Loading...
HomeMy WebLinkAboutI202301 LOC Idaho Public Utilities Commission Brad Little,Governor P.O. Box 83720, Boise, ID 83720.0074 Eric Anderson,President John R.Hammond,Jr.,Commissioner Edward Lodge,Commissioner Letter of Concern April 10, 2023 Report# I202301 Pat Darras—Vice President of Engineering & Operations Services Intermountain Gas Company 400 N 4th St. Bismarck, ND 58501 Dear Mr. Darras: On March 27-30, 2023, the Idaho Public Utilities Commission, Pipeline Safety Division, pursuant to Chapter 601 of Title 49, United States Code, conducted a Records inspection of Intermountain Gas Company (IGC). As a result of the inspection, it appears there are area(s) of concern that do not fully meet the intent of the pipeline safety regulations Title 49, Code of Federal Regulations, Part 192 for calendar year 2022. The item(s) listed below are of concern: 1. 49 CFR�192.605 Procedural manual for operations, maintenance, and emergencies. (a) General. Each operator shall prepare and follow for each pipeline, a manual of written procedures for conducting operations and maintenance activities and for emergency response. For transmission lines, the manual must also include procedures for handling abnormal operations. This manual must be reviewed and updated by the operator at intervals not exceeding 15 months,but at least once each calendar year. This manual must be prepared before operations of a pipeline system commence. Appropriate parts of the manual must be kept at locations where operations and maintenance activities are conducted. Finding(s)- Per IGC OPS 706 Leak Survey (1.1) Leak survey shall be documented in the Inspection and Survey application (e.g., IQGeo), except for unodorized lines and shorted casings which will be documented in PCAD. Prior to the implementation of OPS 402-Corrosion Control, shorted casings will be documented in legacy software applications. At a minimum, leak survey records shall contain the following information: (1.1.3) Survey Method. After viewing 2022 Leak Survey records, the Survey Method was not identified. 11331 W.Chinden Blvd.,Building 8 Suite 201-A,Boise ID 83714 Telephone:(208)334-0300 Facsimile:(208)334-3762 The above-mentioned item(s) were brought to the attention of IGC compliance representatives during the inspection. We would request that you review these matter(s) and respond in writing within 30 days regarding the above issue(s) including any planned corrective actions. If you have any questions concerning this notice, please contact me at (208) 334-0333. All written responses should be addressed to me at: 11331 W Chinden Blvd, Ste 201-A, Boise, Idaho 83714 or you can fax your response to (208) 334-3762. Because of the good faith that you have exhibited up to this time, we expect that you will take action to bring your program into compliance with pipeline safety regulations. We appreciate your attention to this matter and your effort to promote pipeline safety. Sincerely, Jeff Broo s Pipeline Safety, Program Manager Idaho Public Utility Commission