gas Co. Construction Revision Date:Sept.16,2024
Intermountain Gas Company OPSMOC-2266
Montana-Dakota Utilities Co. Page 10 of 32
Tracer Wire Configuration. In IDAHO refer to Appendix 2 — IGC Transition Fitting Tracer Wire
Configuration.
6.7. Tracer wire at end of mains shall terminate above ground.
6.7.1. If the end of main terminates under a hard surface (e.g., asphalt or concrete), the
tracer wire should terminate in a flush-mount locate test station.
6.7.2. An underground locate device (e.g., zinc locate coupon, magnesium anode or marker
ball)should be installed at the end of main.
6.7.2.1. The connection shall be spliced below ground as near the end of main as
possible.
6.7.2.2. The location of the underground locate device shall be identified on the As-
Built drawing.
6.8. Transition fitting tracer wire for service lines shall be directly connected to the transition fitting.
6.8.1. A locate coupon or magnesium anode should be installed at the base of the ASR.
6.8.1.1. Install locate coupon in the same trench as the service line without allowing
the coupon to be in direct contact with the ASR.
6.8.1.2. The location of the locate coupon/magnesium anode shall be identified on
the As-Built drawing.
6.8.2. Refer to Appendix 3— MDUG PE Service Line with Steel Main Wire Configuration.
6.9. A locate test station shall be installed approximately every 1000', but no further than 1500'
apart.
6.9.1. A zinc coated locate coupon or magnesium anode should be installed at test stations
or at tie-in locations to existing systems on main extensions when under 1000 feet.
6.9.2. Locate coupon/magnesium anode wire lead shall terminate in the test station. A
single locate wire shall be spliced into the PE tracer wire and terminate in the same
test station. Locate coupon/magnesium anode wire lead and PE tracer wire shall not
be spliced together below ground.
6.9.3. New main with service lines spaced less than 1000' (e.g., plats, subdivisions)do not
require test stations.
6.9.4. The location of the locate coupons/ magnesium anodes and locate test stations shall
be identified on the As-Built drawing.
6.10. Wire should be installed immediately adjacent to the pipe or separated approximately two (2")
inches to six (6") inches from the pipe. Wire should not be wrapped around the pipe, including
wire connections (half hitch). Except for trenchless installations, wire should not be taped to
the pipe. Refer to OPS 322 —Trenchless Pipeline Installation.
6.11. A continuity check of tracer wire (e.g., line locate) should be made after pipeline installations.
6.11.1. New wire connections that do not have continuity shall be repaired. Existing wire or
wire connections that do not have continuity shall be reported to local Field
Operations Management, or their designee.
7. Care and Maintenance of Tools
7.1. Equipment used in joining PE pipe shall be maintained in accordance with the manufacturer's
recommended practices or procedures.
7.2. Heat fusion equipment shall be free of rust, corrosion, dirt, and/or molten plastic residue that
can impair the quality of fusion joints.
7.3. After each use, remove melt residue from the heater surface with a soft wooden stick or by
wiping with a clean dry, lint-free, non-synthetic cloth such as cotton or paper towel.
7.4. Faceplates shall not be changed while the tool is hot. Bolts should be tightened carefully to
prevent stripping. High temperature anti-seize lubricant should be used on faceplate bolts to
minimize galling.
POLICY STATEMENT OPS 307
Cascade Natural Gas Corporation Polyethylene(PE) Main and Service Status: Released
Great Plains Natural Gas Co. Construction Revision Date:Sept.16,2024
Intermountain Gas Company OPSMOC-2266
Montana-Dakota Utilities Co. Page 11 of 32
7.5. Malfunctioning equipment shall not be used and will be repaired or replaced.
8. Documentation
8.1. As-Built documents shall be completed in accordance with MDUG Gas As-Built
Documentation Guidance Document located on the P&P SharePoint site.
8.2. Cascade Natural Gas:
8.2.1. Main installation shall be documented on CNG 336— Distribution Line Report.
8.2.2. Service Line installation and relocations shall be documented per the requirements of
CNG CID 860— Facilities Installation Diagram.
8.3. Intermountain Gas:
8.3.1. Main installation, including relocations 15' or longer, shall be documented on IGC
319— Distribution Line Report.
8.3.2. Service line installations and relocations shall be documented on IGC 512—Service
Line Work Order.
8.3.3. Main relocation less than 15' shall be documented on IGC 457—Report of Damage
and/or Repair.
8.4. Montana-Dakota Utilities and Great Plains Natural Gas:
8.4.1. Main and service line installations and relocations shall be documented in PCAD and
when applicable Task Forms.
8.5. Documentation not completed on As-Built documents shall be documented in approved
compliance tracking software (e.g., Maximo).
POLICY STATEMENT OPS 307
Cascade Natural Gas Corporation Polyethylene(PE) Main and Service Status: Released
Great Plains Natural Gas Co. Construction Revision Date: Sept. 16,2024
Intermountain Gas Company OPSMOC-2266
Montana-Dakota Utilities Co. Page 12 of 32
Appendix 1 -CNG, MDU, and GPNG Transition Fitting Tracer Wire Configuration
CNG, MDU & GPNG TRANSITION FITTING MARKER
TEST STATION WITH PE TRACER WIRE ANODE
TEST HEAD DETAIL
PE TRACF
MARKER TEST STATION STEEL ItA..�
WITH TEST LEADS 0
ANODE `EAD
0 0 O
C
GRADE
a
PLACEMENT DETAIL
� J d
�] d
O �
! PE PIPE
6"
Min.
O
STEEL TRACE HARE O
.1 ANON
J J
TRACE HARE CONNECTION LUG ?E TRACE WRE
STEEL PF
ANODE
TRANSITION NON-CONTROLLABLE nTTINC
24
Alin.
POLICY STATEMENT OPS 307
Cascade Natural Gas Corporation Polyethylene(PE) Main and Service Status: Released
Great Plains Natural Gas Co. Construction Revision Date: Sept. 16,2024
Intermountain Gas Company OPSMOC-2266
Montana-Dakota Utilities Co. Page 13 of 32
Appendix 2—IGC Transition Fitting Tracer Wire Configuration
IGC STANDARD INSTALLATION FOR
STEEL TO PLASTIC TIE-IN WITH ANODE
WIRE COLORS
WHITE/RED: STEEL
YELLOW: PLASTIC
BLACK: ANODE
O WIRING MALONEY: OPTION #1 TEST POST
WIRE JUMPER TOP: STEEL LEAD'S
ON OUTSIDE MIDDLE: ANODE LEAD CONNECTED
ON INSIDE
BOTTOM: PLASTIC LEAD
WIRING MALONEY: OPTION #2
TOP: STEEL ANODE LEAD'S
O CONNECTED
ON INSIDE
BOTTOM: PLASTIC LEAD
GROUND LEVEL
ip 2 WIRE LEADS
"7 FROM STEEL
LOCATING WIRE
FOR PLASTIC
STEEL PIPE
PLASTIC PIPE
TRANSITION
FITTING
a
WIRE FROM ANODE
ANODE
POLICY STATEMENT OPS 307
Cascade Natural Gas Corporation Polyethylene(PE) Main and Service Status: Released
Great Plains Natural Gas Co. Construction Revision Date: Sept. 16,2024
Intermountain Gas Company OPSMOC-2266
Montana-Dakota Utilities Co. Page 14 of 32
Appendix 3—MDUG PE Service Line with Steel Main Wire Configuration
srwa.
Wrap wire around riser
Note: oo Nor BURY line shall be above final grade.
o,
�b
Tina/Drade rifle/Grade
1
Note: When an optional locate coupon is used, install theJW
locate coupon in /he some trench as the service line.
Donotallow the coupon to be in direct contact with
the onode/ess meter riser.Tracer wirer connection or exothermic weld
JTracer Wlre
Anode%ss� I!x
rS,A.ml
Svrvlce rronsNhn Tee Service Riser
o-iCe rN and Slow/to
Nc Trans/Non FJII/np soo'e ao.n .nr 4DU UTILITIES CROUPM-21Ch-h A 400 N 40,staN01lain D, STEEL TO P.E. SERWCE TRANSIMV rTMW AND
0noevnq NYTDo 6'339 TRACER WIRE CONN£CRON
POLICY STATEMENT OPS 307
Cascade Natural Gas Corporation Polyethylene(PE) Main and Service Status: Released
Great Plains Natural Gas Co. Construction Revision Date:Sept.16,2024
Intermountain Gas Company OPSMOC-2266
Montana-Dakota Utilities Co. Page 15 of 32
APPENDIX 4 - HORIZONTAL LOT SIDE
W/PRIMARY DISTRIBUTION
ELECTRIC FEEDER
COT SIDE STREET SIDE
DEPENDING ON UTILITIES 30%48" w
t-
- - O
z
WARNING TAPE--- __--__ w
w
WHEN REQUIRED = v
— — X
O
_ GAS COMMS ELEC,
Z =I 4"MIN. Utility
a 12"MIN FOR Owner Set
WASHINGTON I ELEC
r SEDER
12"
MIN.
NOTES:
1. NATIVE SOIL OR SELECTED BACKFILL.
2_ 6"OF ACCEPTABLE MATERIAL OR SAND AROUND PIPE WHERE
NECESSARY. IF DITCH WALL ADJACENT TO THE PIPE IS NOT
CLEAN AND FREE OF ROCKS OR OTHER HARD OBJECTS,
MAINTAIN 3'BETWEEN DITCH WALL AND EDGE OF PIPE.
3. D-P.REQUIRES 30"MINIMUM COVER(24"IN CONSOLIDATED
ROCK). H.P.REQUIRES ENGINEERING SERVICES OR SYSTEM
INTEGRITY APPROVAL AND 36"MINIMUM COVER_
Drawn: J WOKOJANCE Date:9127123
Engineer. DRAFTING SERVICES
GAS MAY BE PLACED ON A LEVEL ABOVE ALL OTHER UTILITIES Construction Services Approval:OPSMOC-1780
PROVIDED 12"VERTICAL SEPARATION IS MAINTAINED.
Drawing Name:JOINT&PROVIDED TRENCH
POLICY STATEMENT OPS 307
Cascade Natural Gas Corporation Polyethylene(PE) Main and Service Status: Released
Great Plains Natural Gas Co. Construction Revision Date:Sept.16,2024
Intermountain Gas Company OPSMOC-2266
Montana-Dakota Utilities Co. Page 16 of 32
APPENDIX 5 - STACKED STREET SIDE
STREET SIDE LOT SIDE
—I I—III—_ III I I III
— 24" —
___ WARNING TAPE
-I WHEN REQUIRED
4"MIN. ST LIGHT
_ 17 MIN FOR _
WASHINGrON _—
COMMS
z = GAS _ z
-
i
f
12"MIN.
or Utility Owner
set
NOTES:
1. NATIVE SOIL OR SELECTED BACKFILL.
2_ 6'OF ACCEPTABLE MATERIAL OR SAND AROUND PIPE WHERE
NECESSARY. IF DITCH WALL ADJACENT TO THE PIPE IS NOT
CLEAN AND FREE OF ROCKS OR OTHER HARD OBJECTS,
MAINTAIN W BETWEEN DITCH WALL AND EDGE OF PIPE.
3. D-P.REQUIRES 30"MINIMUM COVER(24"IN CONSOLIDATED
ROCK). H.P.REQUIRES ENGINEERING SERVICES OR SYSTEM
INTEGRITY APPROVAL AND 36"MINIMUM COVER.
Drawn: J WOKOJANCE Date:9127/23
Engineer. DRAFTING SERVICES
GAS MAY BE PLACED ON A LEVEL ABOVE ALL OTHER UTILITIES Construction Services Approval:OPSMOC-1780
PRO`IDED 12"VERTICAL SEPARATION IS MAINTAINED.
Drawing Name:JOINT&PROVIDED TRENCH
POLICY STATEMENT OPS 307
Cascade Natural Gas Corporation Polyethylene(PE) Main and Service Status: Released
Great Plains Natural Gas Co. Construction Revision Date: Sept. 16,2024
Intermountain Gas Company OPSMOC-2266
Montana-Dakota Utilities Co. Page 17 of 32
APPENDIX 6 - HORIZONTAL STREET SIDE
STREET SIDE LOT SIDE
_III III —1II II
lb I 36" -
-I I MIN.
WARNING TAPE WHEN REQUIRED
- ST LIGHT —
-
GAS —
ELEC .12
� —
-' I I III I I=1 I I I I=1 I I-
4"MIN. 12" 12"
12"MIN FOR or Utility Owner or Utility
WASHhGrCN Set Owner Set
12"
MIN
NOTES:
1. NATIVE SOIL OR SELECTED BACKFILL.
2. 6.OF ACCEPTABLE MATERIAL OR SAND AROUND PIPE WHERE
NECESSARY. IF DITCH WALL ADJACENT TO THE PIPE IS NOT
CLEAN AND FREE OF ROCKS OR OTHER HARD OBJECTS,
MAINTAIN 3'BETWEEN DITCH WALL AND EDGE OF PIPE.
3. D.P.REQUIRES 30"MINIMUM COVER(24"IN CONSOLIDATED
ROCK). H.P.REQUIRES ENGINEERING SERVICES OR SYSTEM
INTEGRITY APPROVAL AND 36"MINIMUM COVER.
Drawn: J WOKOJANCE Date:9/27/23
Engineer. DRAFTING SERVICES
GAS MAY BE PLACED ON A LEVEL ABOVE ALL OTHER UTILITIES Construction Services A royal:OPSMOC-1780
PROVIDED 12"VERTICAL SEPARATION IS MAINTAINED.
Drawing Name:JOINT&PROVIDED TRENCH
POLICY STATEMENT OPS 307
Cascade Natural Gas Corporation Polyethylene(PE) Main and Service Status: Released
Great Plains Natural Gas Co. Construction Revision Date:Sept.16,2024
Intermountain Gas Company OPSMOC-2266
Montana-Dakota Utilities Co. Page 18 of 32
APPENDIX 7 - STACKED LOT SIDE
LOT SIDE STREET SIDE
co Z
w
w
z o
J
WARNING TAPE Z
------- -------- ,
WHEN REQUIRED O
U
Z
GA S N
12 ! 3 {
0
g� COMMS
ELEC `
36"
NOTES-
1- NATIVE SOIL OR SELECTED BACKFILL.
2_ 6'OF ACCEPTABLE MATERIAL OR SAND AROUND PIPE WHERE
NECESSARY_ IF DITCH WALL ADJACENT TO THE PIPE IS NOT
CLEAN AND FREE OF ROCKS OR OTHER HARD OBJECTS,
MAINTAIN 3'BETWEEN DITCH WALL AND EDGE OF PIPE.
3. D-P.REQUIRES 30"MINIMUM COVER(24"IN CONSOLIDATED
ROCK). H.P_REQUIRES ENGINEERING SERVICES OR SYSTEM
INTEGRITY APPROVAL AND 36"MINIMUM COVER_
Drawn: J WOKOJANCE Date:9t27123
Engineer. DRAFTING SERVICES
GAS MAY BE PLACED ON A LEVEL ABOVE ALL OTHER UTILITIES Construction Services Approval:OPSMOC-1780
PROVIDED 12"VERTICAL SEPARATION IS MAINTAINED.
Drawing Name:JOINT&PROVIDED TRENCH
POLICY STATEMENT OPS 307
Cascade Natural Gas Corporation Polyethylene(PE) Main and Service Status: Released
Great Plains Natural Gas Co. Construction Revision Date:Sept.16,2024
Intermountain Gas Company OPSMOC-2266
Montana-Dakota Utilities Co. Page 19 of 32
APPENDIX 8 - STACKED STREET SIDE
STREET SIDE LOT SIDE
bo z
z o
z o
J
________ WARNING TAPE _ ______ M z
WHEN REQUIRED o
z
GAS N
1
z '
V g COMMS
ELEC
--
36"
NOTES:
1. NATIVE SOIL OR SELECTED BACKFILL.
2_ 6'OF ACCEPTABLE MATERIAL OR SAND AROUND PIPE WHERE
NECESSARY_ IF DITCH WALL ADJACENT TO THE PIPE IS NOT
CLEAN AND FREE OF ROCKS OR OTHER HARD OBJECTS,
MAINTAIN 3'BETWEEN DITCH WALL AND EDGE OF PIPE_
3. D-P.REQUIRES 30"MINIMUM COVER(24"IN CONSOLIDATED
ROCK). H.P_REQUIRES ENGINEERING SERVICES OR SYSTEM
INTEGRITY APPROVAL AND 36"MINIMUM COVER_
Drawn:J WOKOJANCE Date:9/27f23
Engineer: DRAFTING SERVICES
GAS MAY BE PLACED ON A LEVEL ABOVE ALL OTHER UTILITIES Construction Services Approval:OPSMOC-1780
PROVIDED 12"VERTICAL SEPARATION IS MAINTAINED.
Drawing Name:JOINT&PROVIDED TRENCH
POLICY STATEMENT OPS 307
Cascade Natural Gas Corporation Polyethylene(PE) Main and Service Status: Released
Great Plains Natural Gas Co. Construction Revision Date:Sept.16,2024
Intermountain Gas Company OPSMOC-2266
Montana-Dakota Utilities Co. Page 20 of 32
APPENDIX 9 - TRENCHED/ROCK SAW DITCH
TRENCH WIDTH MAY VARY
0
=1I =
___ WARNING TAPE ___
WHEN REQUIRED = 8
z a
N
= _ O
------------
a
__________.. O
Z u_
N _Z
ELEC
NOTES:
1. NATIVE SOIL OR SELECTED BACKFILL.
2. 6.OF ACCEPTABLE MATERIAL OR SAND AROUND PIPE WHERE
NECESSARY_ IF DITCH WALL ADJACENT TO THE PIPE IS NOT
CLEAN AND FREE OF ROCKS OR OTHER HARD OBJECTS,
MAINTAIN 3"BETWEEN DITCH WALL AND EDGE OF PIPE.
3. D.P.REQUIRES 30"MINIMUM COVER(24"IN CONSOLIDATED
ROCK). H.P_REQUIRES ENGINEERING SERVICES OR SYSTEM
INTEGRITY APPROVAL AND 36"MINIMUM COVER_
Drawn: J WOKOJANCE Date:9/2723
Engineer. DRAFTING SERVICES
GAS MAY BE PLACED ON A LEVEL ABOVE ALL OTHER UTILITIES Construction Services Approval:OPSMOC-1780
PROVIDED 12"VERTICAL SEPARATION IS MAINTAINED.
Drawing Name:JOINT&PROVIDED TRENCH
POLICY STATEMENT OPS 307
Cascade Natural Gas Corporation Polyethylene(PE) Main and Service Status: Released
Great Plains Natural Gas Co. Construction Revision Date: Sept. 16,2024
Intermountain Gas Company OPSMOC-2266
Montana-Dakota Utilities Co. Page 21 of 32
APPENDIX 10
Typical Gas Service Line joint trench including Gas,
secondary electric and Communications
Private Property ! Stacked
-�--
.� _ >
00 G $ j t
- Trench width to vary. a
N C �
:o
I I �
O
GAS I H
{
c
O
Z `
v 4"MIN. Ua1dy
12"MIN FOR
WAMNGTON 12"
NOTES- Min.
1. NATIVE SOIL OR SELECTED BACKFILL.
2- 6"OF ACCEPTABLE MATERIAL OR SAND AROUND PIPE WHERE
NECESSARY. IF DITCH WALL ADJACENT TO THE PIPE IS NOT
CLEAN AND FREE OF ROCKS OR OTHER HARD OBJECTS,
MAINTAIN 3"BETWEEN DITCH WALL AND EDGE OF PIPE.
3. 2"AND LARGER SERVICE TO BE INSTALLED AT MAIN DEPTH
REQUIREMENTS.EXCEPTION TO THIS STEP WOULD INCLUDE
AREAS NEAR THE RISER WHERE DEPTH MAY BE LESS THAN
MAIN DEPTH REQUIREMENTS DUE TO BURY LINE Drawn: J WOKOJANCE Date:9/27/23
REQUIREMENTS OF ANODELESS RISERS.
Engineer. DRAFTING SERVICES
GAS MAY BE PLACED ON A LEVEL ABOVE ALL OTHER UTILITIES Construction Services Approval:OPSMOC-1780
PROVIDED 12"VERTICAL SEPARATION IS MAINTAINED.
Drawing Name:JOINT&PROVIDED TRENCH
POLICY STATEMENT OPS 307
Cascade Natural Gas Corporation Polyethylene(PE) Main and Service Status: Released
Great Plains Natural Gas Co. Construction Revision Date:Sept.16,2024
Intermountain Gas Company OPSMOC-2266
Montana-Dakota Utilities Co. Page 22 of 32
APPENDIX 11
Typical Gas Service Line joint trench including Gas.
secondary electric and Communications
ROW ! Stacked
o
Trench width to vary .�.
• A•• •.g• • .•P'
GAS
COMMS ELEC 2
Z O
z —
v 4" MIN. utility
12"MIN FOR
WASHINGTON 12"
NOTES- Min-
1. NATIVE SOIL OR SELECTED BACKFILL.
2. 6-OF ACCEPTABLE MATERIAL OR SAND AROUND PIPE WHERE
NECESSARY. IF DITCH WALL ADJACENT TO THE PIPE IS NOT
CLEAN AND FREE OF ROCKS OR OTHER HARD OBJECTS.
MAINTAIN 3'BETWEEN DITCH WALL AND EDGE OF PIPE.
3. 2"AND LARGER SERVICE TO BE INSTALLED AT MAIN DEPTH
REQUIREMENTS.EXCEPTION TO THIS STEP WOULD INCLUDE
AREAS NEAR THE RISER WHERE DEPTH MAY BE LESS THAN
MAIN DEPTH REQUIREMENTS DUE TO BURY LINE Drawn: J'WOKOJANCE Date:9/27/23
REQUIREMENTS OF ANODELESS RISERS.
Engineer. DRAFTING SERVICES
GAS MAY BE PLACED ON A LEVEL ABOVE ALL OTHER UTILITIE Construction Services Approval:OPSMOC-1780
PROVIDED 12"VERTICAL SEPARATION IS MAINTAINED.
Drawing Name:JOINT&PROVIDED TRENCH
POLICY STATEMENT OPS 307
Cascade Natural Gas Corporation Polyethylene(PE) Main and Service Status: Released
Great Plains Natural Gas Co. Construction Revision Date: Sept. 16,2024
Intermountain Gas Company OPSMOC-2266
Montana-Dakota Utilities Co. Page 23 of 32
APPENDIX 12
Typical Gas Service Line joint trench including Gas,
secondary electric and Communications
Private Property i Horizontal
g
y I Q
Trench vlfidth to vary,' a)
• F
r•. J
SAS COMMS aEC w
4"MIN. Utility
17 MIN FOR
WASHINGTON 12"
NOTES- Min.
1. NATIVE SOIL OR SELECTED BACKFILL.
2_ 6"OF ACCEPTABLE MATERIAL OR SAND AROUND PIPE WHERE
NECESSARY. IF DITCH WALL ADJACENT TO THE PIPE IS NOT
CLEAN AND FREE OF ROCKS OR OTHER HARD OBJECTS,
MAINTAIN 3"BETWEEN DITCH WALL AND EDGE OF PIPE.
3. 2'AND LARGER SERVICE TO BE INSTALLED AT MAIN DEPTH
REQUIREMENTS.EXCEPTION TO THIS STEP WOULD INCLUDE
AREAS NEAR THE RISER WHERE DEPTH MAY BE LESS THAN
MAIN DEPTH REQUIREMENTS DUE TO BURY LINE Drawn: J WOKOJANCE Date:9127/23
REQUIREMENTS OF ANODELESS RISERS.
Engineer. DRAFTING SERVICES
GAS MAY BE PLACED ON A LEVEL ABOVE ALL OTHER UTILITIES Construction Services Approval:OPSMOC-1780
PROVIDED 12"VERTICAL SEPARATION IS MAINTAINED.
Drawing Name:JOINT&PROVIDED TRENCH
POLICY STATEMENT OPS 307
Cascade Natural Gas Corporation Polyethylene(PE) Main and Service Status: Released
Great Plains Natural Gas Co. Construction Revision Date:Sept.16,2024
Intermountain Gas Company OPSMOC-2266
Montana-Dakota Utilities Co. Page 24 of 32
APPENDIX 13
Typical Gas Service Line joint trench including Gas,
secondary electric and Communications
ROW/ Horizontal
�` i it �I`` . ''f: .� ' •''.
I . >
° 1 .. . a
N 0 I Trench width to vary )
� L
O
GAS`', COMMS aEC }
4"MIN. Utility
12"MIN FOR
WASHINGTON 12"
NOTES: Min.
1_ NATIVE SOIL OR SELECTED BACKFILL.
2_ 6"OF ACCEPTABLE MATERIAL OR SAND AROUND PIPE WHERE
NECESSARY, IF DITCH WALL ADJACENT TO THE PIPE IS NOT
CLEAN AND FREE OF ROCKS OR OTHER HARD OBJECTS,
MAINTAIN 3"BETWEEN DITCH WALL AND EDGE OF PIPE.
3. 2"AND LARGER SERVICE TO BE INSTALLED AT MAIN DEPTH
REQUIREMENTS.EXCEPTION TO THIS STEP WOULD INCLUDE
AREAS NEAR THE RISER WHERE DEPTH MAY BE LESS THAN
MAIN DEPTH REQUIREMENTS DUE TO BURY LINE Drawn: J WOKOJANCE Date:9l27123
REQUIREMENTS OF ANODELESS RISERS.
Engineer. DRAFTING SERVICES
GAS MAY BE PLACED ON A LEVEL ABOVE ALL OTHER UTILITIES Construction Services A royal:OPSMOC-1780
PROVIDED 12"VERTICAL SEPARATION IS MAINTAINED.
Drawing Name:JOINT&PROVIDED TRENCH
POLICY STATEMENT OPS 307
Cascade Natural Gas Corporation Polyethylene(PE) Main and Service Status: Released
Great Plains Natural Gas Co. Construction Revision Date:Sept.16,2024
Intermountain Gas Company OPSMOC-2266
Montana-Dakota Utilities Co. Page 25 of 32
APPENDIX 14
Typical Gas Service Line joint trench including Gas,
secondary electric and Communications
Private Property!Trenched 1 Rock Saw Ditch
1• I
ED
a
C
i
o C '
Trench width to vary O',
C4
Q�
� rV..
I o
I
COMMS pi
I )
ELEC
NOTES-
1- NATIVE SOIL OR SELECTED BACKFILL.
2. 6-OF ACCEPTABLE MATERIAL OR SAND AROUND PIPE WHERE
NECESSARY- IF DITCH WALL ADJACENT TO THE PIPE IS NOT
CLEAN AND FREE OF ROCKS OR OTHER HARD OBJECTS,
MAINTAIN 3"BETWEEN DITCH WALL AND EDGE OF PIPE.
3. 2"AND LARGER SERVICE TO BE INSTALLED AT MAIN DEPTH
REQUIREMENTS.EXCEPTION TO THIS STEP WOULD INCLUDE
AREAS NEAR THE RISER WHERE DEPTH MAY BE LESS THAN
MAIN DEPTH REQUIREMENTS DUE TO BURY LINE Drawn: J WOKOJANCE Date:9/27123
REQUIREMENTS OF ANODELESS RISERS.
Engineer. DRAFTING SERVICES
GAS MAY BE PLACED ON A LEVEL ABOVE ALL OTHER UTILITIES Construction Services Approval:OPSMOC-1780
PROVIDED 12"VERTICAL SEPARATION IS MAINTAINED.
Drawing Name:JOINT&PROVIDED TRENCH
POLICY STATEMENT OPS 307
Cascade Natural Gas Corporation Polyethylene(PE) Main and Service Status: Released
Great Plains Natural Gas Co. Construction Revision Date: Sept. 16,2024
Intermountain Gas Company OPSMOC-2266
Montana-Dakota Utilities Co. Page 26 of 32
APPENDIX 15
Typical Gas Service Line joint trench including Gas.
secondary electric and Communications
ROW 1 Trenched 1 Rock Saw Ditch
N Trench width to vary , o
Q
LL ;0 ��--
�_� L
0
COMMS
T
C
ELEC
NOTES-
1- NATIVE SOIL OR SELECTED BACKFILL.
2_ 6"OF ACCEPTABLE MATERIAL OR SAND AROUND PIPE WHERE
NECESSARY. IF DITCH WALL ADJACENT TO THE PIPE IS NOT
CLEAN AND FREE OF ROCKS OR OTHER HARD OBJECTS,
MAINTAIN 3"BETWEEN DITCH WALL AND EDGE OF PIPE_
3. 2"AND LARGER SERVICE TO BE INSTALLED AT MAIN DEPTH
REQUIREMENTS.EXCEPTION TO THIS STEP WOULD INCLUDE
AREAS NEAR THE RISER WHERE DEPTH MAY BE LESS THAN
MAIN DEPTH REQUIREMENTS DUE TO BURY LINE Drawn: J WOKOJANCE Date:9/27J23
REQUIREMENTS OF ANODELESS RISERS.
Engineer: DRAFTING SERVICES
GAS MAY BE PLACED ON A LEVEL ABOVE ALL OTHER UTILITIES Construction Services A roval:OPSMOC-1780
PROVIDED 12"VERTICAL SEPARATION IS MAINTAINED.
Drawing Name:JOINT&PROVIDED TRENCH
POLICY STATEMENT OPS 307
Cascade Natural Gas Corporation Polyethylene(PE) Main and Service Status: Released
Great Plains Natural Gas Co. Construction Revision Date:Sept.16,2024
Intermountain Gas Company OPSMOC-2266
Montana-Dakota Utilities Co. Page 27 of 32
EXHIBIT 1
Quality Inspection Protocol Checklist
OPS 307 Acceptance Criteria for Conforming Work Related
Section Quality
Protocol
2_1 a) Polyethylene (PE) pipe containing scratches exceeding 10% of wall QIP 024
thickness are not installed.
b Fittings or pipe containing creases or folds are not installed.
4_1 a) Area to be joined is cleaned inside and out with a clean, lint free QIP 040
Butt Fusion cloth.
4_1 a) From each pipe end, an area approximately 2 times the fitting length QIP 041
GFCP is cleaned with approved cleaning agent.
Coupling b After cleaning, no visible debris remains on the surfaces to be fused.
4.1 a) Fitting and area of pipe to be joined is cleaned with clean, lint free QIP 045
Socket cloth.
Fusion b) When contamination is present on pipe, it is cleaned with isopropyl
alcohol.
4.1 a) At the saddle tee installation location, an area of pipe approximately QIP 049
GFCP 3 times the fitting length is cleaned with approved cleaning agent.
Saddle Tee b After cleaning, no visible debris remains on the surfaces to be fused.
4.1 a) From each pipe end, an area approximately 2 times the fitting length QIP 051
Innogaz is cleaned with an isopropyl alcohol impregnated towel. QIP 052
b After cleaning, no visible debris remains on the surfaces to be fused.
4_3 a) When soap or water are used to clean pipe during cutting, pipe QIP 040
surface is cleaned with isopropyl alcohol before facing.
4_4 a) If drilling lubricants were used, the outside and inside diameter of QIP 040
the fusion area is cleaned using 90% or greater isopropyl alcohol. QIP 041
QIP 045
QIP 049
QIP 051
5_2 a) The qualified individual performs a visual inspection of the complete QIP 040
fusion joint. QIP 041
b) or c)A fusion joint deemed visually unacceptable is not placed into QIP 045
service. QIP 049
QIP 051
QIP 052
5.11 a) Chips (shavings)are removed with a clean, lint free cloth. QIP 040
Butt Fusion b) Pipe high/low alignment is checked.
c) If clamp adjustments are made after initial facing, pipe is refaced,
chips (shavings)are removed, and pipe high/low alignment is
checked.
a) Plates are clean. QIP 040
b) Nonstick coating is intact.
c) Temperature is between 400 -450°F.
a) The fusion joint is held under fusion force in the machine for a QIP 040
minimum of 30 seconds per inch of pipe diameter or until the pipe
surface is cool to the touch.
b) The fusion joint is not pressure tested, pulled, installed, or handled QIP 040
roughly for a minimum of 30 minutes after cooling.
5.11.8 Is contractor equipment being inspected? QIP 040
•Yes = inspect, No = proceed to next step.
POLICY STATEMENT OPS 307
Cascade Natural Gas Corporation Polyethylene(PE) Main and Service Status: Released
Great Plains Natural Gas Co. Construction Revision Date:Sept.16,2024
Intermountain Gas Company OPSMOC-2266
Montana-Dakota Utilities Co. Page 28 of 32
a A calibrated pyrometer is used to verify heater plate temperature.
5.12.1 Is ambient temperature below-10°F or above 120°F? QIP 041
•Yes = inspect, No = proceed to next step. QIP 049
a) Fitting is not installed. QIP 051
QIP 052
5.12 a Pipe ends are cutsquarely. QIP 041
GFCP b) Stab depth marks are present or reapplied after scraping. QIP 041
Coupling c Pipe is wiped clean with isopropyl alcohol.
a) Each end of the fitting is aligned with stab marks on the pipe. QIP 041
b) Fusion joint is secured in clamping device before fusion begins.
c) After the fusion cycle is complete, adhere to the manufacturers
cooling times before the joint is removed from the clamping device.
d) After the fusion cycle is complete, adhere to the manufacturers
cooling times before the joint is tapped or pressure tested.
Was the power interrupted during the fusion cycle? QIP 041
•Yes = inspect, No = proceed to next step.
a) The joint is allowed to cool to ambient temperature before
attempting to refuse.
b) Verify with pyrometer that fitting and surrounding pipe temperature
have equalized with pipe temperature at least 2 feet away from
fitting.
5.12 a) Fittings are only fused to Teel Plastics pipe OR gas piping systems QIP 045
Socket listed on the Performance Pipe Qualified Gas Distribution Piping
Fusion Systems document.
a) Ends are cut squarely, then cleaned inside and out. QIP 045
b) Chamfering is performed, and the rounding clamp is placed at the
bottom of the depth gauge.
a) Plates are cleaned with a clean, lint free cloth. QIP 045
b) Nonstick coating is intact.
c Tem erature is between 490 -510' F.
a) Pipe fusion area and fusion tools are shielded from wind, snow, QIP 045
blowing dust, and rain by using a canopy or similar device.
b) Pipe and fitting are pulled straight from the heating iron.
c) While joining, the fitting is held flush against the rounding clamp for
the appropriate cooling time.
d) Joint is allowed to cool an addition 5 minutes after cooling time,
before stressing joint.
5.12 a) Fusion joint is secured in clamping device before fusion begins. QIP 049
GFCP b) After the fusion cycle is complete, adhere to the manufacturers
Saddle Tee stated cooling times before the joint is removed from the clamping
device.
c) After the fusion cycle is complete, adhere to the manufacturers
stated cooling times before the joint is tapped or pressure tested.
Was the power interrupted during the fusion cycle? QIP 049
•Yes = inspect, No = proceed to next step.
a) The joint is allowed to cool to ambient temperature before
attempting to refuse.
b) Verify with pyrometer that fitting and surrounding pipe temperature
have equalized with pipe temperature at least 2 feet away from
fitting.
5.12 a Pipe ends are cutsquarely. QIP 051
b Stab depth marks are present or reapplied after scraping. QIP 051
POLICY STATEMENT OPS 307
Cascade Natural Gas Corporation Polyethylene(PE) Main and Service Status: Released
Great Plains Natural Gas Co. Construction Revision Date:Sept.16,2024
Intermountain Gas Company OPSMOC-2266
Montana-Dakota Utilities Co. Page 29 of 32
Innogaz a) Each end of the fitting is aligned with stab marks on the pipe. QIP 051
Coupling b) Fusion joint is secured in clamping device before fusion begins.
c) Cooling time indicated on the electrofusion processor has passed
before the joint is removed from the clamping device or pressure
tested.
Was the power interrupted during the fusion cycle? QIP 051
•Yes = inspect, No = proceed to next step.
a) Power failure occurs during the first 25% of the fusion time and the
joint is allowed to cool undisturbed for 1 hour before attempting to
refuse OR power failure occurs after the first 25% of the fusion time
and the joint is replaced.
b Pop-up indicators have risen OR fitting is replaced. QIP 051
5.12 a) Fusion joint is secured in clamping device before fusion begins. QIP 052
Innogaz b) Cooling time indicated on the electrofusion processor has passed
Saddle Tee before the joint is removed from the clamping device, tapped or
pressure tested.
Was the power interrupted during the fusion cycle? QIP 052
•Yes = inspect, No = proceed to next step.
a) Power failure occurs during the first 25% of the fusion time and the
joint is allowed to cool undisturbed for 1 hour before attempting to
refuse OR power failure occurs after the first 25% of the fusion time
and the joint is replaced.
b Pop-up indicator has risen OR fitting is replaced. QIP 052
5.12.2 a) A paint scraper is not used unless the working space is confined, QIP 041
requiring a hand tool. QIP 049
b) Sandpaper, utility/emery cloth, rasps, files, or abrasives/grinders are QIP 051
not used. QIP 052
5.12.3 a) An acceptable method is used to confirm removal of a minimum of QIP 041
.007" pipe material. QIP 049
QIP 051
QIP 052
5.13.1 a) Pipe end is cut squarely. QIP 048
Met Fit b No burrs are present.
Coupling a Stab depth is marked and measured on the pipe. QIP 048
a) The rings are bottomed out and past the locking grip. QIP 048
b Stab depth mark is visible.
5.16 (Washington) Is an underground structure present in a PE installation area? QIP 002
•Yes = inspect, No = proceed to next step. QIP 005
a) Pipe has a minimum separation of 6"when crossing non-electric QIP 006
utilities OR protective measures are used.
b) Pipe has a minimum separation of 12"when paralleling utilities OR
protective measures are used.
c) Pipe has a minimum separation of 12"when crossing electric OR
protective measures are used.
5.16 (States other than Washington) Is an underground structure present in a PE QIP 002
installation area? QIP 005
•Yes = inspect, No = proceed to next step. QIP 006
a) Pipe has a minimum separation of 4"when crossing or paralleling
underground non-electric utilities and structures OR protective
measures are used.
b) Pipe has a minimum separation of 12"when crossing or paralleling
electric OR protective measures are used.
POLICY STATEMENT OPS 307
Cascade Natural Gas Corporation Polyethylene(PE) Main and Service Status: Released
Great Plains Natural Gas Co. Construction Revision Date:Sept.16,2024
Intermountain Gas Company OPSMOC-2266
Montana-Dakota Utilities Co. Page 30 of 32
5.16.3 a Service lines are not installed in a bore with electric. QIP 007
5.17 a) Pipe is not installed within 10' of a system radiating temperatures QIP 005
above 1001F. QIP 006
5.22 a) Main is installed with a minimum cover of 54" in cultivated QIP 005
agricultural areas, 30" in soil, OR 24" in consolidated rock.
5.22 a) Ditch bottom provides uniform support with firm material for pipeline. QIP 008
b) Ditch bottom is clean and free of rocks or other hard objects OR 6"
of bedding material is laid before the pipe is placed.
c) Bedding material is either: Native material clean and free of rocks or
other hard objects; sand; or non-fractured gravel not exceeding 1/4"
minus in size.
5.22 a) Pipe is shaded with 6" of backfill material. QIP 008
b) Backfill material is either: Native material clean and free of rocks or
other hard objects; sand; or non-fractured gravel not exceeding 1/4"
minus in size.
5.22 a Final backfill does not contain trash or debris. QIP 008
5.22.9 Is the project in Oregon or upon completion of installation of underground QIP 161
facilities has Field Operations determined it to be necessary to mark
facilities?
•Yes = inspect, No = proceed to next step.
a Facilities are marked per the requirements of OPS 611.
5.23 Is the service line installed in soil? QIP 006
•Yes = inspect, No = proceed to next step.
a) Pipe smaller than 2" is installed with a minimum cover of 18"on
private property, 24" in the ROW unless a lesser minimum cover is
approved.
b) Pipe 2" and larger is installed with a minimum cover of 30", except
areas near the riser as required due to bury line requirements of
anodeless service risers.
c) Pipe is installed with a minimum cover of 54" in cultivated
agricultural areas unless a lesser minimum cover is approved.
5.23 Is the service line installed in consolidated rock? QIP 006
•Yes = inspect, No = proceed to next step.
a) Pipe smaller than 2" is installed with a minimum cover of 12"on
private property or 18" in the ROW, unless a lesser minimum cover
is approved.
b) Pipe 2" and larger is installed with a minimum cover of 24", unless a
lesser minimum cover is approved and/or except areas near the
riser as required due to bury line requirements of anodeless service
risers.
c) Pipe is installed with a minimum cover of 54" in cultivated
agricultural areas unless a lesser minimum cover is approved.
6 a) Tracer wire is not brazed or soldered. QIP 047
b Tracer wire is installed within approximately 6"of the pipe.
POLICY STATEMENT OPS 307
Cascade Natural Gas Corporation Polyethylene(PE) Main and Service Status: Released
Great Plains Natural Gas Co. Construction Revision Date:Sept.16,2024
Intermountain Gas Company OPSMOC-2266
Montana-Dakota Utilities Co. Page 31 of 32
ADMINISTRATION
The Vice President, Engineering &Operations Services of the MDU Utilities Group is responsible for
establishing this policy.Administration of this policy is the responsibility of the Director, Policy&
Procedures.
Reviewed: rrrEanaurrrvN -_ Approved:
Director, Polic`yF�mcedures Vice PresicTei�F
Engineering &Operations Services
Date: 7-12-24 Date: 7-15-24
REVISIONS
Major Revision Summary MOC Date
New integrated procedure. Replaced CNG CP 607, IGC OPSMOC-301 1/4/2022
4027, and MDU GDS Sec. 5
2023 Annual Procedure Review: Added QIP requested by
QMS. Added NESC recommendations. Align language with OPSMOC-1722 7/22/2024
OPS 306 and 308.
Minor Revision Summary MOC Date
Revised 5.16 to add minimum separation requirements in OPSMOC-1415 2/11/2022
Washington.
Add TR-33 note to section 5.11. N/A 8/23/2022
Language in section 5.4 has been edited to distinguish
between pipe larger than two inches (Section 5.4.1) and pipe OPSMOC-1540 10/4/2022
two inches and smaller(Section 5.4.2).
Change the discontinuance date for socket fusion and
sidewall heat fusion tapping tees in the areas they are OPSMOC-1707 11/23/2022
currently being used.
5.6. Plastic joining manuals, procedures, and specification
are available in the Guides & Resources section of the
MDUG Policy& Procedure SharePoint site. Contractors can OPSMOC-1820 2/15/2023
access manuals on the manufacturer's website. 5.6.1.
George Fischer Central Plastics Electrofusion Installation and
Training Manual. 5.6.2. Inno az Electrofusion System
POLICY STATEMENT OPS 307
Cascade Natural Gas Corporation Polyethylene(PE) Main and Service Status: Released
Great Plains Natural Gas Co. Construction Revision Date:Sept.16,2024
Intermountain Gas Company OPSMOC-2266
Montana-Dakota Utilities Co. Page 32 of 32
Installation Procedure. ***5.6.1. and 5.6.2. are linking to the
manufacturer's website.
Change the sunset date of the use of socket fusion, and OPSMOC-2059 1/4/2024
Constab mechanical fittings in section 5.3.2 & 5.23.3.
Implement Maximo/Locusview to document SSIP projects. OPSMOC-1814 5/13/2024
Removal of reference to use of saddle fusion fittings in OPSMOC-2113 5/31/2024
section 5.3.2.
Revised section 5.3. Clarification on Met-Fit and Continental OPSMOC-2266 9/16/2024
Stab Fittings.